1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5121331 MGR.NO. 059 PAGE 001 CONT 6239 SEC 29 JOB 001 RES ENGR PYATT, NED PROJ SUP - 623929001 HWY US0059 11401 US 59 VICTORIA CNTY VICTORIA DIST 13 CONTRACT PRICE $ 110,313.72 REPORT DATE 05/06/2013 11.22.11 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 WORLD TECHNICAL SERVICES, INC. 09518 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 01, 2012 TIME COMPUTED FROM JUN 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 304 304 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 334 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 334 334 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5121331 MGR.NO. 059 PAGE 001 CONT 6239 SEC 29 JOB 001 RES ENGR PYATT, NED PROJ SUP - 623929001 HWY US0059 11401 US 59 VICTORIA CNTY VICTORIA DIST 13 CONTRACT PRICE $ 110,313.72 REPORT DATE 05/06/2013 11.22.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 WORLD TECHNICAL SERVICES, INC. 09518 DIST. 13 COUNTY VICTORIA CONTROL 6239-29-001 PROJECT SUP - 623929001 HIGHWAY US0059 0LIMITS- US 59 US 77 0TYPE OF WORK- RUBBER LITTER PICKUP (STATE USE PROGRAM) 0 0050 RUBBER LITTER NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY DISTRICT 4/26/2012 0 0075 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (1) CYC 178.000 75.000 163.380 12,253.50 0080 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (2) CYC 178.000 75.000 95.780 7,183.50 0085 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (3) CYC 178.000 75.000 11.270 845.25 0090 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (4) CYC 178.000 71.000 129.580 9,200.18 0095 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (5) CYC 178.000 69.000 219.730 15,161.37 0 SUBTOTAL BID ITEMS $ 44,643.80 0 TOTAL AMOUNT WORK DONE RUBBER LITTER $ 44,643.80 0 TOTAL AMOUNT WORK DONE CONTROL 6239-29-001 $ 44,643.80 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5121331 MGR.NO. 059 PAGE 001 CONT 6239 SEC 29 JOB 001 RES ENGR PYATT, NED PROJ SUP - 623929001 HWY US0059 11401 US 59 VICTORIA CNTY VICTORIA DIST 13 CONTRACT PRICE $ 110,313.72 REPORT DATE 05/06/2013 11.22.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 WORLD TECHNICAL SERVICES, INC. 09518 0*********************************************************************************************************************************** -LIMITS - US 59 0 US 77 DATE WORK BEGAN JUN 1 , 2012 WORKING DAYS USED 334 PERCENT COMPLETE 40.46 PERCENT TIME USED 45.70 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6239-29-001 SUP - 623929001 13 US0059 VICTORIA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (1) CYC 178.000 75.000 163.380 12,253.50 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (2) CYC 178.000 75.000 95.780 7,183.50 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (3) CYC 178.000 75.000 11.270 845.25 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (4) CYC 178.000 71.000 129.580 9,200.18 0735 DEBRIS-CNTR MEDIANS/MAINLANES-AREA (5) CYC 178.000 69.000 219.730 15,161.37 0 SUBTOTAL BID ITEMS $ 44,643.80 0 CONTRACT TOTAL ALL ITEMS $ 44,643.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5121331 MGR.NO. 059 PAGE 001 CONT 6239 SEC 29 JOB 001 RES ENGR PYATT, NED PROJ SUP - 623929001 HWY US0059 11401 US 59 VICTORIA CNTY VICTORIA DIST 13 CONTRACT PRICE $ 110,313.72 REPORT DATE 05/06/2013 11.22.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 235 SUP - 623929001 6239-29-001 44,643.80 .00 44,643.80 .00 .00 44,643.80 39,066.14 5,577.66 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 44,643.80 .00 44,643.80 .00 .00 44,643.80 39,066.14 5,577.66 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5121331 MGR.NO. 059 PAGE 001 CONT 6239 SEC 29 JOB 001 RES ENGR PYATT, NED PROJ SUP - 623929001 HWY US0059 11401 US 59 VICTORIA CNTY VICTORIA DIST 13 CONTRACT PRICE $ 110,313.72 REPORT DATE 05/06/2013 11.22.13 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6239-29-001 SUP - 623929001 13 US0059 VICTORIA -LIMITS - US 59 US 77 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0735 DEBRIS-CNTR CYC 178.000 9.000 163.380 1,470.42 MEDIANS/MAINLANES-AREA (1) 80 0735 DEBRIS-CNTR CYC 178.000 9.000 95.780 862.02 MEDIANS/MAINLANES-AREA (2) 85 0735 DEBRIS-CNTR CYC 178.000 9.000 11.270 101.43 MEDIANS/MAINLANES-AREA (3) 90 0735 DEBRIS-CNTR CYC 178.000 9.000 129.580 1,166.22 MEDIANS/MAINLANES-AREA (4) 95 0735 DEBRIS-CNTR CYC 178.000 9.000 219.730 1,977.57 MEDIANS/MAINLANES-AREA (5) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 5,577.66 0 TOTAL AMOUNT WORK DONE TO DATE - $ 44,643.80