1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1090307 MGR.NO. 010 PAGE 001 CONT 6189 SEC 79 JOB 001 RES ENGR STAFFPR, RUSTY PROJ RMC - 618979001 HWY SH0016 1601 SOUTHWEST PKWY WICHI CNTY YOUNG DIST 03 CONTRACT PRICE $ 53,332.16 REPORT DATE 07/16/2009 08.25.51 CONTRACTOR RWE SERVICES, LLC 13987 EST PERIOD JUN 08,2009 TO JUN 30,2009 EST NO 001 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 08, 2009 TIME COMPUTED FROM JUN 15, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 33 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 09 TOTAL DAYS ALLOWED = 33 DATE WORK COMPLETED DAYS CHARGED TO DATE = 12 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 0 LIQUIDATED DAMAGES 8 1 TIME NOT STARTED 0 DAYS AT $ 400 PER DAY 9 1 TIME NOT STARTED TOTAL = $ .00 10 1 TIME NOT STARTED 11 1 TOO WET CERTIFIED AS CORRECT AND 12 1 TOO WET ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 SATURDAY 21 1 SUNDAY 22 1 23 1 24 1 25 1 26 1 27 1 28 1 SUNDAY 29 1 30 1 TIME SUSP - LETTER SUBMITTED 0 ----- ----- ----- 23 12 11 2 SATURDAY 3 SUNDAY 0 HOLIDAY 3 TIME NOT STARTED 2 TOO WET 1 TIME SUSP - LETTER SUBMITTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1090307 MGR.NO. 010 PAGE 001 CONT 6189 SEC 79 JOB 001 RES ENGR STAFFPR, RUSTY PROJ RMC - 618979001 HWY SH0016 1601 SOUTHWEST PKWY WICHI CNTY YOUNG DIST 03 CONTRACT PRICE $ 53,332.16 REPORT DATE 07/16/2009 08.25.52 CONTRACTOR RWE SERVICES, LLC 13987 EST PERIOD JUN 08,2009 TO JUN 30,2009 EST NO 001 DIST. 03 COUNTY YOUNG CONTROL 6189-79-001 PROJECT RMC - 618979001 HIGHWAY SH0016 0LIMITS- VARIOUS ROADWAYS IN YOUNG COUNTY 0TYPE OF WORK- MOWING HWY RIGHT OF WAY 0 0005 PREPARED BY LARRY D TEGTMEYER P.E. 0 0055 MOWING HWY RIGHT OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 3,284.000 1,642.000 16.240 26,666.08 0 SUBTOTAL BID ITEMS $ 26,666.08 0 TOTAL AMOUNT WORK DONE MOWING HWY RIGHT OF WAY $ 26,666.08 0 TOTAL AMOUNT WORK DONE CONTROL 6189-79-001 $ 26,666.08 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1090307 MGR.NO. 010 PAGE 001 CONT 6189 SEC 79 JOB 001 RES ENGR STAFFPR, RUSTY PROJ RMC - 618979001 HWY SH0016 1601 SOUTHWEST PKWY WICHI CNTY YOUNG DIST 03 CONTRACT PRICE $ 53,332.16 REPORT DATE 07/16/2009 08.25.52 CONTRACTOR RWE SERVICES, LLC 13987 EST PERIOD JUN 08,2009 TO JUN 30,2009 EST NO 001 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 YOUNG COUNTY DATE WORK BEGAN JUN 8 , 2009 WORKING DAYS USED 12 PERCENT COMPLETE 50.00 PERCENT TIME USED 36.30 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6189-79-001 RMC - 618979001 03 SH0016 YOUNG - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 3,284.000 1,642.000 16.240 26,666.08 0 SUBTOTAL BID ITEMS $ 26,666.08 0 CONTRACT TOTAL ALL ITEMS $ 26,666.08 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1090307 MGR.NO. 010 PAGE 001 CONT 6189 SEC 79 JOB 001 RES ENGR STAFFPR, RUSTY PROJ RMC - 618979001 HWY SH0016 1601 SOUTHWEST PKWY WICHI CNTY YOUNG DIST 03 CONTRACT PRICE $ 53,332.16 REPORT DATE 07/16/2009 08.25.52 CONTRACTOR RWE SERVICES, LLC 13987 EST PERIOD JUN 08,2009 TO JUN 30,2009 EST NO 001 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 252 RMC - 618979001 6189-79-001 26,666.08 .00 26,666.08 .00 .00 26,666.08 .00 26,666.08 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 26,666.08 .00 26,666.08 .00 .00 26,666.08 .00 26,666.08 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1090307 MGR.NO. 010 PAGE 001 CONT 6189 SEC 79 JOB 001 RES ENGR STAFFPR, RUSTY PROJ RMC - 618979001 HWY SH0016 1601 SOUTHWEST PKWY WICHI CNTY YOUNG DIST 03 CONTRACT PRICE $ 53,332.16 REPORT DATE 07/16/2009 08.25.52 CONTRACTOR RWE SERVICES, LLC 13987 EST PERIOD JUN 08,2009 TO JUN 30,2009 EST NO 001 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6189-79-001 RMC - 618979001 03 SH0016 YOUNG -LIMITS - VARIOUS ROADWAYS IN YOUNG COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 3,284.000 1,642.000 16.240 26,666.08 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 26,666.08 0 TOTAL AMOUNT WORK DONE TO DATE - $ 26,666.08