1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11100302 MGR.NO. 010 PAGE 001 CONT 6214 SEC 16 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 621416001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 158,734.40 REPORT DATE 05/09/2012 09.00.12 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD MAR 21,2011 TO APR 30,2012 EST NO 014 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 21, 2011 TIME COMPUTED FROM MAR 28, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 377 370 7 BROUGHT FORWARD ADDL DAYS GRANTED = 45 APR 12 1 1 TOTAL DAYS ALLOWED = 410 2 1 DATE WORK COMPLETED 04/30/12 3 1 DAYS CHARGED TO DATE = 400 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 407 400 7 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11100302 MGR.NO. 010 PAGE 001 CONT 6214 SEC 16 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 621416001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 158,734.40 REPORT DATE 05/09/2012 09.00.14 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD MAR 21,2011 TO APR 30,2012 EST NO 014 & FINAL DIST. 03 COUNTY WICHITA CONTROL 6214-16-001 PROJECT RMC - 621416001 HIGHWAY IH0044 0LIMITS- VARIOUS LOCATION IN WICHITA & WILBARGER COUNTIES 0TYPE OF WORK- ROUTINE STREET SWEEPING & DEBRIS REMOVAL 0 0005 PREPARED BY LARRY TEGTMEYER, P.E. 0 0055 ROUTINE ST.SWEEPING/DEBRI REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0735 DEBRIS REMOVAL (SPOT DEBRIS) MI 50.000 32.000 1.000 32.00 0065 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 451.800 450.700 100.000 45,070.00 0070 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 474.600 470.200 100.000 47,020.00 0075 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 444.000 441.700 140.000 61,838.00 0080 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 27.210 29.970 140.000 4,195.80 0085 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 50.000 12.000 1.000 12.00 0090 0738 CLEANING/SWEEPING (SPOT) MI 25.000 0.000 1.000 .00 0200 9000*CLEANING/SWEEPING-CENTER MEDIAN (2) MI 24.700 24.700 250.000 6,175.00 0205 9000*CLEANING/SWEEPING-OUTSIDE MAIN LANES(2) MI 26.600 26.600 250.000 6,650.00 0210 9000*CLEANING/SWEEPING-FRONTAGE RD (2) MI 0.600 0.600 250.000 150.00 0215 9000*CLEANING/SWEEPING-ENTR/EXIT RAMP (2) MI 0.900 0.900 250.000 225.00 0 SUBTOTAL BID ITEMS $ 171,367.80 0 TOTAL AMOUNT WORK DONE ROUTINE ST.SWEEPING/DEBRI REMOVAL $ 171,367.80 0 TOTAL AMOUNT WORK DONE CONTROL 6214-16-001 $ 171,367.80 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11100302 MGR.NO. 010 PAGE 001 CONT 6214 SEC 16 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 621416001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 158,734.40 REPORT DATE 05/09/2012 09.00.15 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD MAR 21,2011 TO APR 30,2012 EST NO 014 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATION IN 0 WICHITA & WILBARGER COUNTIES DATE WORK BEGAN MAR 21, 2011 WORKING DAYS USED 400 PERCENT COMPLETE 100.00 PERCENT TIME USED 97.50 DATE COMPLETED APR 30 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6214-16-001 RMC - 621416001 03 IH0044 WICHITA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0735 DEBRIS REMOVAL (SPOT DEBRIS) MI 50.000 32.000 1.000 32.00 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 451.800 450.700 100.000 45,070.00 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 474.600 470.200 100.000 47,020.00 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 444.000 441.700 140.000 61,838.00 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 27.210 29.970 140.000 4,195.80 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 50.000 12.000 1.000 12.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* CLEANING/SWEEPING-CENTER MEDIAN (2) MI 24.700 24.700 250.000 6,175.00 9000* CLEANING/SWEEPING-OUTSIDE MAIN LANES(2) MI 26.600 26.600 250.000 6,650.00 9000* CLEANING/SWEEPING-FRONTAGE RD (2) MI 0.600 .600 250.000 150.00 9000* CLEANING/SWEEPING-ENTR/EXIT RAMP (2) MI .900 .900 250.000 225.00 0 SUBTOTAL BID ITEMS $ 171,367.80 1 CONTRACT TOTAL ALL ITEMS $ 171,367.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11100302 MGR.NO. 010 PAGE 001 CONT 6214 SEC 16 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 621416001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 158,734.40 REPORT DATE 05/09/2012 09.00.15 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD MAR 21,2011 TO APR 30,2012 EST NO 014 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 243 RMC - 621416001 6214-16-001 171,367.80 .00 171,367.80 .00 .00 171,367.80 163,292.80 8,075.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 171,367.80 .00 171,367.80 .00 .00 171,367.80 163,292.80 8,075.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11100302 MGR.NO. 010 PAGE 001 CONT 6214 SEC 16 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 621416001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 158,734.40 REPORT DATE 05/09/2012 09.00.16 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD MAR 21,2011 TO APR 30,2012 EST NO 014 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6214-16-001 RMC - 621416001 03 IH0044 WICHITA -LIMITS - VARIOUS LOCATION IN WICHITA & WILBARGER COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) - * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 200 9000* CLEANING/SWEEPING-CENTER MI 0.000 15.100 250.000 3,775.00 MEDIAN (2) 205 9000* CLEANING/SWEEPING-OUTSIDE MI 0.000 16.300 250.000 4,075.00 MAIN LANES(2) 210 9000* CLEANING/SWEEPING-FRONTAGE MI 0.000 0.600 250.000 150.00 RD (2) 215 9000* CLEANING/SWEEPING-ENTR/EXIT MI 0.000 0.300 250.000 75.00 RAMP (2) 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 8,075.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 171,367.80