1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11080303 MGR.NO. 010 PAGE 001 CONT 6182 SEC 08 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618208001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 9,769.00 REPORT DATE 02/25/2010 15.38.32 CONTRACTOR TEXAS CUTTERS 7255 EST PERIOD FEB 02,2009 TO JAN 31,2010 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 02, 2009 TIME COMPUTED FROM FEB 02, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 333 333 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 10 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 01/31/10 3 1 DAYS CHARGED TO DATE = 364 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 364 364 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11080303 MGR.NO. 010 PAGE 001 CONT 6182 SEC 08 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618208001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 9,769.00 REPORT DATE 02/25/2010 15.38.33 CONTRACTOR TEXAS CUTTERS 7255 EST PERIOD FEB 02,2009 TO JAN 31,2010 EST NO 013 & FINAL DIST. 03 COUNTY WILBARGER CONTROL 6182-08-001 PROJECT RMC - 618208001 HIGHWAY US0070 0LIMITS- VARIOUS LOCATION IN WILBARGER COUNTY 0TYPE OF WORK- PICNIC AREA MAINTENANCE SERVICES 0 0005 PREPARED BY SS 0 0055 PICNIC AREA MAINTENANCE SERVICES NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0745 JANITORIAL MAINT (PICNIC AREAS) CYC 52.000 44.000 153.250 6,743.00 0065 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 12.000 14.000 150.000 2,100.00 0 SUBTOTAL BID ITEMS $ 8,843.00 0 TOTAL AMOUNT WORK DONE PICNIC AREA MAINTENANCE SERVICES $ 8,843.00 0 TOTAL AMOUNT WORK DONE CONTROL 6182-08-001 $ 8,843.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11080303 MGR.NO. 010 PAGE 001 CONT 6182 SEC 08 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618208001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 9,769.00 REPORT DATE 02/25/2010 15.38.33 CONTRACTOR TEXAS CUTTERS 7255 EST PERIOD FEB 02,2009 TO JAN 31,2010 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATION IN 0 WILBARGER COUNTY DATE WORK BEGAN FEB 2 , 2009 WORKING DAYS USED 364 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.70 DATE COMPLETED JAN 31 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6182-08-001 RMC - 618208001 03 US0070 WILBARGER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0745 JANITORIAL MAINT (PICNIC AREAS) CYC 52.000 44.000 153.250 6,743.00 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 12.000 14.000 150.000 2,100.00 0 SUBTOTAL BID ITEMS $ 8,843.00 0 CONTRACT TOTAL ALL ITEMS $ 8,843.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11080303 MGR.NO. 010 PAGE 001 CONT 6182 SEC 08 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618208001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 9,769.00 REPORT DATE 02/25/2010 15.38.33 CONTRACTOR TEXAS CUTTERS 7255 EST PERIOD FEB 02,2009 TO JAN 31,2010 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 244 RMC - 618208001 6182-08-001 8,843.00 .00 8,843.00 .00 .00 8,843.00 8,843.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 8,843.00 .00 8,843.00 .00 .00 8,843.00 8,843.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11080303 MGR.NO. 010 PAGE 001 CONT 6182 SEC 08 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 618208001 HWY US0070 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 9,769.00 REPORT DATE 02/25/2010 15.38.33 CONTRACTOR TEXAS CUTTERS 7255 EST PERIOD FEB 02,2009 TO JAN 31,2010 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6182-08-001 RMC - 618208001 03 US0070 WILBARGER -LIMITS - VARIOUS LOCATION IN WILBARGER COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 8,843.00