1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6091531 MGR.NO. 009 PAGE 001 CONT 6197 SEC 98 JOB 001 RES ENGR RODRIGUEZ, CLINT PROJ SUP - 619798001 HWY US0281 2154 2ND STREET PLEASANTO CNTY ATASCOSA DIST 15 CONTRACT PRICE $ 12,960.00 REPORT DATE 11/09/2009 16.06.37 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 EARTHLY VISIONS OUTREACH 10503 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 12, 2009 TIME COMPUTED FROM JUN 06, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 117 117 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 148 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 148 148 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6091531 MGR.NO. 009 PAGE 001 CONT 6197 SEC 98 JOB 001 RES ENGR RODRIGUEZ, CLINT PROJ SUP - 619798001 HWY US0281 2154 2ND STREET PLEASANTO CNTY ATASCOSA DIST 15 CONTRACT PRICE $ 12,960.00 REPORT DATE 11/09/2009 16.06.37 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 EARTHLY VISIONS OUTREACH 10503 DIST. 15 COUNTY ATASCOSA CONTROL 6197-98-001 PROJECT SUP - 619798001 HIGHWAY US0281 0LIMITS- 2154 2ND STREET 2154 2ND STREET 0TYPE OF WORK- JANITORIAL SERVICES 0 0005 PREPARED BY CINDY ADAMI 0 0055 JANITORIAL MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7206 JANITORIAL MAINTENANCE MO 24.000 4.500 540.000 2,430.00 0 SUBTOTAL BID ITEMS $ 2,430.00 0 TOTAL AMOUNT WORK DONE JANITORIAL MAINTENANCE $ 2,430.00 0 TOTAL AMOUNT WORK DONE CONTROL 6197-98-001 $ 2,430.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6091531 MGR.NO. 009 PAGE 001 CONT 6197 SEC 98 JOB 001 RES ENGR RODRIGUEZ, CLINT PROJ SUP - 619798001 HWY US0281 2154 2ND STREET PLEASANTO CNTY ATASCOSA DIST 15 CONTRACT PRICE $ 12,960.00 REPORT DATE 11/09/2009 16.06.37 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 EARTHLY VISIONS OUTREACH 10503 0*********************************************************************************************************************************** -LIMITS - 2154 2ND STREET 0 2154 2ND STREET DATE WORK BEGAN JUN 12, 2009 WORKING DAYS USED 148 PERCENT COMPLETE 18.75 PERCENT TIME USED 20.20 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6197-98-001 SUP - 619798001 15 US0281 ATASCOSA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7206 JANITORIAL MAINTENANCE MO 24.000 4.500 540.000 2,430.00 0 SUBTOTAL BID ITEMS $ 2,430.00 0 CONTRACT TOTAL ALL ITEMS $ 2,430.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6091531 MGR.NO. 009 PAGE 001 CONT 6197 SEC 98 JOB 001 RES ENGR RODRIGUEZ, CLINT PROJ SUP - 619798001 HWY US0281 2154 2ND STREET PLEASANTO CNTY ATASCOSA DIST 15 CONTRACT PRICE $ 12,960.00 REPORT DATE 11/09/2009 16.06.37 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 EARTHLY VISIONS OUTREACH 10503 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 7 SUP - 619798001 6197-98-001 2,430.00 .00 2,430.00 .00 .00 2,430.00 1,890.00 540.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 2,430.00 .00 2,430.00 .00 .00 2,430.00 1,890.00 540.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6091531 MGR.NO. 009 PAGE 001 CONT 6197 SEC 98 JOB 001 RES ENGR RODRIGUEZ, CLINT PROJ SUP - 619798001 HWY US0281 2154 2ND STREET PLEASANTO CNTY ATASCOSA DIST 15 CONTRACT PRICE $ 12,960.00 REPORT DATE 11/09/2009 16.06.37 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 EARTHLY VISIONS OUTREACH 10503 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6197-98-001 SUP - 619798001 15 US0281 ATASCOSA -LIMITS - 2154 2ND STREET 2154 2ND STREET LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 7206 JANITORIAL MAINTENANCE MO 24.000 1.000 540.000 540.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 540.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 2,430.00