1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4091004 MGR.NO. 070 PAGE 001 CONT 6183 SEC 50 JOB 001 RES ENGR SCHNEIDER, PAUL PROJ BPM - 618350001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 170,170.00 REPORT DATE 09/03/2009 09.11.21 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUN 01,2009 TO AUG 22,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 12, 2009 TIME COMPUTED FROM JUN 01, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 70 61 52 9 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 TOTAL DAYS ALLOWED = 70 2 1 SUNDAY DATE WORK COMPLETED 08/22/09 3 1 DAYS CHARGED TO DATE = 70 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 SUNDAY ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 WORK COMPLETED AND ACCEPTED - - - ----- ----- ----- 83 70 13 0 SATURDAY 3 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4091004 MGR.NO. 070 PAGE 001 CONT 6183 SEC 50 JOB 001 RES ENGR SCHNEIDER, PAUL PROJ BPM - 618350001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 170,170.00 REPORT DATE 09/03/2009 09.11.22 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUN 01,2009 TO AUG 22,2009 EST NO 003 & FINAL DIST. 10 COUNTY SMITH CONTROL 6183-50-001 PROJECT BPM - 618350001 HIGHWAY US0069 0LIMITS- VARIOUS STRUCTURES IN SMITH AND HENDERSON COUNTIES 0TYPE OF WORK- BRIDGE PREVENTIVE MAINTENANCE 0 0005 PREPARED BY PAUL SCHNEIDER, P.E. 0 0055 MISCELLANEOUS BRIDGE REPAIRS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0104 REMOVING CONC (RIPRAP) SY 67.000 67.000 50.000 3,350.00 0065 0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 427.000 563.000 50.000 28,150.00 0070 0164 BROADCAST SEED (TEMP) (WARM) SY 100.000 100.000 10.000 1,000.00 0075 0164 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 100.000 0.000 10.000 .00 0080 0168 VEGETATIVE WATERING MG 2.200 0.000 150.000 .00 0085 0401 FLOWABLE BACKFILL CY 197.000 45.000 100.000 4,500.00 0090 0432 RIPRAP (STONE COMMON)(DRY)(18 IN) CY 967.000 899.000 80.000 71,920.00 0095 0432 RIPRAP (CONC)(CL B)(5 IN) CY 8.000 10.000 500.000 5,000.00 0100 0466 WINGWALL (FW-0)(HW=11 FT) EA 1.000 1.000 10,000.000 10,000.00 0105 0480 CLEAN EXIST CULVS EA 14.000 15.000 1,000.000 15,000.00 0110 0500 MOBILIZATION LS 1.000 1.000 5,000.000 5,000.00 0115 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 3,500.000 10,500.00 0120 0506 TEMPORARY SEDIMENT CONTROL FENCE LF 200.000 0.000 10.000 .00 0125 0438 CLEAN AND SEAL CRACKS LF 29.000 29.000 20.000 580.00 0 SUBTOTAL BID ITEMS $ 155,000.00 0 TOTAL AMOUNT WORK DONE MISCELLANEOUS BRIDGE REPAIRS $ 155,000.00 0 TOTAL AMOUNT WORK DONE CONTROL 6183-50-001 $ 155,000.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4091004 MGR.NO. 070 PAGE 001 CONT 6183 SEC 50 JOB 001 RES ENGR SCHNEIDER, PAUL PROJ BPM - 618350001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 170,170.00 REPORT DATE 09/03/2009 09.11.22 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUN 01,2009 TO AUG 22,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS STRUCTURES IN SMITH AND 0 HENDERSON COUNTIES DATE WORK BEGAN JUN 12, 2009 WORKING DAYS USED 70 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 22 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6183-50-001 BPM - 618350001 10 US0069 SMITH - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (RIPRAP) SY 67.000 67.000 50.000 3,350.00 0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 427.000 563.000 50.000 28,150.00 0164 BROADCAST SEED (TEMP) (WARM) SY 100.000 100.000 10.000 1,000.00 0401 FLOWABLE BACKFILL CY 197.000 45.000 100.000 4,500.00 0432 RIPRAP (STONE COMMON)(DRY)(18 IN) CY 967.000 899.000 80.000 71,920.00 0432 RIPRAP (CONC)(CL B)(5 IN) CY 8.000 10.000 500.000 5,000.00 0438 CLEAN AND SEAL CRACKS LF 29.000 29.000 20.000 580.00 0466 WINGWALL (FW-0)(HW=11 FT) EA 1.000 1.000 10,000.000 10,000.00 0480 CLEAN EXIST CULVS EA 14.000 15.000 1,000.000 15,000.00 0500 MOBILIZATION LS 1.000 1.000 5,000.000 5,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 3,500.000 10,500.00 0 SUBTOTAL BID ITEMS $ 155,000.00 0 CONTRACT TOTAL ALL ITEMS $ 155,000.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4091004 MGR.NO. 070 PAGE 001 CONT 6183 SEC 50 JOB 001 RES ENGR SCHNEIDER, PAUL PROJ BPM - 618350001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 170,170.00 REPORT DATE 09/03/2009 09.11.22 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUN 01,2009 TO AUG 22,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 212 BPM - 618350001 6183-50-001 155,000.00 .00 155,000.00 .00 .00 155,000.00 35,490.00 119,510.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 155,000.00 .00 155,000.00 .00 .00 155,000.00 35,490.00 119,510.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4091004 MGR.NO. 070 PAGE 001 CONT 6183 SEC 50 JOB 001 RES ENGR SCHNEIDER, PAUL PROJ BPM - 618350001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 170,170.00 REPORT DATE 09/03/2009 09.11.22 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD JUN 01,2009 TO AUG 22,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6183-50-001 BPM - 618350001 10 US0069 SMITH -LIMITS - VARIOUS STRUCTURES IN SMITH AND HENDERSON COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0104 REMOVING CONC (RIPRAP) SY 67.000 67.000 50.000 3,350.00 65 0132 EMBANKMENT (FINAL)(ORD CY 427.000 458.000 50.000 22,900.00 COMP)(TY B) 70 0164 BROADCAST SEED (TEMP) (WARM) SY 100.000 100.000 10.000 1,000.00 85 0401 FLOWABLE BACKFILL CY 197.000 45.000 100.000 4,500.00 90 0432 RIPRAP (STONE CY 967.000 771.000 80.000 61,680.00 COMMON)(DRY)(18 IN) 95 0432 RIPRAP (CONC)(CL B)(5 IN) CY 8.000 10.000 500.000 5,000.00 125 0438 CLEAN AND SEAL CRACKS LF 29.000 29.000 20.000 580.00 105 0480 CLEAN EXIST CULVS EA 14.000 12.000 1,000.000 12,000.00 110 0500 MOBILIZATION LS 1.000 1.000 5,000.000 5,000.00 115 0502 BARRICADES, SIGNS AND MO 3.000 1.000 3,500.000 3,500.00 TRAFFIC HANDLING --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 119,510.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 155,000.00