1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6094005 MGR.NO. PAGE 001 CONT 6194 SEC 89 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619489001 HWY US0271 2709 W. FRONT TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 1,310,310.00 REPORT DATE 09/03/2010 14.31.22 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 13,2009 TO AUG 16,2010 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 13, 2009 TIME COMPUTED FROM AUG 17, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 255 353 244 109 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 10 1 1 SUNDAY TOTAL DAYS ALLOWED = 255 2 1 DATE WORK COMPLETED 08/16/10 3 1 DAYS CHARGED TO DATE = 254 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 625 6 1 7 1 SATURDAY LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 625 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 SATURDAY 15 1 SUNDAY 16 1 WORK COMPLETED AND ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 369 254 115 2 SATURDAY 3 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6094005 MGR.NO. PAGE 001 CONT 6194 SEC 89 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619489001 HWY US0271 2709 W. FRONT TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 1,310,310.00 REPORT DATE 09/03/2010 14.31.22 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 13,2009 TO AUG 16,2010 EST NO 013 & FINAL DIST. 10 COUNTY SMITH CONTROL 6194-89-001 PROJECT RMC - 619489001 HIGHWAY US0271 0LIMITS- VARIOUS LOCATIONS WITHIN THE TYLER DISTRICT 0TYPE OF WORK- LONG LINE THERMO 0 0005 PREPARED BY LESLIE WICKHAM 0 0055 THERMOPLASTIC STRIPING NET LENGTH 0.100 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REFL PAV MRK TY I (W) 4" (BRK)(060MIL) LF 150,000.000 136,650.000 .120 16,398.00 0065 0666 REFL PAV MRK TY I (W) 4" (SLD)(060MIL) LF 2,548,000.000 4,151,789.000 .120 498,214.68 0070 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 40,000.000 35,097.000 .200 7,019.40 0075 0666 REFL PAV MRK TY I (Y) 4" (BRK)(060MIL) LF 600,000.000 415,731.000 .130 54,045.03 0080 0666 REFL PAV MRK TY I (Y) 4" (SLD)(060MIL) LF 5,600,000.000 5,544,617.000 .130 720,800.21 0085 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 50,000.000 0.000 .170 .00 0090 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 265,000.000 0.000 .170 .00 0095 0666 REFL PAV MRK TY I (W) 8" (SLD)(100MIL) LF 7,000.000 0.000 .400 .00 0100 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 40,000.000 7,520.000 .180 1,353.60 0105 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 600,000.000 73,782.000 .180 13,280.76 0110 0677 ELIM EXT PAV MRK & MRKS ( 4") LF 1,000.000 0.000 1.000 .00 0 SUBTOTAL BID ITEMS $ 1,311,111.68 0 TOTAL AMOUNT WORK DONE THERMOPLASTIC STRIPING $ 1,311,111.68 0 TOTAL AMOUNT WORK DONE CONTROL 6194-89-001 $ 1,311,111.68 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6094005 MGR.NO. PAGE 001 CONT 6194 SEC 89 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619489001 HWY US0271 2709 W. FRONT TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 1,310,310.00 REPORT DATE 09/03/2010 14.31.23 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 13,2009 TO AUG 16,2010 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS WITHIN THE TYLER 0 DISTRICT DATE WORK BEGAN AUG 13, 2009 WORKING DAYS USED 254 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.60 DATE COMPLETED AUG 16 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6194-89-001 RMC - 619489001 10 US0271 SMITH - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0666 REFL PAV MRK TY I (W) 4" (BRK)(060MIL) LF 150,000.000 136,650.000 .120 16,398.00 0666 REFL PAV MRK TY I (W) 4" (SLD)(060MIL) LF 2,548,000.000 4,151,789.000 .120 498,214.68 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 40,000.000 35,097.000 .200 7,019.40 0666 REFL PAV MRK TY I (Y) 4" (BRK)(060MIL) LF 600,000.000 415,731.000 .130 54,045.03 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 40,000.000 7,520.000 .180 1,353.60 0666 REFL PAV MRK TY I (Y) 4" (SLD)(060MIL) LF 5,600,000.000 5,544,617.000 .130 720,800.21 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 600,000.000 73,782.000 .180 13,280.76 0 SUBTOTAL BID ITEMS $ 1,311,111.68 0 CONTRACT TOTAL ALL ITEMS $ 1,311,111.68 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6094005 MGR.NO. PAGE 001 CONT 6194 SEC 89 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619489001 HWY US0271 2709 W. FRONT TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 1,310,310.00 REPORT DATE 09/03/2010 14.31.23 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 13,2009 TO AUG 16,2010 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 212 RMC - 619489001 6194-89-001 1,311,111.68 .00 1,311,111.68 .00 .00 1,311,111.68 1,166,879.93 144,231.75 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 1,311,111.68 .00 1,311,111.68 .00 .00 1,311,111.68 1,166,879.93 144,231.75 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6094005 MGR.NO. PAGE 001 CONT 6194 SEC 89 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 619489001 HWY US0271 2709 W. FRONT TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 1,310,310.00 REPORT DATE 09/03/2010 14.31.23 CONTRACTOR STRIPING TECHNOLOGY, L.P. 12338 EST PERIOD AUG 13,2009 TO AUG 16,2010 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6194-89-001 RMC - 619489001 10 US0271 SMITH -LIMITS - VARIOUS LOCATIONS WITHIN THE TYLER DISTRICT LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0666 REFL PAV MRK TY I (W) 4" LF 150,000.000 24,780.000 0.120 2,973.60 (BRK)(060MIL) 65 0666 REFL PAV MRK TY I (W) 4" LF 2,548,000.000 512,280.000 0.120 61,473.60 (SLD)(060MIL) 70 0666 REFL PAV MRK TY I (W) 8" LF 40,000.000 2,738.000 0.200 547.60 (SLD)(060MIL) 75 0666 REFL PAV MRK TY I (Y) 4" LF 600,000.000 45,140.000 0.130 5,868.20 (BRK)(060MIL) 80 0666 REFL PAV MRK TY I (Y) 4" LF 5,600,000.000 564,375.000 0.130 73,368.75 (SLD)(060MIL) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 144,231.75 0 TOTAL AMOUNT WORK DONE TO DATE - $ 1,311,111.68