1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11080709 MGR.NO. 051 PAGE 001 CONT 6187 SEC 98 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618798001 HWY US0087 2124 N.MAIN JUNCTION CNTY CONCHO DIST 07 CONTRACT PRICE $ 66,356.84 REPORT DATE 08/28/2009 12.34.55 CONTRACTOR EGGEMEYER MOWING & EST PERIOD JUL 13,2009 TO JUL 31,2009 EST NO 002 & FINAL CONTRACTING, INC. 09323 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 13, 2009 TIME COMPUTED FROM JUL 13, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 38 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 09 TOTAL DAYS ALLOWED = 38 DATE WORK COMPLETED 07/31/09 DAYS CHARGED TO DATE = 14 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 400 0 LIQUIDATED DAMAGES 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 SATURDAY 19 1 SUNDAY 20 1 21 1 22 1 23 1 24 1 25 1 SATURDAY 26 1 SUNDAY 27 1 28 1 29 1 30 1 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 19 14 5 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11080709 MGR.NO. 051 PAGE 001 CONT 6187 SEC 98 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618798001 HWY US0087 2124 N.MAIN JUNCTION CNTY CONCHO DIST 07 CONTRACT PRICE $ 66,356.84 REPORT DATE 08/28/2009 12.34.56 CONTRACTOR EGGEMEYER MOWING & EST PERIOD JUL 13,2009 TO JUL 31,2009 EST NO 002 & FINAL CONTRACTING, INC. 09323 DIST. 07 COUNTY CONCHO CONTROL 6187-98-001 PROJECT RMC - 618798001 HIGHWAY US0087 0LIMITS- VARIOUS HIGHWAYS IN CONCHO ETC COUNTIES 0TYPE OF WORK- FULL WIDTH MOWING 0 0050 ROADSIDE MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY JUNCTION AREA OFFICE 0 0075 0730 FULL-WIDTH MOWING AC 3,652.000 3,652.000 18.170 66,356.84 0 SUBTOTAL BID ITEMS $ 66,356.84 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 66,356.84 0 TOTAL AMOUNT WORK DONE CONTROL 6187-98-001 $ 66,356.84 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11080709 MGR.NO. 051 PAGE 001 CONT 6187 SEC 98 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618798001 HWY US0087 2124 N.MAIN JUNCTION CNTY CONCHO DIST 07 CONTRACT PRICE $ 66,356.84 REPORT DATE 08/28/2009 12.34.56 CONTRACTOR EGGEMEYER MOWING & EST PERIOD JUL 13,2009 TO JUL 31,2009 EST NO 002 & FINAL CONTRACTING, INC. 09323 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS IN CONCHO ETC 0 COUNTIES DATE WORK BEGAN JUL 13, 2009 WORKING DAYS USED 14 PERCENT COMPLETE 100.00 PERCENT TIME USED 36.80 DATE COMPLETED JUL 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6187-98-001 RMC - 618798001 07 US0087 CONCHO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 3,652.000 3,652.000 18.170 66,356.84 0 SUBTOTAL BID ITEMS $ 66,356.84 0 CONTRACT TOTAL ALL ITEMS $ 66,356.84 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11080709 MGR.NO. 051 PAGE 001 CONT 6187 SEC 98 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618798001 HWY US0087 2124 N.MAIN JUNCTION CNTY CONCHO DIST 07 CONTRACT PRICE $ 66,356.84 REPORT DATE 08/28/2009 12.34.56 CONTRACTOR EGGEMEYER MOWING & EST PERIOD JUL 13,2009 TO JUL 31,2009 EST NO 002 & FINAL CONTRACTING, INC. 09323 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 48 RMC - 618798001 6187-98-001 66,356.84 .00 66,356.84 .00 .00 66,356.84 66,356.84 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 66,356.84 .00 66,356.84 .00 .00 66,356.84 66,356.84 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11080709 MGR.NO. 051 PAGE 001 CONT 6187 SEC 98 JOB 001 RES ENGR NOWLIN, LEWIS PROJ RMC - 618798001 HWY US0087 2124 N.MAIN JUNCTION CNTY CONCHO DIST 07 CONTRACT PRICE $ 66,356.84 REPORT DATE 08/28/2009 12.34.56 CONTRACTOR EGGEMEYER MOWING & EST PERIOD JUL 13,2009 TO JUL 31,2009 EST NO 002 & FINAL CONTRACTING, INC. 09323 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6187-98-001 RMC - 618798001 07 US0087 CONCHO -LIMITS - VARIOUS HIGHWAYS IN CONCHO ETC COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 66,356.84