1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8131002 MGR.NO. 770 PAGE 001 CONT 6257 SEC 61 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625761001 HWY SH0135 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 168,084.00 REPORT DATE 04/02/2014 14.21.53 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 04,2013 TO FEB 15,2014 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 18, 2013 TIME COMPUTED FROM NOV 04, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 116 89 55 34 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 14 1 1 SATURDAY TOTAL DAYS ALLOWED = 116 2 1 SUNDAY DATE WORK COMPLETED 02/15/14 3 1 DAYS CHARGED TO DATE = 61 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 RAIN LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 590 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 RAIN 11 1 RAIN CERTIFIED AS CORRECT AND 12 1 RAIN ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 104 61 43 2 SATURDAY 2 SUNDAY 0 HOLIDAY 4 RAIN 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8131002 MGR.NO. 770 PAGE 001 CONT 6257 SEC 61 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625761001 HWY SH0135 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 168,084.00 REPORT DATE 04/02/2014 14.21.53 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 04,2013 TO FEB 15,2014 EST NO 005 & FINAL DIST. 10 COUNTY CHEROKEE CONTROL 6257-61-001 PROJECT RMC - 625761001 HIGHWAY SH0135 0LIMITS- VARIOUS ROADWAYS IN CHEROKEE AND RUSK COUNTY 0TYPE OF WORK- TREE TRIMMING AND BRUSH REMOVAL 0 0005 PREPARED BY BRAD BASSETT 0 0055 TREE TRIMMING NET LENGTH116.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE TRIMMING/BRUSH REMOVAL MI 116.000 116.000 1,449.000 168,084.00 0 SUBTOTAL BID ITEMS $ 168,084.00 0 TOTAL AMOUNT WORK DONE TREE TRIMMING $ 168,084.00 0 TOTAL AMOUNT WORK DONE CONTROL 6257-61-001 $ 168,084.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8131002 MGR.NO. 770 PAGE 001 CONT 6257 SEC 61 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625761001 HWY SH0135 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 168,084.00 REPORT DATE 04/02/2014 14.21.53 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 04,2013 TO FEB 15,2014 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 CHEROKEE AND RUSK COUNTY DATE WORK BEGAN NOV 18, 2013 WORKING DAYS USED 61 PERCENT COMPLETE 100.00 PERCENT TIME USED 52.50 DATE COMPLETED FEB 15 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6257-61-001 RMC - 625761001 10 SH0135 CHEROKEE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE TRIMMING/BRUSH REMOVAL MI 116.000 116.000 1,449.000 168,084.00 0 SUBTOTAL BID ITEMS $ 168,084.00 0 CONTRACT TOTAL ALL ITEMS $ 168,084.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8131002 MGR.NO. 770 PAGE 001 CONT 6257 SEC 61 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625761001 HWY SH0135 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 168,084.00 REPORT DATE 04/02/2014 14.21.53 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 04,2013 TO FEB 15,2014 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 37 RMC - 625761001 6257-61-001 168,084.00 .00 168,084.00 .00 .00 168,084.00 168,084.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 168,084.00 .00 168,084.00 .00 .00 168,084.00 168,084.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8131002 MGR.NO. 770 PAGE 001 CONT 6257 SEC 61 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 625761001 HWY SH0135 2709 W FRONT ST TYLER CNTY CHEROKEE DIST 10 CONTRACT PRICE $ 168,084.00 REPORT DATE 04/02/2014 14.21.54 CONTRACTOR TERRY ENTERPRISES 10469 EST PERIOD NOV 04,2013 TO FEB 15,2014 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6257-61-001 RMC - 625761001 10 SH0135 CHEROKEE -LIMITS - VARIOUS ROADWAYS IN CHEROKEE AND RUSK COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 168,084.00