1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12111012 MGR.NO. 770 PAGE 001 CONT 6236 SEC 59 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 623659001 HWY FM2869 2709 W FRONT ST TYLER CNTY WOOD DIST 10 CONTRACT PRICE $ 192,056.62 REPORT DATE 12/21/2012 10.31.10 CONTRACTOR M. CO. 15397 EST PERIOD MAR 06,2012 TO DEC 11,2012 EST NO 010 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN MAR 07, 2012 TIME COMPUTED FROM MAR 06, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 221 270 188 82 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 12 1 1 SATURDAY TOTAL DAYS ALLOWED = 221 2 1 SUNDAY DATE WORK COMPLETED 12/11/12 3 1 DAYS CHARGED TO DATE = 194 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 590 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 281 194 87 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12111012 MGR.NO. 770 PAGE 001 CONT 6236 SEC 59 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 623659001 HWY FM2869 2709 W FRONT ST TYLER CNTY WOOD DIST 10 CONTRACT PRICE $ 192,056.62 REPORT DATE 12/21/2012 10.31.11 CONTRACTOR M. CO. 15397 EST PERIOD MAR 06,2012 TO DEC 11,2012 EST NO 010 & FINAL DIST. 10 COUNTY WOOD CONTROL 6236-59-001 PROJECT RMC - 623659001 HIGHWAY FM2869 0LIMITS- MINEOLA MTCE. WOOD CO. 0TYPE OF WORK- TREE TRIMMING AND BRUSH CONTROL 0 0005 PREPARED BY RHEATIA GANDY 0 0055 TREE TRIMMING & BRUSH CONTROL NET LENGTH155.260 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE TRIMMING/BRUSH REMOVAL MI 155.260 157.230 1,237.000 194,493.51 0 SUBTOTAL BID ITEMS $ 194,493.51 0 TOTAL AMOUNT WORK DONE TREE TRIMMING & BRUSH CONTROL $ 194,493.51 0 TOTAL AMOUNT WORK DONE CONTROL 6236-59-001 $ 194,493.51 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12111012 MGR.NO. 770 PAGE 001 CONT 6236 SEC 59 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 623659001 HWY FM2869 2709 W FRONT ST TYLER CNTY WOOD DIST 10 CONTRACT PRICE $ 192,056.62 REPORT DATE 12/21/2012 10.31.11 CONTRACTOR M. CO. 15397 EST PERIOD MAR 06,2012 TO DEC 11,2012 EST NO 010 & FINAL 0*********************************************************************************************************************************** -LIMITS - MINEOLA MTCE. 0 WOOD CO. DATE WORK BEGAN MAR 7 , 2012 WORKING DAYS USED 194 PERCENT COMPLETE 100.00 PERCENT TIME USED 87.70 DATE COMPLETED DEC 11 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6236-59-001 RMC - 623659001 10 FM2869 WOOD - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE TRIMMING/BRUSH REMOVAL MI 155.260 157.230 1,237.000 194,493.51 0 SUBTOTAL BID ITEMS $ 194,493.51 0 CONTRACT TOTAL ALL ITEMS $ 194,493.51 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12111012 MGR.NO. 770 PAGE 001 CONT 6236 SEC 59 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 623659001 HWY FM2869 2709 W FRONT ST TYLER CNTY WOOD DIST 10 CONTRACT PRICE $ 192,056.62 REPORT DATE 12/21/2012 10.31.11 CONTRACTOR M. CO. 15397 EST PERIOD MAR 06,2012 TO DEC 11,2012 EST NO 010 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 250 RMC - 623659001 6236-59-001 194,493.51 .00 194,493.51 .00 .00 194,493.51 191,401.01 3,092.50 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 194,493.51 .00 194,493.51 .00 .00 194,493.51 191,401.01 3,092.50 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12111012 MGR.NO. 770 PAGE 001 CONT 6236 SEC 59 JOB 001 RES ENGR GANDY, RHEATIA PROJ RMC - 623659001 HWY FM2869 2709 W FRONT ST TYLER CNTY WOOD DIST 10 CONTRACT PRICE $ 192,056.62 REPORT DATE 12/21/2012 10.31.11 CONTRACTOR M. CO. 15397 EST PERIOD MAR 06,2012 TO DEC 11,2012 EST NO 010 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6236-59-001 RMC - 623659001 10 FM2869 WOOD -LIMITS - MINEOLA MTCE. WOOD CO. LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0752 TREE TRIMMING/BRUSH REMOVAL MI 155.260 2.500 1,237.000 3,092.50 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 3,092.50 0 TOTAL AMOUNT WORK DONE TO DATE - $ 194,493.51