1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4120331 MGR.NO. 010 PAGE 001 CONT 6241 SEC 53 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 624153001 HWY FM0369 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 69,500.16 REPORT DATE 05/03/2013 11.37.02 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 013 WORK SERVICES CORPORATION 11541 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 01, 2012 TIME COMPUTED FROM APR 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 365 365 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 395 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 395 395 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4120331 MGR.NO. 010 PAGE 001 CONT 6241 SEC 53 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 624153001 HWY FM0369 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 69,500.16 REPORT DATE 05/03/2013 11.37.03 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 013 WORK SERVICES CORPORATION 11541 DIST. 03 COUNTY WICHITA CONTROL 6241-53-001 PROJECT SUP - 624153001 HIGHWAY FM0369 0LIMITS- WICHITA FALLS DISTRICT COMPLEX 0TYPE OF WORK- JANITORIAL MAINTENANCE 0 0005 PREPARED BY SS 0 0055 JANITORIAL MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7206 JANITORIAL MAINTENANCE MO 24.000 13.000 2,895.840 37,645.92 0 SUBTOTAL BID ITEMS $ 37,645.92 0 TOTAL AMOUNT WORK DONE JANITORIAL MAINTENANCE $ 37,645.92 0 TOTAL AMOUNT WORK DONE CONTROL 6241-53-001 $ 37,645.92 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4120331 MGR.NO. 010 PAGE 001 CONT 6241 SEC 53 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 624153001 HWY FM0369 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 69,500.16 REPORT DATE 05/03/2013 11.37.03 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 013 WORK SERVICES CORPORATION 11541 0*********************************************************************************************************************************** -LIMITS - WICHITA FALLS 0 DISTRICT COMPLEX DATE WORK BEGAN APR 1 , 2012 WORKING DAYS USED 395 PERCENT COMPLETE 54.16 PERCENT TIME USED 54.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6241-53-001 SUP - 624153001 03 FM0369 WICHITA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7206 JANITORIAL MAINTENANCE MO 24.000 13.000 2,895.840 37,645.92 0 SUBTOTAL BID ITEMS $ 37,645.92 0 CONTRACT TOTAL ALL ITEMS $ 37,645.92 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4120331 MGR.NO. 010 PAGE 001 CONT 6241 SEC 53 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 624153001 HWY FM0369 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 69,500.16 REPORT DATE 05/03/2013 11.37.03 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 013 WORK SERVICES CORPORATION 11541 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 243 SUP - 624153001 6241-53-001 37,645.92 .00 37,645.92 .00 .00 37,645.92 34,750.08 2,895.84 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 37,645.92 .00 37,645.92 .00 .00 37,645.92 34,750.08 2,895.84 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4120331 MGR.NO. 010 PAGE 001 CONT 6241 SEC 53 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 624153001 HWY FM0369 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 69,500.16 REPORT DATE 05/03/2013 11.37.04 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 013 WORK SERVICES CORPORATION 11541 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6241-53-001 SUP - 624153001 03 FM0369 WICHITA -LIMITS - WICHITA FALLS DISTRICT COMPLEX LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 7206 JANITORIAL MAINTENANCE MO 24.000 1.000 2,895.840 2,895.84 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 2,895.84 0 TOTAL AMOUNT WORK DONE TO DATE - $ 37,645.92