1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1090302 MGR.NO. 010 PAGE 001 CONT 6189 SEC 55 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618955001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 248,004.00 REPORT DATE 07/21/2010 16.14.57 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD APR 22,2009 TO JUL 15,2010 EST NO 016 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 22, 2009 TIME COMPUTED FROM APR 28, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 435 414 21 BROUGHT FORWARD ADDL DAYS GRANTED = 61 JUL 10 1 1 RAIN TOTAL DAYS ALLOWED = 426 2 1 RAIN DATE WORK COMPLETED 07/15/10 3 1 SATURDAY DAYS CHARGED TO DATE = 418 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 RAIN LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 RAIN 0 DAYS AT $ 400 PER DAY 9 1 RAIN TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 RAIN ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 WORK COMPLETED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 450 418 32 2 SATURDAY 2 SUNDAY 0 HOLIDAY 6 RAIN 1 WORK COMPLETED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1090302 MGR.NO. 010 PAGE 001 CONT 6189 SEC 55 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618955001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 248,004.00 REPORT DATE 07/21/2010 16.14.58 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD APR 22,2009 TO JUL 15,2010 EST NO 016 & FINAL DIST. 03 COUNTY WILBARGER CONTROL 6189-55-001 PROJECT RMC - 618955001 HIGHWAY US0070 0LIMITS- VARIOUS LOCATIONS IN WICHITA & WILBARGER COUNTIES 0TYPE OF WORK- STREET SWEEPING & DEBRIS REMOVAL 0 0005 PREPARED BY LARRY D TEGTMEYER P.E. 0 0055 STREET SWEEPING & DEBRIS REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0735 DEBRIS REMOVAL (SPOT DEBRIS) MI 50.000 53.500 100.000 5,350.00 0065 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 516.400 520.300 80.000 41,624.00 0070 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 541.600 556.900 85.000 47,336.50 0075 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 592.000 595.250 200.000 119,050.00 0080 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 36.280 39.710 200.000 7,942.00 0085 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 50.000 48.134 300.000 14,440.20 0090 0738 CLEANING/SWEEPING (SPOT) MI 50.000 13.300 300.000 3,990.00 0 SUBTOTAL BID ITEMS $ 239,732.70 0 TOTAL AMOUNT WORK DONE STREET SWEEPING & DEBRIS REMOVAL $ 239,732.70 0 TOTAL AMOUNT WORK DONE CONTROL 6189-55-001 $ 239,732.70 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1090302 MGR.NO. 010 PAGE 001 CONT 6189 SEC 55 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618955001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 248,004.00 REPORT DATE 07/21/2010 16.14.58 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD APR 22,2009 TO JUL 15,2010 EST NO 016 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN 0 WICHITA & WILBARGER COUNTIES DATE WORK BEGAN APR 22, 2009 WORKING DAYS USED 418 PERCENT COMPLETE 100.00 PERCENT TIME USED 98.10 DATE COMPLETED JUL 15 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6189-55-001 RMC - 618955001 03 US0070 WILBARGER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0735 DEBRIS REMOVAL (SPOT DEBRIS) MI 50.000 53.500 100.000 5,350.00 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 516.400 520.300 80.000 41,624.00 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 541.600 556.900 85.000 47,336.50 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 592.000 595.250 200.000 119,050.00 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 36.280 39.710 200.000 7,942.00 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 50.000 48.134 300.000 14,440.20 0738 CLEANING/SWEEPING (SPOT) MI 50.000 13.300 300.000 3,990.00 0 SUBTOTAL BID ITEMS $ 239,732.70 0 CONTRACT TOTAL ALL ITEMS $ 239,732.70 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1090302 MGR.NO. 010 PAGE 001 CONT 6189 SEC 55 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618955001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 248,004.00 REPORT DATE 07/21/2010 16.14.58 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD APR 22,2009 TO JUL 15,2010 EST NO 016 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 244 RMC - 618955001 6189-55-001 239,732.70 .00 239,732.70 .00 .00 239,732.70 224,774.20 14,958.50 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 239,732.70 .00 239,732.70 .00 .00 239,732.70 224,774.20 14,958.50 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1090302 MGR.NO. 010 PAGE 001 CONT 6189 SEC 55 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618955001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 248,004.00 REPORT DATE 07/21/2010 16.14.58 CONTRACTOR WILSON CONTRACTING 13438 EST PERIOD APR 22,2009 TO JUL 15,2010 EST NO 016 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6189-55-001 RMC - 618955001 03 US0070 WILBARGER -LIMITS - VARIOUS LOCATIONS IN WICHITA & WILBARGER COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0735 DEBRIS REMOVAL (SPOT DEBRIS) MI 50.000 46.000 100.000 4,600.00 65 0738 CLEANING/SWEEPING (CENTER MI 516.400 28.700 80.000 2,296.00 MEDIAN) 70 0738 CLEANING/SWEEPING (OUTSIDE MI 541.600 28.500 85.000 2,422.50 MAIN LANE) 75 0738 CLEANING/SWEEPING (FRONTAGE MI 592.000 27.000 200.000 5,400.00 ROAD) 80 0738 CLEANING/SWEEPING MI 36.280 1.200 200.000 240.00 (ENTRANCE/EXIT RAMP) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 14,958.50 0 TOTAL AMOUNT WORK DONE TO DATE - $ 239,732.70