1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7070301 MGR.NO. 010 PAGE 001 CONT 6162 SEC 59 JOB 001 RES ENGR SLAYDEN, SUSIE PROJ RMC - 616259001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 12,535.56 REPORT DATE 08/10/2009 08.55.05 CONTRACTOR PRO LAWN 12794 EST PERIOD AUG 01,2007 TO JUL 31,2009 EST NO 024 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 21, 2007 TIME COMPUTED FROM AUG 01, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 700 700 0 BROUGHT FORWARD ADDL DAYS GRANTED = 1 JUL 09 1 1 TOTAL DAYS ALLOWED = 731 2 1 DATE WORK COMPLETED 07/31/09 3 1 DAYS CHARGED TO DATE = 731 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 450 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 450 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 731 731 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7070301 MGR.NO. 010 PAGE 001 CONT 6162 SEC 59 JOB 001 RES ENGR SLAYDEN, SUSIE PROJ RMC - 616259001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 12,535.56 REPORT DATE 08/10/2009 08.55.05 CONTRACTOR PRO LAWN 12794 EST PERIOD AUG 01,2007 TO JUL 31,2009 EST NO 024 & FINAL DIST. 03 COUNTY WILBARGER CONTROL 6162-59-001 PROJECT RMC - 616259001 HIGHWAY US0287 0LIMITS- FANNIN STREET BOWIE STREET IN VERNON 0TYPE OF WORK- LANDSCAPE MAINTENANCE 0 0005 PREPARED BY LARRY D TEGTMEYER P.E. 0 0055 LANDSCAPE MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0751 MOWING, TRIMMING, AND EDGING CYC 36.000 26.000 348.210 9,053.46 0 SUBTOTAL BID ITEMS $ 9,053.46 0 TOTAL AMOUNT WORK DONE LANDSCAPE MAINTENANCE $ 9,053.46 0 TOTAL AMOUNT WORK DONE CONTROL 6162-59-001 $ 9,053.46 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7070301 MGR.NO. 010 PAGE 001 CONT 6162 SEC 59 JOB 001 RES ENGR SLAYDEN, SUSIE PROJ RMC - 616259001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 12,535.56 REPORT DATE 08/10/2009 08.55.05 CONTRACTOR PRO LAWN 12794 EST PERIOD AUG 01,2007 TO JUL 31,2009 EST NO 024 & FINAL 0*********************************************************************************************************************************** -LIMITS - FANNIN STREET 0 BOWIE STREET IN VERNON DATE WORK BEGAN AUG 21, 2007 WORKING DAYS USED 731 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JUL 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6162-59-001 RMC - 616259001 03 US0287 WILBARGER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0751 MOWING, TRIMMING, AND EDGING CYC 36.000 26.000 348.210 9,053.46 0 SUBTOTAL BID ITEMS $ 9,053.46 0 CONTRACT TOTAL ALL ITEMS $ 9,053.46 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7070301 MGR.NO. 010 PAGE 001 CONT 6162 SEC 59 JOB 001 RES ENGR SLAYDEN, SUSIE PROJ RMC - 616259001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 12,535.56 REPORT DATE 08/10/2009 08.55.05 CONTRACTOR PRO LAWN 12794 EST PERIOD AUG 01,2007 TO JUL 31,2009 EST NO 024 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 244 RMC - 616259001 6162-59-001 9,053.46 .00 9,053.46 .00 .00 9,053.46 8,357.04 696.42 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 9,053.46 .00 9,053.46 .00 .00 9,053.46 8,357.04 696.42 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7070301 MGR.NO. 010 PAGE 001 CONT 6162 SEC 59 JOB 001 RES ENGR SLAYDEN, SUSIE PROJ RMC - 616259001 HWY US0287 1601 SOUTHWEST PKWY WICHI CNTY WILBARGER DIST 03 CONTRACT PRICE $ 12,535.56 REPORT DATE 08/10/2009 08.55.06 CONTRACTOR PRO LAWN 12794 EST PERIOD AUG 01,2007 TO JUL 31,2009 EST NO 024 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6162-59-001 RMC - 616259001 03 US0287 WILBARGER -LIMITS - FANNIN STREET BOWIE STREET IN VERNON LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0751 MOWING, TRIMMING, AND EDGING CYC 36.000 2.000 348.210 696.42 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 696.42 0 TOTAL AMOUNT WORK DONE TO DATE - $ 9,053.46