1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11124003 MGR.NO. 770 PAGE 001 CONT 6247 SEC 58 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 624758001 HWY FM0095 2709 W FRONT ST TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 762,358.90 REPORT DATE 11/06/2013 14.35.15 CONTRACTOR A. L. HELMCAMP, INC. 6559 EST PERIOD MAR 25,2013 TO OCT 02,2013 EST NO 008 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 17, 2013 TIME COMPUTED FROM MAR 25, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 86 192 58 134 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 13 1 1 TIME SUSPENDED TOTAL DAYS ALLOWED = 86 2 1 WORK COMPLETED AND ACCEPTED DATE WORK COMPLETED 10/02/13 DAYS CHARGED TO DATE = 58 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 610 0 LIQUIDATED DAMAGES 0 DAYS AT $ 610 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 194 58 136 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 TIME SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11124003 MGR.NO. 770 PAGE 001 CONT 6247 SEC 58 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 624758001 HWY FM0095 2709 W FRONT ST TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 762,358.90 REPORT DATE 11/06/2013 14.35.16 CONTRACTOR A. L. HELMCAMP, INC. 6559 EST PERIOD MAR 25,2013 TO OCT 02,2013 EST NO 008 & FINAL DIST. 10 COUNTY RUSK CONTROL 6247-58-001 PROJECT RMC - 624758001 HIGHWAY FM0095 0LIMITS- 3.929 MI S OF US 84, S 0.01 MI S OF FM 1971 0TYPE OF WORK- REHAB OF ROADWAY 0 0005 PREPARED BY BRADLEY BASSETT 0 0055 REHAB OF ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0105 REMOVING STAB BASE AND ASPH PAV (6") SY 25,635.000 24,689.000 2.000 49,378.00 0065 0164 BROADCAST SEED (TEMP) (WARM) SY 23,300.000 0.000 .010 .00 0070 0164 BROADCAST SEED (TEMP) (COOL) SY 23,300.000 0.000 .010 .00 0075 0164 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 46,600.000 0.000 .050 .00 0080 0168 VEGETATIVE WATERING MG 1,025.000 0.000 .010 .00 0085 0247 FL BS (CMP IN PLC)(TY A GR 2) (6") SY 25,635.000 24,689.000 11.670 288,120.63 0090 0275 CEMENT TON 564.000 542.000 122.000 66,124.00 0095 0275 CEMENT TREAT (NEW BASE) (6") SY 25,635.000 24,689.000 1.400 34,564.60 0100 0275 CEMENT TREAT(EXIST MATL)(8") SY 25,635.000 24,689.000 1.400 34,564.60 0105 0310 PRIME COAT & BLOTTER (MC-30) GAL 6,409.000 4,821.000 4.000 19,284.00 0110 0316 ASPH (AC-20-5TR) GAL 19,996.000 17,190.000 4.000 68,760.00 0115 0316 AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B) CY 233.000 235.000 95.000 22,325.00 0120 0316 AGGR (TY-PD OR TY-PL GR-3 SAC-B) CY 270.000 270.000 95.000 25,650.00 0125 0500 MOBILIZATION LS 1.000 1.000 75,000.000 75,000.00 0130 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 2,000.000 8,000.00 0135 1122 ROCK FILTER DAMS (INSTALL) (TY 1) LF 420.000 91.000 20.000 1,820.00 0140 1122 ROCK FILTER DAMS (REMOVE) LF 420.000 0.000 5.000 .00 0145 1122 BACKHOE WORK (EROSION & SEDM CONT) HR 50.000 0.000 40.000 .00 0150 1122 TEMPORARY SEDIMENT CONTROL FENCE INSTLL LF 1,100.000 733.000 2.000 1,466.00 0155 0662 WK ZN PAV MRK NON-REMOV (Y) 1 4" (BRK) LF 260.000 0.000 .100 .00 0160 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD) LF 15,840.000 0.000 .100 .00 0165 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 870.000 0.000 .750 .00 0170 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 20.000 0.000 3.910 .00 0175 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 15,840.000 11,415.000 .620 7,077.30 0180 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 260.000 1,640.000 .720 1,180.80 0185 0672 REFL PAV MRKR TY II-A-A EA 407.000 225.000 3.000 675.00 0190 0760 DITCH CLEANING AND RESHAPING (FOOT) LF 20,975.000 2,599.000 .100 259.90 0195 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 28.000 28.000 63.000 1,764.00 0 SUBTOTAL BID ITEMS $ 706,013.83 0 TOTAL AMOUNT WORK DONE REHAB OF ROADWAY $ 706,013.83 0 TOTAL AMOUNT WORK DONE CONTROL 6247-58-001 $ 706,013.83 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11124003 MGR.NO. 770 PAGE 001 CONT 6247 SEC 58 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 624758001 HWY FM0095 2709 W FRONT ST TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 762,358.90 REPORT DATE 11/06/2013 14.35.16 CONTRACTOR A. L. HELMCAMP, INC. 6559 EST PERIOD MAR 25,2013 TO OCT 02,2013 EST NO 008 & FINAL 0*********************************************************************************************************************************** -LIMITS - 3.929 MI S OF US 84, S 0 0.01 MI S OF FM 1971 DATE WORK BEGAN JUN 17, 2013 WORKING DAYS USED 58 PERCENT COMPLETE 100.00 PERCENT TIME USED 67.40 DATE COMPLETED OCT 2 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6247-58-001 RMC - 624758001 10 FM0095 RUSK - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0105 REMOVING STAB BASE AND ASPH PAV (6") SY 25,635.000 24,689.000 2.000 49,378.00 0247 FL BS (CMP IN PLC)(TY A GR 2) (6") SY 25,635.000 24,689.000 11.670 288,120.63 0275 CEMENT TON 564.000 542.000 122.000 66,124.00 0275 CEMENT TREAT (NEW BASE) (6") SY 25,635.000 24,689.000 1.400 34,564.60 0275 CEMENT TREAT(EXIST MATL)(8") SY 25,635.000 24,689.000 1.400 34,564.60 0310 PRIME COAT & BLOTTER (MC-30) GAL 6,409.000 4,821.000 4.000 19,284.00 0316 ASPH (AC-20-5TR) GAL 19,996.000 17,190.000 4.000 68,760.00 0316 AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B) CY 233.000 235.000 95.000 22,325.00 0316 AGGR (TY-PD OR TY-PL GR-3 SAC-B) CY 270.000 270.000 95.000 25,650.00 0500 MOBILIZATION LS 1.000 1.000 75,000.000 75,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 4.000 2,000.000 8,000.00 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 260.000 1,640.000 .720 1,180.80 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 15,840.000 11,415.000 .620 7,077.30 0672 REFL PAV MRKR TY II-A-A EA 407.000 225.000 3.000 675.00 0760 DITCH CLEANING AND RESHAPING (FOOT) LF 20,975.000 2,599.000 .100 259.90 1122 ROCK FILTER DAMS (INSTALL) (TY 1) LF 420.000 91.000 20.000 1,820.00 11122 TEMPORARY SEDIMENT CONTROL FENCE INSTLL LF 1,100.000 733.000 2.000 1,466.00 6834 PORTABLE CHANGEABLE MESSAGE SIGN DAY 28.000 28.000 63.000 1,764.00 0 SUBTOTAL BID ITEMS $ 706,013.83 0 CONTRACT TOTAL ALL ITEMS $ 706,013.83 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11124003 MGR.NO. 770 PAGE 001 CONT 6247 SEC 58 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 624758001 HWY FM0095 2709 W FRONT ST TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 762,358.90 REPORT DATE 11/06/2013 14.35.16 CONTRACTOR A. L. HELMCAMP, INC. 6559 EST PERIOD MAR 25,2013 TO OCT 02,2013 EST NO 008 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 201 RMC - 624758001 6247-58-001 706,013.83 .00 706,013.83 .00 .00 706,013.83 706,013.83 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 706,013.83 .00 706,013.83 .00 .00 706,013.83 706,013.83 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11124003 MGR.NO. 770 PAGE 001 CONT 6247 SEC 58 JOB 001 RES ENGR FONTENOT, JACQUES PROJ RMC - 624758001 HWY FM0095 2709 W FRONT ST TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 762,358.90 REPORT DATE 11/06/2013 14.35.17 CONTRACTOR A. L. HELMCAMP, INC. 6559 EST PERIOD MAR 25,2013 TO OCT 02,2013 EST NO 008 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6247-58-001 RMC - 624758001 10 FM0095 RUSK -LIMITS - 3.929 MI S OF US 84, S 0.01 MI S OF FM 1971 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 706,013.83