1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5124013 MGR.NO. PAGE 001 CONT 6240 SEC 11 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624011001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 422,400.00 REPORT DATE 10/04/2013 14.22.51 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 01,2012 TO SEP 12,2013 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 04, 2012 TIME COMPUTED FROM SEP 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 255 365 248 117 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 13 1 1 SUNDAY TOTAL DAYS ALLOWED = 255 2 1 HOLIDAY DATE WORK COMPLETED 09/12/13 3 1 DAYS CHARGED TO DATE = 255 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 SATURDAY LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED AND ACCEPTED ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 377 255 122 1 SATURDAY 2 SUNDAY 1 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5124013 MGR.NO. PAGE 001 CONT 6240 SEC 11 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624011001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 422,400.00 REPORT DATE 10/04/2013 14.22.51 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 01,2012 TO SEP 12,2013 EST NO 013 & FINAL DIST. 10 COUNTY SMITH CONTROL 6240-11-001 PROJECT RMC - 624011001 HIGHWAY US0069 0LIMITS- VARIOUS ROADWAYS IN THE TYLER DISTRICT 0TYPE OF WORK- PAINT AND BEAD STRIPING 0 0005 PREPARED BY LESLIE WICKHAM 0 0055 PAINT AND BEAD STRIPING NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REF PAV MRK TY II (W) 4" (BRK) LF 65,000.000 64,240.000 .120 7,708.80 0065 0666 REF PAV MRK TY II (W) 4" (SLD) LF 750,000.000 1,028,527.000 .120 123,423.24 0070 0666 REF PAV MRK TY II (W) 8" (SLD) LF 6,500.000 12,921.000 .500 6,460.50 0075 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 175,000.000 106,467.000 .120 12,776.04 0080 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 3,003,500.000 1,461,183.000 .100 146,118.30 0 SUBTOTAL BID ITEMS $ 296,486.88 0 TOTAL AMOUNT WORK DONE PAINT AND BEAD STRIPING $ 296,486.88 0 TOTAL AMOUNT WORK DONE CONTROL 6240-11-001 $ 296,486.88 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5124013 MGR.NO. PAGE 001 CONT 6240 SEC 11 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624011001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 422,400.00 REPORT DATE 10/04/2013 14.22.51 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 01,2012 TO SEP 12,2013 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN THE TYLER 0 DISTRICT DATE WORK BEGAN SEP 4 , 2012 WORKING DAYS USED 255 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED SEP 12 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6240-11-001 RMC - 624011001 10 US0069 SMITH - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0666 REF PAV MRK TY II (W) 4" (BRK) LF 65,000.000 64,240.000 .120 7,708.80 0666 REF PAV MRK TY II (W) 4" (SLD) LF 750,000.000 1,028,527.000 .120 123,423.24 0666 REF PAV MRK TY II (W) 8" (SLD) LF 6,500.000 12,921.000 .500 6,460.50 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 175,000.000 106,467.000 .120 12,776.04 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 3,003,500.000 1,461,183.000 .100 146,118.30 0 SUBTOTAL BID ITEMS $ 296,486.88 0 CONTRACT TOTAL ALL ITEMS $ 296,486.88 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5124013 MGR.NO. PAGE 001 CONT 6240 SEC 11 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624011001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 422,400.00 REPORT DATE 10/04/2013 14.22.51 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 01,2012 TO SEP 12,2013 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 212 RMC - 624011001 6240-11-001 296,486.88 .00 296,486.88 .00 .00 296,486.88 296,486.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 296,486.88 .00 296,486.88 .00 .00 296,486.88 296,486.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5124013 MGR.NO. PAGE 001 CONT 6240 SEC 11 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 624011001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 422,400.00 REPORT DATE 10/04/2013 14.22.51 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD SEP 01,2012 TO SEP 12,2013 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6240-11-001 RMC - 624011001 10 US0069 SMITH -LIMITS - VARIOUS ROADWAYS IN THE TYLER DISTRICT - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 296,486.88