1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11080712 MGR.NO. 051 PAGE 001 CONT 6188 SEC 01 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618801001 HWY SH0041 2124 N. MAIN JUNCTION CNTY REAL DIST 07 CONTRACT PRICE $ 36,162.62 REPORT DATE 08/20/2009 14.50.07 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD AUG 06,2009 TO AUG 13,2009 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 06, 2009 TIME COMPUTED FROM AUG 06, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 23 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 TOTAL DAYS ALLOWED = 23 DATE WORK COMPLETED 08/13/09 DAYS CHARGED TO DATE = 6 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED AND ACCEPTED TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 8 6 2 0 SATURDAY 1 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11080712 MGR.NO. 051 PAGE 001 CONT 6188 SEC 01 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618801001 HWY SH0041 2124 N. MAIN JUNCTION CNTY REAL DIST 07 CONTRACT PRICE $ 36,162.62 REPORT DATE 08/20/2009 14.50.08 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD AUG 06,2009 TO AUG 13,2009 EST NO 002 & FINAL DIST. 07 COUNTY REAL CONTROL 6188-01-001 PROJECT RMC - 618801001 HIGHWAY SH0041 0LIMITS- VARIOUS HIGHWAYS IN REAL ETC COUNTIES 0TYPE OF WORK- FULL WIDTH MOWING 0 0050 ROADSIDE MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY JUNCTION AREA OFFICE 0 0075 0730 FULL-WIDTH MOWING AC 1,646.000 1,604.000 21.970 35,239.88 0 SUBTOTAL BID ITEMS $ 35,239.88 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 35,239.88 0 TOTAL AMOUNT WORK DONE CONTROL 6188-01-001 $ 35,239.88 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11080712 MGR.NO. 051 PAGE 001 CONT 6188 SEC 01 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618801001 HWY SH0041 2124 N. MAIN JUNCTION CNTY REAL DIST 07 CONTRACT PRICE $ 36,162.62 REPORT DATE 08/20/2009 14.50.08 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD AUG 06,2009 TO AUG 13,2009 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS IN REAL ETC 0 COUNTIES DATE WORK BEGAN AUG 6 , 2009 WORKING DAYS USED 6 PERCENT COMPLETE 100.00 PERCENT TIME USED 26.00 DATE COMPLETED AUG 13 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6188-01-001 RMC - 618801001 07 SH0041 REAL - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 1,646.000 1,604.000 21.970 35,239.88 0 SUBTOTAL BID ITEMS $ 35,239.88 0 CONTRACT TOTAL ALL ITEMS $ 35,239.88 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11080712 MGR.NO. 051 PAGE 001 CONT 6188 SEC 01 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618801001 HWY SH0041 2124 N. MAIN JUNCTION CNTY REAL DIST 07 CONTRACT PRICE $ 36,162.62 REPORT DATE 08/20/2009 14.50.08 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD AUG 06,2009 TO AUG 13,2009 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 193 RMC - 618801001 6188-01-001 35,239.88 .00 35,239.88 .00 .00 35,239.88 35,239.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 35,239.88 .00 35,239.88 .00 .00 35,239.88 35,239.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11080712 MGR.NO. 051 PAGE 001 CONT 6188 SEC 01 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618801001 HWY SH0041 2124 N. MAIN JUNCTION CNTY REAL DIST 07 CONTRACT PRICE $ 36,162.62 REPORT DATE 08/20/2009 14.50.08 CONTRACTOR R&M INCORPORATED 10648 EST PERIOD AUG 06,2009 TO AUG 13,2009 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6188-01-001 RMC - 618801001 07 SH0041 REAL -LIMITS - VARIOUS HIGHWAYS IN REAL ETC COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 35,239.88