1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12081001 MGR.NO. PAGE 001 CONT 6186 SEC 92 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 618692001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 172,919.92 REPORT DATE 01/05/2010 14.21.33 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2009 TO DEC 18,2009 EST NO 007 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 11, 2009 TIME COMPUTED FROM JUN 01, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 37 183 54 129 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 09 1 1 TOO WET TOTAL DAYS ALLOWED = 37 2 1 RAIN DATE WORK COMPLETED 08/04/09 3 1 TOO WET DAYS CHARGED TO DATE = 36 4 1 TOO WET ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 400 6 1 SUNDAY 7 1 RAIN PHASE II 8 1 RAIN CONTRACT WORK DAYS = 32 9 1 TOO WET ADDL DAYS GRANTED = 0 10 1 TOTAL DAYS ALLOWED = 32 11 1 DATE WORK COMPLETED 12/18/09 12 1 SATURDAY DAYS CHARGED TO DATE = 20 13 1 SUNDAY ASSESSED LIQ DAMAGES = 0 14 1 TOO WET LIQ DAMAGE RATE $ 400 15 1 TOO WET 16 1 TOO WET CONTRACT TOTALS 17 1 TOO WET CONTRACT WORK DAYS = 69 18 1 WORK COMPLETED AND ACCEPTED ADDL DAYS GRANTED = 0 TOTAL DAYS ALLOWED = 69 DAYS CHARGED TO DATE= 56 ASSESSED LIQ DAMAGES= 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR 0 ----- ----- ----- 201 56 145 ---------------------------- AREA/PROJECT ENGINEER 2 SATURDAY 2 SUNDAY 0 HOLIDAY 8 TOO WET 3 RAIN 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12081001 MGR.NO. PAGE 001 CONT 6186 SEC 92 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 618692001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 172,919.92 REPORT DATE 01/05/2010 14.21.34 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2009 TO DEC 18,2009 EST NO 007 & FINAL DIST. 10 COUNTY HENDERSON CONTROL 6186-92-001 PROJECT RMC - 618692001 HIGHWAY SH0031 0LIMITS- VARIOUS ROADWAYS IN THE ATHENS MAINTENANCE SECTION 0TYPE OF WORK- ROW MOWING 0 0005 PREPARED BY LESLIE WICKHAM 0 0055 MOWING HIGHWAY RIGHT OF WAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 7,637.840 7,637.840 19.960 152,451.29 0065 0734 LITTER REMOVAL AC 2,924.090 2,924.090 7.000 20,468.63 0 SUBTOTAL BID ITEMS $ 172,919.92 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 172,919.92 0 TOTAL AMOUNT WORK DONE CONTROL 6186-92-001 $ 172,919.92 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12081001 MGR.NO. PAGE 001 CONT 6186 SEC 92 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 618692001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 172,919.92 REPORT DATE 01/05/2010 14.21.34 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2009 TO DEC 18,2009 EST NO 007 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN THE ATHENS 0 MAINTENANCE SECTION DATE WORK BEGAN JUN 11, 2009 WORKING DAYS USED 56 PERCENT COMPLETE 100.00 PERCENT TIME USED 81.10 DATE COMPLETED DEC 18 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6186-92-001 RMC - 618692001 10 SH0031 HENDERSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 7,637.840 7,637.840 19.960 152,451.29 0734 LITTER REMOVAL AC 2,924.090 2,924.090 7.000 20,468.63 0 SUBTOTAL BID ITEMS $ 172,919.92 0 CONTRACT TOTAL ALL ITEMS $ 172,919.92 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12081001 MGR.NO. PAGE 001 CONT 6186 SEC 92 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 618692001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 172,919.92 REPORT DATE 01/05/2010 14.21.34 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2009 TO DEC 18,2009 EST NO 007 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 108 RMC - 618692001 6186-92-001 172,919.92 .00 172,919.92 .00 .00 172,919.92 142,555.77 30,364.15 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 172,919.92 .00 172,919.92 .00 .00 172,919.92 142,555.77 30,364.15 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12081001 MGR.NO. PAGE 001 CONT 6186 SEC 92 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 618692001 HWY SH0031 2709 W. FRONT ST. TYLER CNTY HENDERSON DIST 10 CONTRACT PRICE $ 172,919.92 REPORT DATE 01/05/2010 14.21.34 CONTRACTOR C & C MOWING CONTRACTORS, INC. 7284 EST PERIOD JUN 01,2009 TO DEC 18,2009 EST NO 007 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6186-92-001 RMC - 618692001 10 SH0031 HENDERSON -LIMITS - VARIOUS ROADWAYS IN THE ATHENS MAINTENANCE SECTION LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 7,637.840 1,521.250 19.960 30,364.15 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 30,364.15 0 TOTAL AMOUNT WORK DONE TO DATE - $ 172,919.92