1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8130708 MGR.NO. 053 PAGE 001 CONT 6264 SEC 24 JOB 001 RES ENGR PETERSON, DONALD PROJ SUP - 626424001 HWY FM2105 2802 ARMSTRONG SAN ANGELO CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 34,320.00 REPORT DATE 07/07/2014 09.30.37 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 010 BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2013 TIME COMPUTED FROM SEP 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 273 273 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 14 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 303 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 303 303 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8130708 MGR.NO. 053 PAGE 001 CONT 6264 SEC 24 JOB 001 RES ENGR PETERSON, DONALD PROJ SUP - 626424001 HWY FM2105 2802 ARMSTRONG SAN ANGELO CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 34,320.00 REPORT DATE 07/07/2014 09.30.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 010 BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 DIST. 07 COUNTY TOM GREEN CONTROL 6264-24-001 PROJECT SUP - 626424001 HIGHWAY FM2105 0LIMITS- RURAL TOM GREEN COUNTY ROADS RURAL TOM GREEN COUNTY ROADS 0TYPE OF WORK- LITTER PICKUP RURAL TOM GREEN COUNTY 0 0050 PREPARED BY DISTRICT MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0734 LITTER REMOVAL - TRACT (1) AC 2,080.000 1,560.000 16.500 25,740.00 0 SUBTOTAL BID ITEMS $ 25,740.00 0 TOTAL AMOUNT WORK DONE PREPARED BY DISTRICT MAINTENANCE $ 25,740.00 0 TOTAL AMOUNT WORK DONE CONTROL 6264-24-001 $ 25,740.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8130708 MGR.NO. 053 PAGE 001 CONT 6264 SEC 24 JOB 001 RES ENGR PETERSON, DONALD PROJ SUP - 626424001 HWY FM2105 2802 ARMSTRONG SAN ANGELO CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 34,320.00 REPORT DATE 07/07/2014 09.30.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 010 BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 0*********************************************************************************************************************************** -LIMITS - RURAL TOM GREEN COUNTY ROADS 0 RURAL TOM GREEN COUNTY ROADS DATE WORK BEGAN SEP 1 , 2013 WORKING DAYS USED 303 PERCENT COMPLETE 75.00 PERCENT TIME USED 41.50 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6264-24-001 SUP - 626424001 07 FM2105 TOM GREEN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) AC 2,080.000 1,560.000 16.500 25,740.00 0 SUBTOTAL BID ITEMS $ 25,740.00 0 CONTRACT TOTAL ALL ITEMS $ 25,740.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8130708 MGR.NO. 053 PAGE 001 CONT 6264 SEC 24 JOB 001 RES ENGR PETERSON, DONALD PROJ SUP - 626424001 HWY FM2105 2802 ARMSTRONG SAN ANGELO CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 34,320.00 REPORT DATE 07/07/2014 09.30.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 010 BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 226 SUP - 626424001 6264-24-001 25,740.00 .00 25,740.00 .00 .00 25,740.00 25,740.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 25,740.00 .00 25,740.00 .00 .00 25,740.00 25,740.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8130708 MGR.NO. 053 PAGE 001 CONT 6264 SEC 24 JOB 001 RES ENGR PETERSON, DONALD PROJ SUP - 626424001 HWY FM2105 2802 ARMSTRONG SAN ANGELO CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 34,320.00 REPORT DATE 07/07/2014 09.30.38 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 010 BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED 15227 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6264-24-001 SUP - 626424001 07 FM2105 TOM GREEN -LIMITS - RURAL TOM GREEN COUNTY ROADS RURAL TOM GREEN COUNTY ROADS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 25,740.00