1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8090904 MGR.NO. 804 PAGE 001 CONT 6198 SEC 55 JOB 001 RES ENGR MORAN, TONY PROJ RMC - 619855001 HWY SH0171 1400 S. ABBOTT AVE. HILLS CNTY HILL DIST 09 CONTRACT PRICE $ 101,998.98 REPORT DATE 03/01/2010 13.10.13 CONTRACTOR JAMES EDWARD MOORE 12496 EST PERIOD SEP 28,2009 TO FEB 01,2010 EST NO 006 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 28, 2009 TIME COMPUTED FROM SEP 28, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 46 126 45 81 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 10 1 1 CONTRACT CANCELED TOTAL DAYS ALLOWED = 46 DATE WORK COMPLETED 02/01/10 DAYS CHARGED TO DATE = 45 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 127 45 82 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 CONTRACT CANCELED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8090904 MGR.NO. 804 PAGE 001 CONT 6198 SEC 55 JOB 001 RES ENGR MORAN, TONY PROJ RMC - 619855001 HWY SH0171 1400 S. ABBOTT AVE. HILLS CNTY HILL DIST 09 CONTRACT PRICE $ 101,998.98 REPORT DATE 03/01/2010 13.10.14 CONTRACTOR JAMES EDWARD MOORE 12496 EST PERIOD SEP 28,2009 TO FEB 01,2010 EST NO 006 & FINAL DIST. 09 COUNTY HILL CONTROL 6198-55-001 PROJECT RMC - 619855001 HIGHWAY SH0171 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- TREE TRIMMING AND TREE REMOVAL 0 0005 PREPARED JUNE 2009 0 0055 ROADWAY NET LENGTH120.700 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE TRIMMING/BRUSH REMOVAL MI 120.700 16.250 835.120 13,570.70 0065 0752 TREE REMOVAL (4"-12" DIA) EA 1.000 0.000 100.000 .00 0070 0752 TREE REMOVAL (12"-18" DIA) EA 4.000 0.000 100.000 .00 0075 0752 TREE REMOVAL (18"-24" DIA) EA 4.000 0.000 125.000 .00 0080 0752 TREE REMOVAL (24"-30" DIA) EA 1.000 0.000 200.000 .00 0 SUBTOTAL BID ITEMS $ 13,570.70 0 TOTAL AMOUNT WORK DONE ROADWAY $ 13,570.70 0 TOTAL AMOUNT WORK DONE CONTROL 6198-55-001 $ 13,570.70 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8090904 MGR.NO. 804 PAGE 001 CONT 6198 SEC 55 JOB 001 RES ENGR MORAN, TONY PROJ RMC - 619855001 HWY SH0171 1400 S. ABBOTT AVE. HILLS CNTY HILL DIST 09 CONTRACT PRICE $ 101,998.98 REPORT DATE 03/01/2010 13.10.14 CONTRACTOR JAMES EDWARD MOORE 12496 EST PERIOD SEP 28,2009 TO FEB 01,2010 EST NO 006 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN SEP 28, 2009 WORKING DAYS USED 45 PERCENT COMPLETE 100.00 PERCENT TIME USED 97.80 DATE COMPLETED FEB 1 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6198-55-001 RMC - 619855001 09 SH0171 HILL - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE TRIMMING/BRUSH REMOVAL MI 120.700 16.250 835.120 13,570.70 0 SUBTOTAL BID ITEMS $ 13,570.70 0 CONTRACT TOTAL ALL ITEMS $ 13,570.70 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8090904 MGR.NO. 804 PAGE 001 CONT 6198 SEC 55 JOB 001 RES ENGR MORAN, TONY PROJ RMC - 619855001 HWY SH0171 1400 S. ABBOTT AVE. HILLS CNTY HILL DIST 09 CONTRACT PRICE $ 101,998.98 REPORT DATE 03/01/2010 13.10.14 CONTRACTOR JAMES EDWARD MOORE 12496 EST PERIOD SEP 28,2009 TO FEB 01,2010 EST NO 006 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 110 RMC - 619855001 6198-55-001 13,570.70 .00 13,570.70 .00 .00 13,570.70 13,570.70 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 13,570.70 .00 13,570.70 .00 .00 13,570.70 13,570.70 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8090904 MGR.NO. 804 PAGE 001 CONT 6198 SEC 55 JOB 001 RES ENGR MORAN, TONY PROJ RMC - 619855001 HWY SH0171 1400 S. ABBOTT AVE. HILLS CNTY HILL DIST 09 CONTRACT PRICE $ 101,998.98 REPORT DATE 03/01/2010 13.10.14 CONTRACTOR JAMES EDWARD MOORE 12496 EST PERIOD SEP 28,2009 TO FEB 01,2010 EST NO 006 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6198-55-001 RMC - 619855001 09 SH0171 HILL -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 13,570.70