1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7124011 MGR.NO. 053 PAGE 001 CONT 6243 SEC 74 JOB 001 RES ENGR PETERSON, DONALD PROJ RMC - 624374001 HWY FM2111 2802 ARMSTRONG SAN ANGELO CNTY RUNNELS DIST 07 CONTRACT PRICE $ 645,686.20 REPORT DATE 05/02/2013 16.57.36 CONTRACTOR LONE WOLF CONSTRUCTION, LLC 14674 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 007 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 03, 2012 TIME COMPUTED FROM OCT 03, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 49 180 109 71 BROUGHT FORWARD ADDL DAYS GRANTED = 25 APR 13 1 1 TOTAL DAYS ALLOWED = 74 2 1 DATE WORK COMPLETED 3 1 TOO WET DAYS CHARGED TO DATE = 129 4 1 TOO WET ASSESSED LIQ DAMAGES = 55 5 1 LIQ DAMAGE RATE $ 610 6 1 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 55 DAYS AT $ 610 PER DAY 9 1 TOTAL = $ 33,550.00 10 1 TOO WET 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 TOO WET 19 1 20 1 21 1 SUNDAY 22 1 23 1 24 1 25 1 26 1 27 1 SATURDAY 28 1 SUNDAY 29 1 30 1 0 ----- ----- ----- 210 129 81 2 SATURDAY 4 SUNDAY 0 HOLIDAY 4 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7124011 MGR.NO. 053 PAGE 001 CONT 6243 SEC 74 JOB 001 RES ENGR PETERSON, DONALD PROJ RMC - 624374001 HWY FM2111 2802 ARMSTRONG SAN ANGELO CNTY RUNNELS DIST 07 CONTRACT PRICE $ 645,686.20 REPORT DATE 05/02/2013 16.57.37 CONTRACTOR LONE WOLF CONSTRUCTION, LLC 14674 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 007 DIST. 07 COUNTY RUNNELS CONTROL 6243-74-001 PROJECT RMC - 624374001 HIGHWAY FM2111 0LIMITS- SH 158 IN RUNNELS COUNTY 4 MILES NORTH OF SH 158 0TYPE OF WORK- ADDING/WIDENING PAVEMENT 0 0005 SAN ANGELO AREA OFFICE-TAM 0 0055 WIDENING AND REPAIR OF EXISTING ROA NET LENGTH 4.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0112 SUBGRADE WIDENING (ORD COMP) STA 422.000 422.000 220.000 92,840.00 0062 0132*EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 4,700.000 4,997.000 6.000 29,982.00 0064 0247*FL BS (CMP IN PLC)(TY A GR 1)(FNAL POS) CY 8,909.000 7,982.330 44.600 356,011.92 0065 0247 FL BS (CMP IN PLC)(TY A GR 4)(FNAL POS) CY 8,909.000 0.000 44.600 .00 0070 0310 PRIME COAT (MC-30) GAL 5,632.000 3,995.000 4.600 18,377.00 0075 0316 AGGR(TY-PB GR-4 SAC-B) CY 256.000 137.000 92.000 12,604.00 0080 0316 ASPH(AC-3 OR AC-5) GAL 9,856.000 5,350.000 3.850 20,597.50 0085 0500 MOBILIZATION LS 1.000 0.900 48,000.000 43,200.00 0090 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 5.000 6,700.000 33,500.00 0090 0502 ADJ EST QUANTITY TO DATE 5.000 0 SUBTOTAL BID ITEMS $ 607,112.42 0 TOTAL AMOUNT WORK DONE WIDENING AND REPAIR OF EXISTING ROA $ 607,112.42 0 TOTAL AMOUNT WORK DONE CONTROL 6243-74-001 $ 607,112.42 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7124011 MGR.NO. 053 PAGE 001 CONT 6243 SEC 74 JOB 001 RES ENGR PETERSON, DONALD PROJ RMC - 624374001 HWY FM2111 2802 ARMSTRONG SAN ANGELO CNTY RUNNELS DIST 07 CONTRACT PRICE $ 645,686.20 REPORT DATE 05/02/2013 16.57.37 CONTRACTOR LONE WOLF CONSTRUCTION, LLC 14674 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 007 0*********************************************************************************************************************************** -LIMITS - SH 158 IN RUNNELS COUNTY 0 4 MILES NORTH OF SH 158 DATE WORK BEGAN OCT 3 , 2012 WORKING DAYS USED 129 PERCENT COMPLETE 94.02 PERCENT TIME USED 174.30 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6243-74-001 RMC - 624374001 07 FM2111 RUNNELS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0112 SUBGRADE WIDENING (ORD COMP) STA 422.000 422.000 220.000 92,840.00 0310 PRIME COAT (MC-30) GAL 5,632.000 3,995.000 4.600 18,377.00 0316 AGGR(TY-PB GR-4 SAC-B) CY 256.000 137.000 92.000 12,604.00 0316 ASPH(AC-3 OR AC-5) GAL 9,856.000 5,350.000 3.850 20,597.50 0500 MOBILIZATION LS 1.000 .900 48,000.000 43,200.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 5.000 6,700.000 33,500.00 0502* ADJ EST QUANTITY TO DATE 5.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00132* EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 4,700.000 4,997.000 6.000 29,982.00 0247* FL BS (CMP IN PLC)(TY A GR 1)(FNAL POS) CY 8,909.000 7,982.330 44.600 356,011.92 0 SUBTOTAL BID ITEMS $ 607,112.42 0 CONTRACT TOTAL ALL ITEMS $ 607,112.42 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7124011 MGR.NO. 053 PAGE 001 CONT 6243 SEC 74 JOB 001 RES ENGR PETERSON, DONALD PROJ RMC - 624374001 HWY FM2111 2802 ARMSTRONG SAN ANGELO CNTY RUNNELS DIST 07 CONTRACT PRICE $ 645,686.20 REPORT DATE 05/02/2013 16.57.37 CONTRACTOR LONE WOLF CONSTRUCTION, LLC 14674 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 007 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 200 RMC - 624374001 6243-74-001 607,112.42 .00 607,112.42 .00 33,550.00 573,562.42 472,105.90 101,456.52 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 607,112.42 .00 607,112.42 .00 33,550.00 573,562.42 472,105.90 101,456.52 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7124011 MGR.NO. 053 PAGE 001 CONT 6243 SEC 74 JOB 001 RES ENGR PETERSON, DONALD PROJ RMC - 624374001 HWY FM2111 2802 ARMSTRONG SAN ANGELO CNTY RUNNELS DIST 07 CONTRACT PRICE $ 645,686.20 REPORT DATE 05/02/2013 16.57.37 CONTRACTOR LONE WOLF CONSTRUCTION, LLC 14674 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 007 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6243-74-001 RMC - 624374001 07 FM2111 RUNNELS -LIMITS - SH 158 IN RUNNELS COUNTY 4 MILES NORTH OF SH 158 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0112 SUBGRADE WIDENING (ORD COMP) STA 422.000 83.000 220.000 18,260.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 62 0132* EMBANKMENT (FINAL)(ORD CY 0.000 1,900.000 6.000 11,400.00 COMP)(TY B) 64 0247* FL BS (CMP IN PLC)(TY A GR CY 0.000 1,883.330 44.600 83,996.52 1)(FNAL POS) 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 113,656.52 0 TOTAL AMOUNT WORK DONE TO DATE - $ 607,112.42