1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1131303 MGR.NO. 002 PAGE 001 CONT 6252 SEC 02 JOB 001 RES ENGR HERMAN, ROBERT PROJ RMC - 625202001 HWY US0087 40 CORPORATE WAY CUERO CNTY DEWITT DIST 13 CONTRACT PRICE $ 246,705.20 REPORT DATE 07/29/2014 14.21.39 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 014 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 17, 2013 TIME COMPUTED FROM JUN 17, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 85 379 32 347 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 14 1 1 TOTAL DAYS ALLOWED = 85 2 1 DATE WORK COMPLETED 3 1 WORK COMPLETED AND ACCEPTED DAYS CHARGED TO DATE = 34 4 1 WORK COMPLETED AND ACCEPTED ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED AND ACCEPTED LIQ DAMAGE RATE $ 590 6 1 WORK COMPLETED AND ACCEPTED 7 1 WORK COMPLETED AND ACCEPTED LIQUIDATED DAMAGES 8 1 WORK COMPLETED AND ACCEPTED 0 DAYS AT $ 590 PER DAY 9 1 WORK COMPLETED AND ACCEPTED TOTAL = $ .00 10 1 WORK COMPLETED AND ACCEPTED 11 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED AND ACCEPTED ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED AND ACCEPTED TO THE CONTRACTOR 14 1 WORK COMPLETED AND ACCEPTED 15 1 WORK COMPLETED AND ACCEPTED 16 1 WORK COMPLETED AND ACCEPTED ---------------------------- 17 1 WORK COMPLETED AND ACCEPTED AREA/PROJECT ENGINEER 18 1 WORK COMPLETED AND ACCEPTED 19 1 WORK COMPLETED AND ACCEPTED 20 1 WORK COMPLETED AND ACCEPTED 21 1 WORK COMPLETED AND ACCEPTED 22 1 WORK COMPLETED AND ACCEPTED 23 1 WORK COMPLETED AND ACCEPTED 24 1 WORK COMPLETED AND ACCEPTED 25 1 WORK COMPLETED AND ACCEPTED 26 1 WORK COMPLETED AND ACCEPTED 27 1 WORK COMPLETED AND ACCEPTED 28 1 WORK COMPLETED AND ACCEPTED 29 1 WORK COMPLETED AND ACCEPTED 30 1 WORK COMPLETED AND ACCEPTED 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 410 34 376 0 SATURDAY 0 SUNDAY 0 HOLIDAY 29 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1131303 MGR.NO. 002 PAGE 001 CONT 6252 SEC 02 JOB 001 RES ENGR HERMAN, ROBERT PROJ RMC - 625202001 HWY US0087 40 CORPORATE WAY CUERO CNTY DEWITT DIST 13 CONTRACT PRICE $ 246,705.20 REPORT DATE 07/29/2014 14.21.39 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 014 DIST. 13 COUNTY DEWITT CONTROL 6252-02-001 PROJECT RMC - 625202001 HIGHWAY US0087 0LIMITS- VARIOUS . 0TYPE OF WORK- MOWING HIGHWAY RIGHTS OF WAY 0 0050 MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY DISTRICT MAINTENANCE 10/2012 0 0075 0730 FULL-WIDTH MOWING AC 11,480.000 8,810.000 21.490 189,326.90 0 SUBTOTAL BID ITEMS $ 189,326.90 0 TOTAL AMOUNT WORK DONE MOWING $ 189,326.90 0 TOTAL AMOUNT WORK DONE CONTROL 6252-02-001 $ 189,326.90 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1131303 MGR.NO. 002 PAGE 001 CONT 6252 SEC 02 JOB 001 RES ENGR HERMAN, ROBERT PROJ RMC - 625202001 HWY US0087 40 CORPORATE WAY CUERO CNTY DEWITT DIST 13 CONTRACT PRICE $ 246,705.20 REPORT DATE 07/29/2014 14.21.39 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 014 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUN 17, 2013 WORKING DAYS USED 34 PERCENT COMPLETE 76.74 PERCENT TIME USED 40.00 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6252-02-001 RMC - 625202001 13 US0087 DEWITT - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 11,480.000 8,810.000 21.490 189,326.90 0 SUBTOTAL BID ITEMS $ 189,326.90 0 CONTRACT TOTAL ALL ITEMS $ 189,326.90 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1131303 MGR.NO. 002 PAGE 001 CONT 6252 SEC 02 JOB 001 RES ENGR HERMAN, ROBERT PROJ RMC - 625202001 HWY US0087 40 CORPORATE WAY CUERO CNTY DEWITT DIST 13 CONTRACT PRICE $ 246,705.20 REPORT DATE 07/29/2014 14.21.39 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 014 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 62 RMC - 625202001 6252-02-001 189,326.90 .00 189,326.90 .00 .00 189,326.90 176,991.64 12,335.26 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 189,326.90 .00 189,326.90 .00 .00 189,326.90 176,991.64 12,335.26 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1131303 MGR.NO. 002 PAGE 001 CONT 6252 SEC 02 JOB 001 RES ENGR HERMAN, ROBERT PROJ RMC - 625202001 HWY US0087 40 CORPORATE WAY CUERO CNTY DEWITT DIST 13 CONTRACT PRICE $ 246,705.20 REPORT DATE 07/29/2014 14.21.39 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 014 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6252-02-001 RMC - 625202001 13 US0087 DEWITT -LIMITS - VARIOUS . LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0730 FULL-WIDTH MOWING AC 11,480.000 574.000 21.490 12,335.26 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 12,335.26 0 TOTAL AMOUNT WORK DONE TO DATE - $ 189,326.90