1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11110303 MGR.NO. 010 PAGE 001 CONT 6235 SEC 78 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 623578001 HWY US0281 1601 SOUTHWEST PKWY WICHI CNTY ARCHER DIST 03 CONTRACT PRICE $ 249,775.00 REPORT DATE 04/18/2012 15.59.41 CONTRACTOR TEXAS ROAD MAINTENANCE 14136 EST PERIOD FEB 06,2012 TO APR 01,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 06, 2012 TIME COMPUTED FROM FEB 13, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 49 55 27 28 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 12 1 1 WORK COMPLETED AND ACCEPTED TOTAL DAYS ALLOWED = 49 DATE WORK COMPLETED 04/01/12 DAYS CHARGED TO DATE = 27 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 56 27 29 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11110303 MGR.NO. 010 PAGE 001 CONT 6235 SEC 78 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 623578001 HWY US0281 1601 SOUTHWEST PKWY WICHI CNTY ARCHER DIST 03 CONTRACT PRICE $ 249,775.00 REPORT DATE 04/18/2012 15.59.41 CONTRACTOR TEXAS ROAD MAINTENANCE 14136 EST PERIOD FEB 06,2012 TO APR 01,2012 EST NO 003 & FINAL DIST. 03 COUNTY ARCHER CONTROL 6235-78-001 PROJECT RMC - 623578001 HIGHWAY US0281 0LIMITS- VARIOUS ROADWAYS IN ARCHER YOUNG AND THROCKMORTON COUNTY 0TYPE OF WORK- CRACK SEAL - HOT 0 0005 CRACK SEAL - HOT 0 0055 PREPARED BY THOMAS G ALLBRITTON PE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 485.000 735.800 515.000 378,937.00 0 SUBTOTAL BID ITEMS $ 378,937.00 0 TOTAL AMOUNT WORK DONE PREPARED BY THOMAS G ALLBRITTON PE $ 378,937.00 0 TOTAL AMOUNT WORK DONE CONTROL 6235-78-001 $ 378,937.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11110303 MGR.NO. 010 PAGE 001 CONT 6235 SEC 78 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 623578001 HWY US0281 1601 SOUTHWEST PKWY WICHI CNTY ARCHER DIST 03 CONTRACT PRICE $ 249,775.00 REPORT DATE 04/18/2012 15.59.41 CONTRACTOR TEXAS ROAD MAINTENANCE 14136 EST PERIOD FEB 06,2012 TO APR 01,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN ARCHER 0 YOUNG AND THROCKMORTON COUNTY DATE WORK BEGAN FEB 6 , 2012 WORKING DAYS USED 27 PERCENT COMPLETE 100.00 PERCENT TIME USED 55.10 DATE COMPLETED APR 1 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6235-78-001 RMC - 623578001 03 US0281 ARCHER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 485.000 735.800 515.000 378,937.00 0 SUBTOTAL BID ITEMS $ 378,937.00 0 CONTRACT TOTAL ALL ITEMS $ 378,937.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11110303 MGR.NO. 010 PAGE 001 CONT 6235 SEC 78 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 623578001 HWY US0281 1601 SOUTHWEST PKWY WICHI CNTY ARCHER DIST 03 CONTRACT PRICE $ 249,775.00 REPORT DATE 04/18/2012 15.59.41 CONTRACTOR TEXAS ROAD MAINTENANCE 14136 EST PERIOD FEB 06,2012 TO APR 01,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 5 RMC - 623578001 6235-78-001 378,937.00 .00 378,937.00 .00 .00 378,937.00 378,937.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 378,937.00 .00 378,937.00 .00 .00 378,937.00 378,937.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11110303 MGR.NO. 010 PAGE 001 CONT 6235 SEC 78 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 623578001 HWY US0281 1601 SOUTHWEST PKWY WICHI CNTY ARCHER DIST 03 CONTRACT PRICE $ 249,775.00 REPORT DATE 04/18/2012 15.59.42 CONTRACTOR TEXAS ROAD MAINTENANCE 14136 EST PERIOD FEB 06,2012 TO APR 01,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6235-78-001 RMC - 623578001 03 US0281 ARCHER -LIMITS - VARIOUS ROADWAYS IN ARCHER YOUNG AND THROCKMORTON COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 378,937.00