1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6121535 MGR.NO. 004 PAGE 001 CONT 6246 SEC 13 JOB 001 RES ENGR LOWAK, TIM PROJ SUP - 624613001 HWY SH0097 317 SH 97 E FLORESVILLE CNTY WILSON DIST 15 CONTRACT PRICE $ 6,480.00 REPORT DATE 06/11/2013 15.29.35 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 13,2012 TO JUN 10,2013 EST NO 013 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 15, 2012 TIME COMPUTED FROM JUN 13, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 353 353 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 13 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 06/10/13 3 1 DAYS CHARGED TO DATE = 362 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 363 362 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6121535 MGR.NO. 004 PAGE 001 CONT 6246 SEC 13 JOB 001 RES ENGR LOWAK, TIM PROJ SUP - 624613001 HWY SH0097 317 SH 97 E FLORESVILLE CNTY WILSON DIST 15 CONTRACT PRICE $ 6,480.00 REPORT DATE 06/11/2013 15.29.36 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 13,2012 TO JUN 10,2013 EST NO 013 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 DIST. 15 COUNTY WILSON CONTROL 6246-13-001 PROJECT SUP - 624613001 HIGHWAY SH0097 0LIMITS- FLORESVILLE MAINTENANCE OFFICE 0TYPE OF WORK- JANITORIAL SERVICES 0 0005 JANITORIAL SERVICES 0 0055 FLORESVILLE MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7206 JANITORIAL MAINTENANCE MO 12.000 11.650 540.000 6,291.00 0 SUBTOTAL BID ITEMS $ 6,291.00 0 TOTAL AMOUNT WORK DONE FLORESVILLE MAINTENANCE $ 6,291.00 0 TOTAL AMOUNT WORK DONE CONTROL 6246-13-001 $ 6,291.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6121535 MGR.NO. 004 PAGE 001 CONT 6246 SEC 13 JOB 001 RES ENGR LOWAK, TIM PROJ SUP - 624613001 HWY SH0097 317 SH 97 E FLORESVILLE CNTY WILSON DIST 15 CONTRACT PRICE $ 6,480.00 REPORT DATE 06/11/2013 15.29.36 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 13,2012 TO JUN 10,2013 EST NO 013 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 0*********************************************************************************************************************************** -LIMITS - FLORESVILLE MAINTENANCE 0 OFFICE DATE WORK BEGAN JUN 15, 2012 WORKING DAYS USED 362 PERCENT COMPLETE 100.00 PERCENT TIME USED 99.10 DATE COMPLETED JUN 10 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6246-13-001 SUP - 624613001 15 SH0097 WILSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7206 JANITORIAL MAINTENANCE MO 12.000 11.650 540.000 6,291.00 0 SUBTOTAL BID ITEMS $ 6,291.00 0 CONTRACT TOTAL ALL ITEMS $ 6,291.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6121535 MGR.NO. 004 PAGE 001 CONT 6246 SEC 13 JOB 001 RES ENGR LOWAK, TIM PROJ SUP - 624613001 HWY SH0097 317 SH 97 E FLORESVILLE CNTY WILSON DIST 15 CONTRACT PRICE $ 6,480.00 REPORT DATE 06/11/2013 15.29.36 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 13,2012 TO JUN 10,2013 EST NO 013 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 247 SUP - 624613001 6246-13-001 6,291.00 .00 6,291.00 .00 .00 6,291.00 6,156.00 135.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 6,291.00 .00 6,291.00 .00 .00 6,291.00 6,156.00 135.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6121535 MGR.NO. 004 PAGE 001 CONT 6246 SEC 13 JOB 001 RES ENGR LOWAK, TIM PROJ SUP - 624613001 HWY SH0097 317 SH 97 E FLORESVILLE CNTY WILSON DIST 15 CONTRACT PRICE $ 6,480.00 REPORT DATE 06/11/2013 15.29.36 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 13,2012 TO JUN 10,2013 EST NO 013 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6246-13-001 SUP - 624613001 15 SH0097 WILSON -LIMITS - FLORESVILLE MAINTENANCE OFFICE LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 7206 JANITORIAL MAINTENANCE MO 12.000 0.250 540.000 135.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 135.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 6,291.00