1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5094001 MGR.NO. 010 PAGE 001 CONT 6193 SEC 81 JOB 001 RES ENGR BROWN, MONTY PROJ RMC - 619381001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 369,006.57 REPORT DATE 09/22/2009 16.52.45 CONTRACTOR WINDING ROAD CONSTRUCTION, EST PERIOD JUL 20,2009 TO SEP 04,2009 EST NO 003 & FINAL INC. 13054 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 20, 2009 TIME COMPUTED FROM JUL 27, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 50 43 25 18 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 09 1 1 TOTAL DAYS ALLOWED = 50 2 1 DATE WORK COMPLETED 09/04/09 3 1 WORK COMPLETED DAYS CHARGED TO DATE = 27 4 1 WORK COMPLETED AND ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 47 27 20 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5094001 MGR.NO. 010 PAGE 001 CONT 6193 SEC 81 JOB 001 RES ENGR BROWN, MONTY PROJ RMC - 619381001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 369,006.57 REPORT DATE 09/22/2009 16.52.46 CONTRACTOR WINDING ROAD CONSTRUCTION, EST PERIOD JUL 20,2009 TO SEP 04,2009 EST NO 003 & FINAL INC. 13054 DIST. 03 COUNTY WICHITA CONTROL 6193-81-001 PROJECT RMC - 619381001 HIGHWAY IH0044 0LIMITS- VARIOUS LOCATIONS IN WICHITA & CLAY COUNTIES 0TYPE OF WORK- REPAIR CONCRETE PAVE & BRIDGE APPROACH 0 0005 PREPARED BY MONTY BROWN, P.E. 0 0055 REPAIF CONC PAVE & BRIDGE APPROACH NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0104 REMOVING CONC (APPR SLAB) SY 170.670 170.670 15.000 2,560.05 0065 0105 REMOVING STAB BASE AND ASPH PAV (2") SY 1,011.110 1,473.310 5.000 7,366.55 0070 0361 FULL-DEPTH REPAIR CRCP (8") SY 2,171.110 2,251.686 73.000 164,373.08 0075 0361 FULL-DEPTH REPAIR CPCD (8") SY 401.780 873.240 76.000 66,366.24 0080 0361 FULL-DEPTH REPAIR CPCD (10") SY 921.330 922.600 112.000 103,331.20 0085 0420 CL S CONC (APPR SLAB) CY 61.630 61.630 420.000 25,884.60 0090 0500 MOBILIZATION LS 1.000 1.000 22,000.000 22,000.00 0095 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 2,500.000 7,500.00 0100 0662 WK ZN PAV MRK SHT TERM (TAB) TY W EA 56.000 0.000 10.000 .00 0105 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 291.000 0.000 3.300 .00 0110 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 1,088.000 0.000 3.300 .00 0115 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 50.000 0.000 4.000 .00 0120 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 1,088.000 0.000 3.300 .00 0125 0666 PAVEMENT SEALER 4" LF 2,325.000 0.000 2.000 .00 0130 0666 PAVEMENT SEALER 8" LF 50.000 0.000 2.000 .00 0135 0672 REFL PAV MRKR TY II-C-R EA 14.000 0.000 10.000 .00 0 SUBTOTAL BID ITEMS $ 399,381.72 0 TOTAL AMOUNT WORK DONE REPAIF CONC PAVE & BRIDGE APPROACH $ 399,381.72 1 TOTAL AMOUNT WORK DONE CONTROL 6193-81-001 $ 399,381.72 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5094001 MGR.NO. 010 PAGE 001 CONT 6193 SEC 81 JOB 001 RES ENGR BROWN, MONTY PROJ RMC - 619381001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 369,006.57 REPORT DATE 09/22/2009 16.52.46 CONTRACTOR WINDING ROAD CONSTRUCTION, EST PERIOD JUL 20,2009 TO SEP 04,2009 EST NO 003 & FINAL INC. 13054 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN 0 WICHITA & CLAY COUNTIES DATE WORK BEGAN JUL 20, 2009 WORKING DAYS USED 27 PERCENT COMPLETE 100.00 PERCENT TIME USED 54.00 DATE COMPLETED SEP 4 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6193-81-001 RMC - 619381001 03 IH0044 WICHITA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (APPR SLAB) SY 170.670 170.670 15.000 2,560.05 0105 REMOVING STAB BASE AND ASPH PAV (2") SY 1,011.110 1,473.310 5.000 7,366.55 0361 FULL-DEPTH REPAIR CRCP (8") SY 2,171.110 2,251.686 73.000 164,373.08 0361 FULL-DEPTH REPAIR CPCD (8") SY 401.780 873.240 76.000 66,366.24 0361 FULL-DEPTH REPAIR CPCD (10") SY 921.330 922.600 112.000 103,331.20 0420 CL S CONC (APPR SLAB) CY 61.630 61.630 420.000 25,884.60 0500 MOBILIZATION LS 1.000 1.000 22,000.000 22,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 2,500.000 7,500.00 0 SUBTOTAL BID ITEMS $ 399,381.72 0 CONTRACT TOTAL ALL ITEMS $ 399,381.72 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5094001 MGR.NO. 010 PAGE 001 CONT 6193 SEC 81 JOB 001 RES ENGR BROWN, MONTY PROJ RMC - 619381001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 369,006.57 REPORT DATE 09/22/2009 16.52.46 CONTRACTOR WINDING ROAD CONSTRUCTION, EST PERIOD JUL 20,2009 TO SEP 04,2009 EST NO 003 & FINAL INC. 13054 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 243 RMC - 619381001 6193-81-001 399,381.72 .00 399,381.72 .00 .00 399,381.72 388,209.52 11,172.20 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 399,381.72 .00 399,381.72 .00 .00 399,381.72 388,209.52 11,172.20 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5094001 MGR.NO. 010 PAGE 001 CONT 6193 SEC 81 JOB 001 RES ENGR BROWN, MONTY PROJ RMC - 619381001 HWY IH0044 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 369,006.57 REPORT DATE 09/22/2009 16.52.46 CONTRACTOR WINDING ROAD CONSTRUCTION, EST PERIOD JUL 20,2009 TO SEP 04,2009 EST NO 003 & FINAL INC. 13054 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6193-81-001 RMC - 619381001 03 IH0044 WICHITA -LIMITS - VARIOUS LOCATIONS IN WICHITA & CLAY COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 85 0420 CL S CONC (APPR SLAB) CY 61.630 15.410 420.000 6,472.20 90 0500 MOBILIZATION LS 1.000 0.100 22,000.000 2,200.00 95 0502 BARRICADES, SIGNS AND MO 3.000 1.000 2,500.000 2,500.00 TRAFFIC HANDLING --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 11,172.20 0 TOTAL AMOUNT WORK DONE TO DATE - $ 399,381.72