1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1090311 MGR.NO. 010 PAGE 001 CONT 6189 SEC 83 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618983001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY BAYLOR DIST 03 CONTRACT PRICE $ 62,170.80 REPORT DATE 04/09/2010 15.40.28 CONTRACTOR BILLY BENSON 8947 EST PERIOD JUL 20,2009 TO APR 02,2010 EST NO 010 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 20, 2009 TIME COMPUTED FROM JUL 27, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 42 255 20 235 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 10 1 1 TOTAL DAYS ALLOWED = 42 2 1 WORK COMPLETED AND ACCEPTED DATE WORK COMPLETED 04/02/10 DAYS CHARGED TO DATE = 21 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 257 21 236 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1090311 MGR.NO. 010 PAGE 001 CONT 6189 SEC 83 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618983001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY BAYLOR DIST 03 CONTRACT PRICE $ 62,170.80 REPORT DATE 04/09/2010 15.40.29 CONTRACTOR BILLY BENSON 8947 EST PERIOD JUL 20,2009 TO APR 02,2010 EST NO 010 & FINAL DIST. 03 COUNTY BAYLOR CONTROL 6189-83-001 PROJECT RMC - 618983001 HIGHWAY US0183 0LIMITS- VARIOUS ROADWAYS IN BAYLOR COUNTY 0TYPE OF WORK- MOWING HWY RIGHT OF WAY 0 0005 PREPARED BY LARRY D TEGTMEYER P.E. 0 0055 MOWING HWY RIGHT OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 4,120.000 3,863.000 15.090 58,292.67 0 SUBTOTAL BID ITEMS $ 58,292.67 0 SPECIAL DEDUCTIONS - 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY UNIT AMOUNT NO. PRICE($) ($) - 0080 00000000775 PLASTIC DELINEATORS EA 13.000 16.500 -214.50 0 0085 00000000776 METAL DELINEATORS EA 11.000 15.780 -173.58 0 TOTAL SPECIAL DEDUCTIONS - $ -388.08 0 TOTAL AMOUNT WORK DONE MOWING HWY RIGHT OF WAY $ 58,292.67 TOTAL SPECIAL DEDUCTIONS MOWING HWY RIGHT OF WAY $ -388.08 0 TOTAL AMOUNT WORK DONE CONTROL 6189-83-001 $ 58,292.67 0 TOTAL SPECIAL DEDUCTIONS CONTROL 6189-83-001 $ -388.08 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1090311 MGR.NO. 010 PAGE 001 CONT 6189 SEC 83 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618983001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY BAYLOR DIST 03 CONTRACT PRICE $ 62,170.80 REPORT DATE 04/09/2010 15.40.29 CONTRACTOR BILLY BENSON 8947 EST PERIOD JUL 20,2009 TO APR 02,2010 EST NO 010 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 BAYLOR COUNTY DATE WORK BEGAN JUL 20, 2009 WORKING DAYS USED 21 PERCENT COMPLETE 100.00 PERCENT TIME USED 50.00 DATE COMPLETED APR 2 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6189-83-001 RMC - 618983001 03 US0183 BAYLOR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 4,120.000 3,863.000 15.090 58,292.67 0 SUBTOTAL BID ITEMS $ 58,292.67 0 CONTRACT TOTAL ALL ITEMS $ 58,292.67 SPECIAL DEDUCTIONS 0 UNIT AMOUNT MATRL. NO. MATERIAL DESCRIPTION UNIT QUANTITY PRICE ($) ($) 0 00000000776 METAL DELINEATORS EA 11.000 15.780 -173.58 0 00000000775 PLASTIC DELINEATORS EA 13.000 16.500 -214.50 0 TOTAL SPECIAL DEDUCTIONS $ -388.08 0 CONTRACT TOTAL SPECIAL DEDUCTIONS $ -388.08 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1090311 MGR.NO. 010 PAGE 001 CONT 6189 SEC 83 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618983001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY BAYLOR DIST 03 CONTRACT PRICE $ 62,170.80 REPORT DATE 04/09/2010 15.40.29 CONTRACTOR BILLY BENSON 8947 EST PERIOD JUL 20,2009 TO APR 02,2010 EST NO 010 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 12 RMC - 618983001 6189-83-001 58,292.67 .00 58,292.67 388.08 .00 57,904.59 28,811.07 29,093.52 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 58,292.67 .00 58,292.67 388.08 .00 57,904.59 28,811.07 29,093.52 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1090311 MGR.NO. 010 PAGE 001 CONT 6189 SEC 83 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618983001 HWY US0183 1601 SOUTHWEST PKWY WICHI CNTY BAYLOR DIST 03 CONTRACT PRICE $ 62,170.80 REPORT DATE 04/09/2010 15.40.29 CONTRACTOR BILLY BENSON 8947 EST PERIOD JUL 20,2009 TO APR 02,2010 EST NO 010 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6189-83-001 RMC - 618983001 03 US0183 BAYLOR -LIMITS - VARIOUS ROADWAYS IN BAYLOR COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 4,120.000 1,928.000 15.090 29,093.52 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 29,093.52 0 TOTAL AMOUNT WORK DONE TO DATE - $ 58,292.67