1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12111001 MGR.NO. 078 PAGE 001 CONT 6234 SEC 73 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623473001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 190,745.29 REPORT DATE 11/06/2012 10.34.36 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2012 TO OCT 20,2012 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 29, 2012 TIME COMPUTED FROM JUN 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 37 122 57 65 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 12 1 1 RAIN TOTAL DAYS ALLOWED = 37 2 1 TOO WET DATE WORK COMPLETED 08/08/12 3 1 DAYS CHARGED TO DATE = 41 4 1 ASSESSED LIQ DAMAGES = 4 5 1 LIQ DAMAGE RATE $ 590 6 1 SATURDAY 7 1 SUNDAY PHASE II 8 1 CONTRACT WORK DAYS = 32 9 1 ADDL DAYS GRANTED = 0 10 1 TOTAL DAYS ALLOWED = 32 11 1 DATE WORK COMPLETED 10/20/12 12 1 TOO WET DAYS CHARGED TO DATE = 28 13 1 SATURDAY ASSESSED LIQ DAMAGES = 0 14 1 SUNDAY LIQ DAMAGE RATE $ 590 15 1 16 1 CONTRACT TOTALS 17 1 CONTRACT WORK DAYS = 69 18 1 ADDL DAYS GRANTED = 0 19 1 TOTAL DAYS ALLOWED = 69 20 1 WORK COMPLETED AND ACCEPTED DAYS CHARGED TO DATE= 69 ASSESSED LIQ DAMAGES= 4 0 LIQUIDATED DAMAGES 4 DAYS AT $ 590 PER DAY 0 DAYS AT $ 590 PER DAY TOTAL = $ 2,360.00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR 0 ----- ----- ----- 142 69 73 ---------------------------- AREA/PROJECT ENGINEER 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 RAIN 2 TOO WET 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12111001 MGR.NO. 078 PAGE 001 CONT 6234 SEC 73 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623473001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 190,745.29 REPORT DATE 11/06/2012 10.34.37 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2012 TO OCT 20,2012 EST NO 005 & FINAL DIST. 10 COUNTY HENDERSON CONTROL 6234-73-001 PROJECT RMC - 623473001 HIGHWAY SH0031 0LIMITS- VARIOUS ROADWAYS IN THE ATHENS MAINTENANCE SECTION 0TYPE OF WORK- FULL WIDTH MOWING/LITTER REMOVAL 0 0005 PREPARED BY LESLIE WICKHAM 0 0055 MOWING HIGHWAY RIGHT OF WAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 7,633.840 7,633.840 21.870 166,952.08 0065 0734 LITTER REMOVAL AC 3,399.030 3,375.690 7.000 23,629.83 0 SUBTOTAL BID ITEMS $ 190,581.91 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 190,581.91 0 TOTAL AMOUNT WORK DONE CONTROL 6234-73-001 $ 190,581.91 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12111001 MGR.NO. 078 PAGE 001 CONT 6234 SEC 73 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623473001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 190,745.29 REPORT DATE 11/06/2012 10.34.37 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2012 TO OCT 20,2012 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN THE ATHENS 0 MAINTENANCE SECTION DATE WORK BEGAN JUN 29, 2012 WORKING DAYS USED 69 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED OCT 20 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6234-73-001 RMC - 623473001 10 SH0031 HENDERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 7,633.840 7,633.840 21.870 166,952.08 0734 LITTER REMOVAL AC 3,399.030 3,375.690 7.000 23,629.83 0 SUBTOTAL BID ITEMS $ 190,581.91 0 CONTRACT TOTAL ALL ITEMS $ 190,581.91 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12111001 MGR.NO. 078 PAGE 001 CONT 6234 SEC 73 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623473001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 190,745.29 REPORT DATE 11/06/2012 10.34.37 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2012 TO OCT 20,2012 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 108 RMC - 623473001 6234-73-001 190,581.91 .00 190,581.91 .00 2,360.00 188,221.91 146,676.57 41,545.34 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 190,581.91 .00 190,581.91 .00 2,360.00 188,221.91 146,676.57 41,545.34 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12111001 MGR.NO. 078 PAGE 001 CONT 6234 SEC 73 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 623473001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 190,745.29 REPORT DATE 11/06/2012 10.34.37 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2012 TO OCT 20,2012 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6234-73-001 RMC - 623473001 10 SH0031 HENDERSON -LIMITS - VARIOUS ROADWAYS IN THE ATHENS MAINTENANCE SECTION LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 7,633.840 1,899.650 21.870 41,545.35 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 41,545.35 0 TOTAL AMOUNT WORK DONE TO DATE - $ 190,581.91