1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12080906 MGR.NO. 803 PAGE 001 CONT 6183 SEC 73 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 618373001 HWY US0281 3502 E. MAIN STREET GATES CNTY HAMILTON DIST 09 CONTRACT PRICE $ 111,628.23 REPORT DATE 12/02/2009 14.28.24 CONTRACTOR TEXAS MOWING SERVICE 6572 EST PERIOD NOV 01,2009 TO NOV 30,2009 EST NO 005 & SM-FIN --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 07, 2009 TIME COMPUTED FROM JUL 08, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 74 117 17 100 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 09 1 1 NO WORK SCHEDULED BY TXDOT TOTAL DAYS ALLOWED = 74 2 1 NO WORK SCHEDULED BY TXDOT DATE WORK COMPLETED 11/30/09 3 1 CYCLE TIME NOT STARTED DAYS CHARGED TO DATE = 28 4 1 CYCLE TIME NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 CYCLE TIME NOT STARTED LIQ DAMAGE RATE $ 400 6 1 CYCLE TIME NOT STARTED 7 1 CYCLE TIME NOT STARTED LIQUIDATED DAMAGES 8 1 CYCLE TIME NOT STARTED 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 HOLIDAY CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 SATURDAY 15 1 SUNDAY 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 RAIN 21 1 TOO WET 22 1 SUNDAY 23 1 24 1 25 1 26 1 HOLIDAY 27 1 LITTER CYCLE COMPLETE 28 1 NO WORK SCHEDULED BY TXDOT 29 1 NO WORK SCHEDULED BY TXDOT 30 1 WORK ACCEPTED 0 ----- ----- ----- 147 28 119 1 SATURDAY 2 SUNDAY 2 HOLIDAY 4 NO WORK SCHEDULED BY TXDOT 6 CYCLE TIME NOT STARTED 1 RAIN 1 TOO WET 1 LITTER CYCLE COMPLETE 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12080906 MGR.NO. 803 PAGE 001 CONT 6183 SEC 73 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 618373001 HWY US0281 3502 E. MAIN STREET GATES CNTY HAMILTON DIST 09 CONTRACT PRICE $ 111,628.23 REPORT DATE 12/02/2009 14.28.25 CONTRACTOR TEXAS MOWING SERVICE 6572 EST PERIOD NOV 01,2009 TO NOV 30,2009 EST NO 005 & SM-FIN DIST. 09 COUNTY HAMILTON CONTROL 6183-73-001 PROJECT RMC - 618373001 HIGHWAY US0281 0LIMITS- STATE MAINTAINED ROADWAYS IN HAMILTON COUNTY 0TYPE OF WORK- MOWING AND LITTER PICKUP AND DISPOSAL 0 0005 PREPARED OCTOBER 2008 0 0055 ROADWAY NET LENGTH287.541 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 SPOT MOWING AC 12.000 0.000 100.000 .00 0065 0730 FULL-WIDTH MOWING - (RURAL) AC 5,027.000 5,028.000 18.490 92,967.72 0070 0734 LITTER REMOVAL AC 1,997.000 1,977.000 7.000 13,839.00 0075 0734 LITTER REMOVAL(SPOT) AC 500.000 0.000 7.000 .00 0 SUBTOTAL BID ITEMS $ 106,806.72 0 TOTAL AMOUNT WORK DONE ROADWAY $ 106,806.72 0 TOTAL AMOUNT WORK DONE CONTROL 6183-73-001 $ 106,806.72 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12080906 MGR.NO. 803 PAGE 001 CONT 6183 SEC 73 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 618373001 HWY US0281 3502 E. MAIN STREET GATES CNTY HAMILTON DIST 09 CONTRACT PRICE $ 111,628.23 REPORT DATE 12/02/2009 14.28.25 CONTRACTOR TEXAS MOWING SERVICE 6572 EST PERIOD NOV 01,2009 TO NOV 30,2009 EST NO 005 & SM-FIN 0*********************************************************************************************************************************** -LIMITS - STATE MAINTAINED ROADWAYS 0 IN HAMILTON COUNTY DATE WORK BEGAN JUL 7 , 2009 WORKING DAYS USED 28 PERCENT COMPLETE 100.00 PERCENT TIME USED 37.80 DATE COMPLETED NOV 30 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6183-73-001 RMC - 618373001 09 US0281 HAMILTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING - (RURAL) AC 5,027.000 5,028.000 18.490 92,967.72 0734 LITTER REMOVAL AC 1,997.000 1,977.000 7.000 13,839.00 0 SUBTOTAL BID ITEMS $ 106,806.72 0 CONTRACT TOTAL ALL ITEMS $ 106,806.72 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12080906 MGR.NO. 803 PAGE 001 CONT 6183 SEC 73 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 618373001 HWY US0281 3502 E. MAIN STREET GATES CNTY HAMILTON DIST 09 CONTRACT PRICE $ 111,628.23 REPORT DATE 12/02/2009 14.28.25 CONTRACTOR TEXAS MOWING SERVICE 6572 EST PERIOD NOV 01,2009 TO NOV 30,2009 EST NO 005 & SM-FIN ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 98 RMC - 618373001 6183-73-001 106,806.72 .00 106,806.72 .00 .00 106,806.72 53,399.86 53,406.86 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 106,806.72 .00 106,806.72 .00 .00 106,806.72 53,399.86 53,406.86 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12080906 MGR.NO. 803 PAGE 001 CONT 6183 SEC 73 JOB 001 RES ENGR BROWN, RICHARD PROJ RMC - 618373001 HWY US0281 3502 E. MAIN STREET GATES CNTY HAMILTON DIST 09 CONTRACT PRICE $ 111,628.23 REPORT DATE 12/02/2009 14.28.25 CONTRACTOR TEXAS MOWING SERVICE 6572 EST PERIOD NOV 01,2009 TO NOV 30,2009 EST NO 005 & SM-FIN ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6183-73-001 RMC - 618373001 09 US0281 HAMILTON -LIMITS - STATE MAINTAINED ROADWAYS IN HAMILTON COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0730 FULL-WIDTH MOWING - (RURAL) AC 5,027.000 2,514.000 18.490 46,483.86 70 0734 LITTER REMOVAL AC 1,997.000 989.000 7.000 6,923.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 53,406.86 0 TOTAL AMOUNT WORK DONE TO DATE - $ 106,806.72