1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11074013 MGR.NO. 006 PAGE 001 CONT 6169 SEC 32 JOB 001 RES ENGR ALVAREZ, PEDRO PROJ RMC - 616932001 HWY US0083 P O BOX 1717 PHARR CNTY HIDALGO DIST 21 CONTRACT PRICE $ 299,886.70 REPORT DATE 06/03/2009 08.37.49 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD MAY 01,2009 TO MAY 31,2009 EST NO 016 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 11, 2008 TIME COMPUTED FROM FEB 20, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 96 445 17 428 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 09 1 1 WORK SUSPENDED TOTAL DAYS ALLOWED = 96 2 1 SATURDAY DATE WORK COMPLETED 05/31/09 3 1 SUNDAY DAYS CHARGED TO DATE = 17 4 1 WORK SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 WORK SUSPENDED LIQ DAMAGE RATE $ 400 6 1 WORK SUSPENDED 7 1 WORK SUSPENDED LIQUIDATED DAMAGES 8 1 WORK SUSPENDED 0 DAYS AT $ 400 PER DAY 9 1 SATURDAY TOTAL = $ .00 10 1 SUNDAY 11 1 TXDOT REQUESTED WORK COMPLETED CERTIFIED AS CORRECT AND 12 1 TXDOT REQUESTED WORK COMPLETED ONE COPY HAS BEEN GIVEN 13 1 TXDOT REQUESTED WORK COMPLETED TO THE CONTRACTOR 14 1 TXDOT REQUESTED WORK COMPLETED 15 1 TXDOT REQUESTED WORK COMPLETED 16 1 SATURDAY ---------------------------- 17 1 SUNDAY AREA/PROJECT ENGINEER 18 1 TXDOT REQUESTED WORK COMPLETED 19 1 TXDOT REQUESTED WORK COMPLETED 20 1 TXDOT REQUESTED WORK COMPLETED 21 1 TXDOT REQUESTED WORK COMPLETED 22 1 TXDOT REQUESTED WORK COMPLETED 23 1 SATURDAY 24 1 SUNDAY 25 1 TXDOT REQUESTED WORK COMPLETED 26 1 TXDOT REQUESTED WORK COMPLETED 27 1 TXDOT REQUESTED WORK COMPLETED 28 1 TXDOT REQUESTED WORK COMPLETED 29 1 TXDOT REQUESTED WORK COMPLETED 30 1 SATURDAY 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 476 17 459 5 SATURDAY 4 SUNDAY 0 HOLIDAY 6 WORK SUSPENDED 15 TXDOT REQUESTED WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11074013 MGR.NO. 006 PAGE 001 CONT 6169 SEC 32 JOB 001 RES ENGR ALVAREZ, PEDRO PROJ RMC - 616932001 HWY US0083 P O BOX 1717 PHARR CNTY HIDALGO DIST 21 CONTRACT PRICE $ 299,886.70 REPORT DATE 06/03/2009 08.37.50 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD MAY 01,2009 TO MAY 31,2009 EST NO 016 DIST. 21 COUNTY HIDALGO CONTROL 6169-32-001 PROJECT RMC - 616932001 HIGHWAY US0083 0LIMITS- DISTRICTWIDE: VARIOUS COUNTIES DISTRICTWIDE: VARIOUS COUNTIES 0TYPE OF WORK- RAISED PAVEMENT MARKINGS 0 0050 RAISED PAVEMENT MARKINGS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY DELIA VILLARREAL 0 0075 0672 REFL PAV MRKR TY I-A EA 652.000 652.000 2.350 1,532.20 0080 0672 REFL PAV MRKR TY I-C EA 18,695.000 8,286.000 2.400 19,886.40 0085 0672 REFL PAV MRKR TY II-A-A EA 87,543.000 39,185.000 2.300 90,125.50 0090 0672 REFL PAV MRKR TY II-C-R EA 21,724.000 21,539.000 2.400 51,693.60 0 SUBTOTAL BID ITEMS $ 163,237.70 0 TOTAL AMOUNT WORK DONE RAISED PAVEMENT MARKINGS $ 163,237.70 0 TOTAL AMOUNT WORK DONE CONTROL 6169-32-001 $ 163,237.70 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11074013 MGR.NO. 006 PAGE 001 CONT 6169 SEC 32 JOB 001 RES ENGR ALVAREZ, PEDRO PROJ RMC - 616932001 HWY US0083 P O BOX 1717 PHARR CNTY HIDALGO DIST 21 CONTRACT PRICE $ 299,886.70 REPORT DATE 06/03/2009 08.37.50 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD MAY 01,2009 TO MAY 31,2009 EST NO 016 0*********************************************************************************************************************************** -LIMITS - DISTRICTWIDE: VARIOUS COUNTIES 0 DISTRICTWIDE: VARIOUS COUNTIES DATE WORK BEGAN FEB 11, 2008 WORKING DAYS USED 17 PERCENT COMPLETE 100.00 PERCENT TIME USED 17.70 DATE COMPLETED MAY 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6169-32-001 RMC - 616932001 21 US0083 HIDALGO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0672 REFL PAV MRKR TY I-A EA 652.000 652.000 2.350 1,532.20 0672 REFL PAV MRKR TY I-C EA 18,695.000 8,286.000 2.400 19,886.40 0672 REFL PAV MRKR TY II-A-A EA 87,543.000 39,185.000 2.300 90,125.50 0672 REFL PAV MRKR TY II-C-R EA 21,724.000 21,539.000 2.400 51,693.60 0 SUBTOTAL BID ITEMS $ 163,237.70 0 CONTRACT TOTAL ALL ITEMS $ 163,237.70 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11074013 MGR.NO. 006 PAGE 001 CONT 6169 SEC 32 JOB 001 RES ENGR ALVAREZ, PEDRO PROJ RMC - 616932001 HWY US0083 P O BOX 1717 PHARR CNTY HIDALGO DIST 21 CONTRACT PRICE $ 299,886.70 REPORT DATE 06/03/2009 08.37.50 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD MAY 01,2009 TO MAY 31,2009 EST NO 016 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 109 RMC - 616932001 6169-32-001 163,237.70 .00 163,237.70 .00 .00 163,237.70 163,237.70 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 163,237.70 .00 163,237.70 .00 .00 163,237.70 163,237.70 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11074013 MGR.NO. 006 PAGE 001 CONT 6169 SEC 32 JOB 001 RES ENGR ALVAREZ, PEDRO PROJ RMC - 616932001 HWY US0083 P O BOX 1717 PHARR CNTY HIDALGO DIST 21 CONTRACT PRICE $ 299,886.70 REPORT DATE 06/03/2009 08.37.50 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD MAY 01,2009 TO MAY 31,2009 EST NO 016 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6169-32-001 RMC - 616932001 21 US0083 HIDALGO -LIMITS - DISTRICTWIDE: VARIOUS COUNTIES DISTRICTWIDE: VARIOUS COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 163,237.70