1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1090313 MGR.NO. 010 PAGE 001 CONT 6189 SEC 85 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618985001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 102,951.78 REPORT DATE 09/09/2009 16.55.36 CONTRACTOR BILLY BENSON 8947 EST PERIOD AUG 01,2009 TO AUG 31,2009 EST NO 004 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAY 20, 2009 TIME COMPUTED FROM MAY 26, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 57 73 11 62 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 TIME SUSP - LETTER SUBMITTED TOTAL DAYS ALLOWED = 57 2 1 TIME SUSP - LETTER SUBMITTED DATE WORK COMPLETED 3 1 TIME SUSP - LETTER SUBMITTED DAYS CHARGED TO DATE = 19 4 1 TIME NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 TIME NOT STARTED LIQ DAMAGE RATE $ 400 6 1 TIME NOT STARTED 7 1 TIME NOT STARTED LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 400 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 TIME SUSP - LETTER SUBMITTED 21 1 TIME SUSP - LETTER SUBMITTED 22 1 TIME SUSP - LETTER SUBMITTED 23 1 TIME SUSP - LETTER SUBMITTED 24 1 TIME SUSP - LETTER SUBMITTED 25 1 TIME SUSP - LETTER SUBMITTED 26 1 TIME SUSP - LETTER SUBMITTED 27 1 TIME SUSP - LETTER SUBMITTED 28 1 TIME SUSP - LETTER SUBMITTED 29 1 TIME SUSP - LETTER SUBMITTED 30 1 TIME SUSP - LETTER SUBMITTED 31 1 TIME SUSP - LETTER SUBMITTED ----- ----- ----- 104 19 85 2 SATURDAY 2 SUNDAY 0 HOLIDAY 15 TIME SUSP - LETTER SUBMITTED 4 TIME NOT STARTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1090313 MGR.NO. 010 PAGE 001 CONT 6189 SEC 85 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618985001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 102,951.78 REPORT DATE 09/09/2009 16.55.36 CONTRACTOR BILLY BENSON 8947 EST PERIOD AUG 01,2009 TO AUG 31,2009 EST NO 004 DIST. 03 COUNTY WILBARGER CONTROL 6189-85-001 PROJECT RMC - 618985001 HIGHWAY US0183 0LIMITS- VARIOUS ROADWAY SIN WILBARGER COUNTY 0TYPE OF WORK- MOWING HWY RIGHT OF WAY 0 0005 PREPARED BY LARRY D TEGTMEYER P.E. 0 0055 MOWING HWY RIGHT OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 264.000 264.000 18.470 4,876.08 0065 0730 FULL-WIDTH MOWING AC 5,310.000 2,738.000 18.470 50,570.86 0 SUBTOTAL BID ITEMS $ 55,446.94 0 TOTAL AMOUNT WORK DONE MOWING HWY RIGHT OF WAY $ 55,446.94 0 TOTAL AMOUNT WORK DONE CONTROL 6189-85-001 $ 55,446.94 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1090313 MGR.NO. 010 PAGE 001 CONT 6189 SEC 85 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618985001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 102,951.78 REPORT DATE 09/09/2009 16.55.36 CONTRACTOR BILLY BENSON 8947 EST PERIOD AUG 01,2009 TO AUG 31,2009 EST NO 004 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAY SIN 0 WILBARGER COUNTY DATE WORK BEGAN MAY 20, 2009 WORKING DAYS USED 19 PERCENT COMPLETE 53.85 PERCENT TIME USED 33.30 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6189-85-001 RMC - 618985001 03 US0183 WILBARGER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 264.000 264.000 18.470 4,876.08 0730 FULL-WIDTH MOWING AC 5,310.000 2,738.000 18.470 50,570.86 0 SUBTOTAL BID ITEMS $ 55,446.94 0 CONTRACT TOTAL ALL ITEMS $ 55,446.94 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1090313 MGR.NO. 010 PAGE 001 CONT 6189 SEC 85 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618985001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 102,951.78 REPORT DATE 09/09/2009 16.55.36 CONTRACTOR BILLY BENSON 8947 EST PERIOD AUG 01,2009 TO AUG 31,2009 EST NO 004 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 244 RMC - 618985001 6189-85-001 55,446.94 .00 55,446.94 .00 .00 55,446.94 47,541.78 7,905.16 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 55,446.94 .00 55,446.94 .00 .00 55,446.94 47,541.78 7,905.16 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1090313 MGR.NO. 010 PAGE 001 CONT 6189 SEC 85 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618985001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 102,951.78 REPORT DATE 09/09/2009 16.55.36 CONTRACTOR BILLY BENSON 8947 EST PERIOD AUG 01,2009 TO AUG 31,2009 EST NO 004 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6189-85-001 RMC - 618985001 03 US0183 WILBARGER -LIMITS - VARIOUS ROADWAY SIN WILBARGER COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 STRIP MOWING AC 264.000 264.000 18.470 4,876.08 65 0730 FULL-WIDTH MOWING AC 5,310.000 164.000 18.470 3,029.08 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 7,905.16 0 TOTAL AMOUNT WORK DONE TO DATE - $ 55,446.94