1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8090752 MGR.NO. 053 PAGE 001 CONT 6201 SEC 95 JOB 001 RES ENGR BEDNARZ, KARL PROJ SUP - 620195001 HWY RM0584 4502 KNICKERBOCKERQ SAN A CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 74,125.38 REPORT DATE 11/08/2009 18.20.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 CONCHO RESOURCE CENTER 10336 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2009 TIME COMPUTED FROM SEP 01, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 30 30 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 61 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 425 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 425 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 61 61 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8090752 MGR.NO. 053 PAGE 001 CONT 6201 SEC 95 JOB 001 RES ENGR BEDNARZ, KARL PROJ SUP - 620195001 HWY RM0584 4502 KNICKERBOCKERQ SAN A CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 74,125.38 REPORT DATE 11/08/2009 18.20.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 CONCHO RESOURCE CENTER 10336 DIST. 07 COUNTY TOM GREEN CONTROL 6201-95-001 PROJECT SUP - 620195001 HIGHWAY RM0584 0LIMITS- VARIOUS TOM GREEN COUNTY VARIOUS TOM GREEN COUNTY 0TYPE OF WORK- LITTER PICK UP 0 0050 LITTER PICKUP TOM GREEN COUNTY URBA NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0734 LITTER REMOVAL AC 10.000 1.000 881.920 881.92 0060 0734 LITTER REMOVAL - TRACT (2) AC 10.000 1.000 910.290 910.29 0065 0734 LITTER REMOVAL - TRACT (3) AC 17.000 2.000 1,686.600 3,373.20 0070 0734 LITTER REMOVAL - TRACT (4) AC 17.000 2.000 1,354.080 2,708.16 0075 0734 LITTER REMOVAL - TRACT (5) AC 4.000 1.000 940.430 940.43 0080 0734 LITTER REMOVAL - TRACT (6) AC 50.000 0.000 15.000 .00 0 SUBTOTAL BID ITEMS $ 8,814.00 0 TOTAL AMOUNT WORK DONE LITTER PICKUP TOM GREEN COUNTY URBA $ 8,814.00 0 TOTAL AMOUNT WORK DONE CONTROL 6201-95-001 $ 8,814.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8090752 MGR.NO. 053 PAGE 001 CONT 6201 SEC 95 JOB 001 RES ENGR BEDNARZ, KARL PROJ SUP - 620195001 HWY RM0584 4502 KNICKERBOCKERQ SAN A CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 74,125.38 REPORT DATE 11/08/2009 18.20.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 CONCHO RESOURCE CENTER 10336 0*********************************************************************************************************************************** -LIMITS - VARIOUS TOM GREEN COUNTY 0 VARIOUS TOM GREEN COUNTY DATE WORK BEGAN SEP 1 , 2009 WORKING DAYS USED 61 PERCENT COMPLETE 11.89 PERCENT TIME USED 16.70 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6201-95-001 SUP - 620195001 07 RM0584 TOM GREEN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL AC 10.000 1.000 881.920 881.92 0734 LITTER REMOVAL - TRACT (2) AC 10.000 1.000 910.290 910.29 0734 LITTER REMOVAL - TRACT (3) AC 17.000 2.000 1,686.600 3,373.20 0734 LITTER REMOVAL - TRACT (4) AC 17.000 2.000 1,354.080 2,708.16 0734 LITTER REMOVAL - TRACT (5) AC 4.000 1.000 940.430 940.43 0 SUBTOTAL BID ITEMS $ 8,814.00 0 CONTRACT TOTAL ALL ITEMS $ 8,814.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8090752 MGR.NO. 053 PAGE 001 CONT 6201 SEC 95 JOB 001 RES ENGR BEDNARZ, KARL PROJ SUP - 620195001 HWY RM0584 4502 KNICKERBOCKERQ SAN A CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 74,125.38 REPORT DATE 11/08/2009 18.20.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 CONCHO RESOURCE CENTER 10336 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 226 SUP - 620195001 6201-95-001 8,814.00 .00 8,814.00 .00 .00 8,814.00 5,773.32 3,040.68 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 8,814.00 .00 8,814.00 .00 .00 8,814.00 5,773.32 3,040.68 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8090752 MGR.NO. 053 PAGE 001 CONT 6201 SEC 95 JOB 001 RES ENGR BEDNARZ, KARL PROJ SUP - 620195001 HWY RM0584 4502 KNICKERBOCKERQ SAN A CNTY TOM GREEN DIST 07 CONTRACT PRICE $ 74,125.38 REPORT DATE 11/08/2009 18.20.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 002 CONCHO RESOURCE CENTER 10336 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6201-95-001 SUP - 620195001 07 RM0584 TOM GREEN -LIMITS - VARIOUS TOM GREEN COUNTY VARIOUS TOM GREEN COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0734 LITTER REMOVAL - TRACT (3) AC 17.000 1.000 1,686.600 1,686.60 70 0734 LITTER REMOVAL - TRACT (4) AC 17.000 1.000 1,354.080 1,354.08 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 3,040.68 0 TOTAL AMOUNT WORK DONE TO DATE - $ 8,814.00