1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8094004 MGR.NO. PAGE 001 CONT 6196 SEC 78 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619678001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 344,825.00 REPORT DATE 10/04/2010 11.48.34 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD OCT 06,2009 TO SEP 30,2010 EST NO 012 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 06, 2009 TIME COMPUTED FROM OCT 06, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 255 330 231 99 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 10 1 1 TOTAL DAYS ALLOWED = 255 2 1 DATE WORK COMPLETED 09/30/10 3 1 DAYS CHARGED TO DATE = 251 4 1 SATURDAY ASSESSED LIQ DAMAGES = 0 5 1 SUNDAY LIQ DAMAGE RATE $ 500 6 1 HOLIDAY 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 SATURDAY 19 1 SUNDAY 20 1 21 1 22 1 23 1 24 1 25 1 SATURDAY 26 1 SUNDAY 27 1 28 1 29 1 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 360 251 109 4 SATURDAY 4 SUNDAY 1 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8094004 MGR.NO. PAGE 001 CONT 6196 SEC 78 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619678001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 344,825.00 REPORT DATE 10/04/2010 11.48.34 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD OCT 06,2009 TO SEP 30,2010 EST NO 012 & FINAL DIST. 10 COUNTY SMITH CONTROL 6196-78-001 PROJECT RMC - 619678001 HIGHWAY US0069 0LIMITS- VARIOUS ROADWAYS WITHIN THE TYLER DISTRICT 0TYPE OF WORK- PAINT AND BEAD STRIPING 0 0005 PREPARED BY LESLIE WICKHAM 0 0055 PAINT AND BEAD STRIPING NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REF PAV MRK TY II (W) 4" (BRK) LF 50,000.000 122,332.000 .120 14,679.84 0065 0666 REF PAV MRK TY II (W) 4" (SLD) LF 700,000.000 1,374,547.000 .080 109,963.76 0070 0666 REF PAV MRK TY II (W) 8" (SLD) LF 5,000.000 15,259.000 .400 6,103.60 0075 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 200,000.000 126,470.000 .110 13,911.70 0080 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 3,045,000.000 2,063,705.000 .085 175,414.93 0 SUBTOTAL BID ITEMS $ 320,073.83 0 TOTAL AMOUNT WORK DONE PAINT AND BEAD STRIPING $ 320,073.83 0 TOTAL AMOUNT WORK DONE CONTROL 6196-78-001 $ 320,073.83 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8094004 MGR.NO. PAGE 001 CONT 6196 SEC 78 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619678001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 344,825.00 REPORT DATE 10/04/2010 11.48.35 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD OCT 06,2009 TO SEP 30,2010 EST NO 012 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS WITHIN THE TYLER 0 DISTRICT DATE WORK BEGAN OCT 6 , 2009 WORKING DAYS USED 251 PERCENT COMPLETE 100.00 PERCENT TIME USED 98.40 DATE COMPLETED SEP 30 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6196-78-001 RMC - 619678001 10 US0069 SMITH - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0666 REF PAV MRK TY II (W) 4" (BRK) LF 50,000.000 122,332.000 .120 14,679.84 0666 REF PAV MRK TY II (W) 4" (SLD) LF 700,000.000 1,374,547.000 .080 109,963.76 0666 REF PAV MRK TY II (W) 8" (SLD) LF 5,000.000 15,259.000 .400 6,103.60 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 200,000.000 126,470.000 .110 13,911.70 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 3,045,000.000 2,063,705.000 .085 175,414.93 0 SUBTOTAL BID ITEMS $ 320,073.83 0 CONTRACT TOTAL ALL ITEMS $ 320,073.83 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8094004 MGR.NO. PAGE 001 CONT 6196 SEC 78 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619678001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 344,825.00 REPORT DATE 10/04/2010 11.48.35 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD OCT 06,2009 TO SEP 30,2010 EST NO 012 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 212 RMC - 619678001 6196-78-001 320,073.83 .00 320,073.83 .00 .00 320,073.83 320,073.83 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 320,073.83 .00 320,073.83 .00 .00 320,073.83 320,073.83 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8094004 MGR.NO. PAGE 001 CONT 6196 SEC 78 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619678001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 344,825.00 REPORT DATE 10/04/2010 11.48.36 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD OCT 06,2009 TO SEP 30,2010 EST NO 012 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6196-78-001 RMC - 619678001 10 US0069 SMITH -LIMITS - VARIOUS ROADWAYS WITHIN THE TYLER DISTRICT - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 320,073.83