1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7084008 MGR.NO. PAGE 001 CONT 6179 SEC 44 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 617944001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 319,369.67 REPORT DATE 12/03/2009 07.16.40 CONTRACTOR R. K. HALL CONSTRUCTION, LTD. 12822 EST PERIOD NOV 03,2008 TO NOV 19,2009 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 17, 2008 TIME COMPUTED FROM NOV 03, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 310 363 295 68 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 09 1 1 SUNDAY TOTAL DAYS ALLOWED = 310 2 1 DATE WORK COMPLETED 11/19/09 3 1 DAYS CHARGED TO DATE = 310 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SUNDAY 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 WORK COMPLETED AND ACCEPTED - - - - ----- ----- ----- 382 310 72 0 SATURDAY 3 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7084008 MGR.NO. PAGE 001 CONT 6179 SEC 44 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 617944001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 319,369.67 REPORT DATE 12/03/2009 07.16.41 CONTRACTOR R. K. HALL CONSTRUCTION, LTD. 12822 EST PERIOD NOV 03,2008 TO NOV 19,2009 EST NO 013 & FINAL DIST. 10 COUNTY SMITH CONTROL 6179-44-001 PROJECT RMC - 617944001 HIGHWAY US0069 0LIMITS- TREE REMOVAL IN THE SOUTH AND NORTH TYLER MAINTENANCE SECTIONS 0TYPE OF WORK- TREE REMOVAL 0 0005 PREPARED BY LESLIE WICKHAM 0 0055 TREE REMOVAL NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0752 TREE REMOVAL (4"-12" DIA) EA 4,058.000 3,670.000 27.880 102,319.60 0065 0752 TREE REMOVAL (12"-18" DIA) EA 1,836.000 1,415.000 55.760 78,900.40 0070 0752 TREE REMOVAL (18"-24" DIA) EA 721.000 540.000 66.910 36,131.40 0075 0752 TREE REMOVAL (24"-30" DIA) EA 328.000 213.000 111.510 23,751.63 0080 0752 TREE REMOVAL (30"-36" DIA) EA 114.000 110.000 83.630 9,199.30 0085 0752 TREE REMOVAL (36"-42" DIA) EA 67.000 59.000 83.630 4,934.17 0090 0752 TREE REMOVAL (42"-48" DIA) EA 20.000 18.000 111.510 2,007.18 0095 0752 TREE REMOVAL (48"-60" DIA) EA 12.000 8.000 111.510 892.08 0100 0752 TREE REMOVAL (60"-72" DIA) EA 3.000 4.000 111.510 446.04 0 SUBTOTAL BID ITEMS $ 258,581.80 0 TOTAL AMOUNT WORK DONE TREE REMOVAL $ 258,581.80 0 TOTAL AMOUNT WORK DONE CONTROL 6179-44-001 $ 258,581.80 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7084008 MGR.NO. PAGE 001 CONT 6179 SEC 44 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 617944001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 319,369.67 REPORT DATE 12/03/2009 07.16.41 CONTRACTOR R. K. HALL CONSTRUCTION, LTD. 12822 EST PERIOD NOV 03,2008 TO NOV 19,2009 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - TREE REMOVAL IN THE SOUTH AND NORTH 0 TYLER MAINTENANCE SECTIONS DATE WORK BEGAN NOV 17, 2008 WORKING DAYS USED 310 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED NOV 19 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6179-44-001 RMC - 617944001 10 US0069 SMITH - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE REMOVAL (4"-12" DIA) EA 4,058.000 3,670.000 27.880 102,319.60 0752 TREE REMOVAL (12"-18" DIA) EA 1,836.000 1,415.000 55.760 78,900.40 0752 TREE REMOVAL (18"-24" DIA) EA 721.000 540.000 66.910 36,131.40 0752 TREE REMOVAL (24"-30" DIA) EA 328.000 213.000 111.510 23,751.63 0752 TREE REMOVAL (30"-36" DIA) EA 114.000 110.000 83.630 9,199.30 0752 TREE REMOVAL (36"-42" DIA) EA 67.000 59.000 83.630 4,934.17 0752 TREE REMOVAL (42"-48" DIA) EA 20.000 18.000 111.510 2,007.18 0752 TREE REMOVAL (48"-60" DIA) EA 12.000 8.000 111.510 892.08 0752 TREE REMOVAL (60"-72" DIA) EA 3.000 4.000 111.510 446.04 0 SUBTOTAL BID ITEMS $ 258,581.80 0 CONTRACT TOTAL ALL ITEMS $ 258,581.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7084008 MGR.NO. PAGE 001 CONT 6179 SEC 44 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 617944001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 319,369.67 REPORT DATE 12/03/2009 07.16.41 CONTRACTOR R. K. HALL CONSTRUCTION, LTD. 12822 EST PERIOD NOV 03,2008 TO NOV 19,2009 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 212 RMC - 617944001 6179-44-001 258,581.80 .00 258,581.80 .00 .00 258,581.80 251,991.05 6,590.75 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 258,581.80 .00 258,581.80 .00 .00 258,581.80 251,991.05 6,590.75 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7084008 MGR.NO. PAGE 001 CONT 6179 SEC 44 JOB 001 RES ENGR WICKHAM, LESLIE PROJ RMC - 617944001 HWY US0069 2709 W. FRONT ST. TYLER CNTY SMITH DIST 10 CONTRACT PRICE $ 319,369.67 REPORT DATE 12/03/2009 07.16.41 CONTRACTOR R. K. HALL CONSTRUCTION, LTD. 12822 EST PERIOD NOV 03,2008 TO NOV 19,2009 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6179-44-001 RMC - 617944001 10 US0069 SMITH -LIMITS - TREE REMOVAL IN THE SOUTH AND NORTH TYLER MAINTENANCE SECTIONS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0752 TREE REMOVAL (4"-12" DIA) EA 4,058.000 12.000 27.880 334.56 65 0752 TREE REMOVAL (12"-18" DIA) EA 1,836.000 89.000 55.760 4,962.64 70 0752 TREE REMOVAL (18"-24" DIA) EA 721.000 11.000 66.910 736.01 75 0752 TREE REMOVAL (24"-30" DIA) EA 328.000 2.000 111.510 223.02 80 0752 TREE REMOVAL (30"-36" DIA) EA 114.000 4.000 83.630 334.52 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 6,590.75 0 TOTAL AMOUNT WORK DONE TO DATE - $ 258,581.80