1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1121002 MGR.NO. PAGE 001 CONT 6237 SEC 68 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623768001 HWY SH0064 2709 W. FRONT ST. TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 119,213.60 REPORT DATE 07/03/2012 10.25.15 CONTRACTOR TEXAS TREE & LANDSCAPE, LTD. 12823 EST PERIOD MAR 12,2012 TO MAY 04,2012 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 26, 2012 TIME COMPUTED FROM MAR 12, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 37 50 28 22 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 12 1 1 TOTAL DAYS ALLOWED = 37 2 1 DATE WORK COMPLETED 05/04/12 3 1 DAYS CHARGED TO DATE = 31 4 1 WORK COMPLETED AND ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 54 31 23 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1121002 MGR.NO. PAGE 001 CONT 6237 SEC 68 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623768001 HWY SH0064 2709 W. FRONT ST. TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 119,213.60 REPORT DATE 07/03/2012 10.25.15 CONTRACTOR TEXAS TREE & LANDSCAPE, LTD. 12823 EST PERIOD MAR 12,2012 TO MAY 04,2012 EST NO 004 & FINAL DIST. 10 COUNTY RUSK CONTROL 6237-68-001 PROJECT RMC - 623768001 HIGHWAY SH0064 0LIMITS- HENDERSON MAINTENANCE SECTION JACKSONVILLE/RUSK MAINTENANCE SECTION 0TYPE OF WORK- REPLACE RAISED PAVEMENT MARKERS 0 0005 PREPARED BY LESLIE WICKHAM 0 0055 RAISED PAVEMENT MARKERS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0672 REFL PAV MRKR TY I-A EA 4,417.000 3,619.000 2.200 7,961.80 0065 0672 REFL PAV MRKR TY I-C EA 4,243.000 3,653.000 2.200 8,036.60 0070 0672 REFL PAV MRKR TY I-R EA 15.000 0.000 2.200 .00 0075 0672 REFL PAV MRKR TY II-A-A EA 45,498.000 39,799.000 2.200 87,557.80 0080 0672 REFL PAV MRKR TY II-C-R EA 15.000 4,405.000 2.200 9,691.00 0 SUBTOTAL BID ITEMS $ 113,247.20 0 TOTAL AMOUNT WORK DONE RAISED PAVEMENT MARKERS $ 113,247.20 0 TOTAL AMOUNT WORK DONE CONTROL 6237-68-001 $ 113,247.20 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1121002 MGR.NO. PAGE 001 CONT 6237 SEC 68 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623768001 HWY SH0064 2709 W. FRONT ST. TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 119,213.60 REPORT DATE 07/03/2012 10.25.16 CONTRACTOR TEXAS TREE & LANDSCAPE, LTD. 12823 EST PERIOD MAR 12,2012 TO MAY 04,2012 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - HENDERSON MAINTENANCE SECTION 0 JACKSONVILLE/RUSK MAINTENANCE SECTION DATE WORK BEGAN MAR 26, 2012 WORKING DAYS USED 31 PERCENT COMPLETE 100.00 PERCENT TIME USED 83.70 DATE COMPLETED MAY 4 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6237-68-001 RMC - 623768001 10 SH0064 RUSK - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0672 REFL PAV MRKR TY I-A EA 4,417.000 3,619.000 2.200 7,961.80 0672 REFL PAV MRKR TY I-C EA 4,243.000 3,653.000 2.200 8,036.60 0672 REFL PAV MRKR TY II-A-A EA 45,498.000 39,799.000 2.200 87,557.80 0672 REFL PAV MRKR TY II-C-R EA 15.000 4,405.000 2.200 9,691.00 0 SUBTOTAL BID ITEMS $ 113,247.20 0 CONTRACT TOTAL ALL ITEMS $ 113,247.20 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1121002 MGR.NO. PAGE 001 CONT 6237 SEC 68 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623768001 HWY SH0064 2709 W. FRONT ST. TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 119,213.60 REPORT DATE 07/03/2012 10.25.16 CONTRACTOR TEXAS TREE & LANDSCAPE, LTD. 12823 EST PERIOD MAR 12,2012 TO MAY 04,2012 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 201 RMC - 623768001 6237-68-001 113,247.20 .00 113,247.20 .00 .00 113,247.20 113,247.20 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 113,247.20 .00 113,247.20 .00 .00 113,247.20 113,247.20 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1121002 MGR.NO. PAGE 001 CONT 6237 SEC 68 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623768001 HWY SH0064 2709 W. FRONT ST. TYLER CNTY RUSK DIST 10 CONTRACT PRICE $ 119,213.60 REPORT DATE 07/03/2012 10.25.16 CONTRACTOR TEXAS TREE & LANDSCAPE, LTD. 12823 EST PERIOD MAR 12,2012 TO MAY 04,2012 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6237-68-001 RMC - 623768001 10 SH0064 RUSK -LIMITS - HENDERSON MAINTENANCE SECTION JACKSONVILLE/RUSK MAINTENANCE SECTION - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 113,247.20