1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12084030 MGR.NO. 020 PAGE 001 CONT 6172 SEC 58 JOB 001 RES ENGR BERMEA, HOMER PROJ RMC - 617258001 HWY US0090 2322 W. US HWY 90 UVALDE CNTY UVALDE DIST 15 CONTRACT PRICE $ 372,146.28 REPORT DATE 10/27/2009 09.55.07 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 23, 2009 TIME COMPUTED FROM JUN 22, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 170 132 13 119 BROUGHT FORWARD ADDL DAYS GRANTED = 0 *** ESTIMATE ALREADY POSTED *** TOTAL DAYS ALLOWED = 170 DATE WORK COMPLETED DAYS CHARGED TO DATE = 13 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 132 13 119 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12084030 MGR.NO. 020 PAGE 001 CONT 6172 SEC 58 JOB 001 RES ENGR BERMEA, HOMER PROJ RMC - 617258001 HWY US0090 2322 W. US HWY 90 UVALDE CNTY UVALDE DIST 15 CONTRACT PRICE $ 372,146.28 REPORT DATE 10/27/2009 09.55.07 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 DIST. 15 COUNTY UVALDE CONTROL 6172-58-001 PROJECT RMC - 617258001 HIGHWAY US0090 0LIMITS- VARIOUS LOCATIONS IN UVALDE COUNTY . 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY BRACEY M KEENEY 0 0055 MOWING RIGHT OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 9,104.000 1,156.000 24.670 28,518.52 0065 0730 FULL-WIDTH MOWING AC 5,980.000 0.000 24.670 .00 0070 0730 SPOT MOWING AC 24.000 0.000 1.000 .00 0 SUBTOTAL BID ITEMS $ 28,518.52 0 TOTAL AMOUNT WORK DONE MOWING RIGHT OF WAY $ 28,518.52 0 TOTAL AMOUNT WORK DONE CONTROL 6172-58-001 $ 28,518.52 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12084030 MGR.NO. 020 PAGE 001 CONT 6172 SEC 58 JOB 001 RES ENGR BERMEA, HOMER PROJ RMC - 617258001 HWY US0090 2322 W. US HWY 90 UVALDE CNTY UVALDE DIST 15 CONTRACT PRICE $ 372,146.28 REPORT DATE 10/27/2009 09.55.09 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN UVALDE COUNTY 0 . DATE WORK BEGAN JUN 23, 2009 WORKING DAYS USED 13 PERCENT COMPLETE 7.66 PERCENT TIME USED 7.60 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6172-58-001 RMC - 617258001 15 US0090 UVALDE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 9,104.000 1,156.000 24.670 28,518.52 0 SUBTOTAL BID ITEMS $ 28,518.52 0 CONTRACT TOTAL ALL ITEMS $ 28,518.52 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12084030 MGR.NO. 020 PAGE 001 CONT 6172 SEC 58 JOB 001 RES ENGR BERMEA, HOMER PROJ RMC - 617258001 HWY US0090 2322 W. US HWY 90 UVALDE CNTY UVALDE DIST 15 CONTRACT PRICE $ 372,146.28 REPORT DATE 10/27/2009 09.55.09 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 232 RMC - 617258001 6172-58-001 28,518.52 .00 28,518.52 .00 .00 28,518.52 28,518.52 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 28,518.52 .00 28,518.52 .00 .00 28,518.52 28,518.52 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12084030 MGR.NO. 020 PAGE 001 CONT 6172 SEC 58 JOB 001 RES ENGR BERMEA, HOMER PROJ RMC - 617258001 HWY US0090 2322 W. US HWY 90 UVALDE CNTY UVALDE DIST 15 CONTRACT PRICE $ 372,146.28 REPORT DATE 10/27/2009 09.55.10 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6172-58-001 RMC - 617258001 15 US0090 UVALDE -LIMITS - VARIOUS LOCATIONS IN UVALDE COUNTY . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 28,518.52