1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12084015 MGR.NO. 013 PAGE 001 CONT 6185 SEC 13 JOB 001 RES ENGR RAINOSEK, BRENT PROJ RMC - 618513001 HWY IH0010 2028 HWY 46 N SEGUIN CNTY GUADALUPE DIST 15 CONTRACT PRICE $ 570,568.68 REPORT DATE 11/04/2009 14.00.21 CONTRACTOR CEDAR SOLUTIONS, LLC 13493 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 01, 2009 TIME COMPUTED FROM JUN 08, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 256 122 29 93 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 DAYS BETWEEN CYCLES TOTAL DAYS ALLOWED = 256 2 1 DAYS BETWEEN CYCLES DATE WORK COMPLETED 3 1 DAYS BETWEEN CYCLES DAYS CHARGED TO DATE = 29 4 1 DAYS BETWEEN CYCLES ASSESSED LIQ DAMAGES = 0 5 1 DAYS BETWEEN CYCLES LIQ DAMAGE RATE $ 500 6 1 DAYS BETWEEN CYCLES 7 1 DAYS BETWEEN CYCLES LIQUIDATED DAMAGES 8 1 DAYS BETWEEN CYCLES 0 DAYS AT $ 500 PER DAY 9 1 DAYS BETWEEN CYCLES TOTAL = $ .00 10 1 DAYS BETWEEN CYCLES 11 1 DAYS BETWEEN CYCLES CERTIFIED AS CORRECT AND 12 1 DAYS BETWEEN CYCLES ONE COPY HAS BEEN GIVEN 13 1 DAYS BETWEEN CYCLES TO THE CONTRACTOR 14 1 DAYS BETWEEN CYCLES 15 1 DAYS BETWEEN CYCLES 16 1 DAYS BETWEEN CYCLES ---------------------------- 17 1 DAYS BETWEEN CYCLES AREA/PROJECT ENGINEER 18 1 DAYS BETWEEN CYCLES 19 1 DAYS BETWEEN CYCLES 20 1 DAYS BETWEEN CYCLES 21 1 DAYS BETWEEN CYCLES 22 1 DAYS BETWEEN CYCLES 23 1 DAYS BETWEEN CYCLES 24 1 DAYS BETWEEN CYCLES 25 1 DAYS BETWEEN CYCLES 26 1 DAYS BETWEEN CYCLES 27 1 DAYS BETWEEN CYCLES 28 1 DAYS BETWEEN CYCLES 29 1 DAYS BETWEEN CYCLES 30 1 DAYS BETWEEN CYCLES 31 1 DAYS BETWEEN CYCLES ----- ----- ----- 153 29 124 0 SATURDAY 0 SUNDAY 0 HOLIDAY 31 DAYS BETWEEN CYCLES 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12084015 MGR.NO. 013 PAGE 001 CONT 6185 SEC 13 JOB 001 RES ENGR RAINOSEK, BRENT PROJ RMC - 618513001 HWY IH0010 2028 HWY 46 N SEGUIN CNTY GUADALUPE DIST 15 CONTRACT PRICE $ 570,568.68 REPORT DATE 11/04/2009 14.00.21 CONTRACTOR CEDAR SOLUTIONS, LLC 13493 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 DIST. 15 COUNTY GUADALUPE CONTROL 6185-13-001 PROJECT RMC - 618513001 HIGHWAY IH0010 0LIMITS- VARIOUS LOCATIONS IN GUADALUPE COUNTY 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 MOWING HWY ROW 0 0055 PREPARED BY MICHELLE BLOCH NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 13,026.000 1,721.000 24.420 42,026.82 0065 0730 FULL-WIDTH MOWING AC 9,608.000 561.000 26.130 14,658.93 0070 0730 SPOT MOWING AC 24.000 0.000 59.030 .00 0 SUBTOTAL BID ITEMS $ 56,685.75 0 TOTAL AMOUNT WORK DONE PREPARED BY MICHELLE BLOCH $ 56,685.75 0 TOTAL AMOUNT WORK DONE CONTROL 6185-13-001 $ 56,685.75 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12084015 MGR.NO. 013 PAGE 001 CONT 6185 SEC 13 JOB 001 RES ENGR RAINOSEK, BRENT PROJ RMC - 618513001 HWY IH0010 2028 HWY 46 N SEGUIN CNTY GUADALUPE DIST 15 CONTRACT PRICE $ 570,568.68 REPORT DATE 11/04/2009 14.00.22 CONTRACTOR CEDAR SOLUTIONS, LLC 13493 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN GUADALUPE 0 COUNTY DATE WORK BEGAN JUN 1 , 2009 WORKING DAYS USED 29 PERCENT COMPLETE 9.93 PERCENT TIME USED 11.30 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6185-13-001 RMC - 618513001 15 IH0010 GUADALUPE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 13,026.000 1,721.000 24.420 42,026.82 0730 FULL-WIDTH MOWING AC 9,608.000 561.000 26.130 14,658.93 0 SUBTOTAL BID ITEMS $ 56,685.75 0 CONTRACT TOTAL ALL ITEMS $ 56,685.75 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12084015 MGR.NO. 013 PAGE 001 CONT 6185 SEC 13 JOB 001 RES ENGR RAINOSEK, BRENT PROJ RMC - 618513001 HWY IH0010 2028 HWY 46 N SEGUIN CNTY GUADALUPE DIST 15 CONTRACT PRICE $ 570,568.68 REPORT DATE 11/04/2009 14.00.22 CONTRACTOR CEDAR SOLUTIONS, LLC 13493 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 95 RMC - 618513001 6185-13-001 56,685.75 .00 56,685.75 .00 .00 56,685.75 56,685.75 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 56,685.75 .00 56,685.75 .00 .00 56,685.75 56,685.75 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12084015 MGR.NO. 013 PAGE 001 CONT 6185 SEC 13 JOB 001 RES ENGR RAINOSEK, BRENT PROJ RMC - 618513001 HWY IH0010 2028 HWY 46 N SEGUIN CNTY GUADALUPE DIST 15 CONTRACT PRICE $ 570,568.68 REPORT DATE 11/04/2009 14.00.23 CONTRACTOR CEDAR SOLUTIONS, LLC 13493 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6185-13-001 RMC - 618513001 15 IH0010 GUADALUPE -LIMITS - VARIOUS LOCATIONS IN GUADALUPE COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 56,685.75