1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12120103 MGR.NO. 001 PAGE 001 CONT 6249 SEC 37 JOB 001 RES ENGR WOODRUFF, MYKOL PROJ RMC - 624937001 HWY US0082 1365 N. MAIN ST. PARIS CNTY FANNIN DIST 01 CONTRACT PRICE $ 198,343.20 REPORT DATE 12/16/2013 08.51.24 CONTRACTOR GANT CONTRACTORS, INC. 13182 EST PERIOD JUN 24,2013 TO OCT 14,2013 EST NO 006 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 24, 2013 TIME COMPUTED FROM JUL 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 60 99 24 75 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 13 1 1 TOTAL DAYS ALLOWED = 60 2 1 DATE WORK COMPLETED 10/14/13 3 1 DAYS CHARGED TO DATE = 34 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 WORK COMPLETED AND ACCEPTED 0 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 113 34 79 1 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12120103 MGR.NO. 001 PAGE 001 CONT 6249 SEC 37 JOB 001 RES ENGR WOODRUFF, MYKOL PROJ RMC - 624937001 HWY US0082 1365 N. MAIN ST. PARIS CNTY FANNIN DIST 01 CONTRACT PRICE $ 198,343.20 REPORT DATE 12/16/2013 08.51.24 CONTRACTOR GANT CONTRACTORS, INC. 13182 EST PERIOD JUN 24,2013 TO OCT 14,2013 EST NO 006 & FINAL DIST. 01 COUNTY FANNIN CONTROL 6249-37-001 PROJECT RMC - 624937001 HIGHWAY US0082 0LIMITS- VARIOUS ROADWAYS IN FANNIN COUNTY 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 ENTERED BY RENEE COSTON 10-15-12 'OTHER WW' 0 0055 MOWING HIGHWAY ROW NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 9,630.000 9,360.000 20.490 191,786.40 0065 0730 SPOT MOWING AC 50.000 0.000 20.490 .00 0 SUBTOTAL BID ITEMS $ 191,786.40 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY ROW $ 191,786.40 0 TOTAL AMOUNT WORK DONE CONTROL 6249-37-001 $ 191,786.40 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12120103 MGR.NO. 001 PAGE 001 CONT 6249 SEC 37 JOB 001 RES ENGR WOODRUFF, MYKOL PROJ RMC - 624937001 HWY US0082 1365 N. MAIN ST. PARIS CNTY FANNIN DIST 01 CONTRACT PRICE $ 198,343.20 REPORT DATE 12/16/2013 08.51.24 CONTRACTOR GANT CONTRACTORS, INC. 13182 EST PERIOD JUN 24,2013 TO OCT 14,2013 EST NO 006 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 FANNIN COUNTY DATE WORK BEGAN JUN 24, 2013 WORKING DAYS USED 34 PERCENT COMPLETE 100.00 PERCENT TIME USED 56.60 DATE COMPLETED OCT 14 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6249-37-001 RMC - 624937001 01 US0082 FANNIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 9,630.000 9,360.000 20.490 191,786.40 0 SUBTOTAL BID ITEMS $ 191,786.40 0 CONTRACT TOTAL ALL ITEMS $ 191,786.40 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12120103 MGR.NO. 001 PAGE 001 CONT 6249 SEC 37 JOB 001 RES ENGR WOODRUFF, MYKOL PROJ RMC - 624937001 HWY US0082 1365 N. MAIN ST. PARIS CNTY FANNIN DIST 01 CONTRACT PRICE $ 198,343.20 REPORT DATE 12/16/2013 08.51.24 CONTRACTOR GANT CONTRACTORS, INC. 13182 EST PERIOD JUN 24,2013 TO OCT 14,2013 EST NO 006 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 75 RMC - 624937001 6249-37-001 191,786.40 .00 191,786.40 .00 .00 191,786.40 191,786.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 191,786.40 .00 191,786.40 .00 .00 191,786.40 191,786.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12120103 MGR.NO. 001 PAGE 001 CONT 6249 SEC 37 JOB 001 RES ENGR WOODRUFF, MYKOL PROJ RMC - 624937001 HWY US0082 1365 N. MAIN ST. PARIS CNTY FANNIN DIST 01 CONTRACT PRICE $ 198,343.20 REPORT DATE 12/16/2013 08.51.24 CONTRACTOR GANT CONTRACTORS, INC. 13182 EST PERIOD JUN 24,2013 TO OCT 14,2013 EST NO 006 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6249-37-001 RMC - 624937001 01 US0082 FANNIN -LIMITS - VARIOUS ROADWAYS IN FANNIN COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 191,786.40