1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7120103 MGR.NO. 007 PAGE 001 CONT 6243 SEC 75 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624375001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 93,985.92 REPORT DATE 05/03/2013 12.57.21 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 04, 2012 TIME COMPUTED FROM SEP 11, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 261 209 140 69 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 261 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 162 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 570 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 SATURDAY 21 1 SUNDAY 22 1 23 1 24 1 25 1 26 1 27 1 SATURDAY 28 1 SUNDAY 29 1 30 1 0 ----- ----- ----- 239 162 77 4 SATURDAY 4 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7120103 MGR.NO. 007 PAGE 001 CONT 6243 SEC 75 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624375001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 93,985.92 REPORT DATE 05/03/2013 12.57.22 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 DIST. 01 COUNTY LAMAR CONTROL 6243-75-001 PROJECT RMC - 624375001 HIGHWAY US0082 0LIMITS- VARIOUS ROADS IN LAMAR AND DELTA COUNTIES 0TYPE OF WORK- ON CALL POTHOLE REPAIR 0 0005 ENTERED BY RENEE COSTON OTHER WW 0 0055 ON CALL POTHOLE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0700 POTHOLE REPAIR (STANDARD) TON 864.000 523.859 108.780 56,985.38 0 SUBTOTAL BID ITEMS $ 56,985.38 0 TOTAL AMOUNT WORK DONE ON CALL POTHOLE REPAIR $ 56,985.38 0 TOTAL AMOUNT WORK DONE CONTROL 6243-75-001 $ 56,985.38 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7120103 MGR.NO. 007 PAGE 001 CONT 6243 SEC 75 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624375001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 93,985.92 REPORT DATE 05/03/2013 12.57.22 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADS IN LAMAR AND 0 DELTA COUNTIES DATE WORK BEGAN SEP 4 , 2012 WORKING DAYS USED 162 PERCENT COMPLETE 60.63 PERCENT TIME USED 62.00 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6243-75-001 RMC - 624375001 01 US0082 LAMAR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0700 POTHOLE REPAIR (STANDARD) TON 864.000 523.859 108.780 56,985.38 0 SUBTOTAL BID ITEMS $ 56,985.38 0 CONTRACT TOTAL ALL ITEMS $ 56,985.38 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7120103 MGR.NO. 007 PAGE 001 CONT 6243 SEC 75 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624375001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 93,985.92 REPORT DATE 05/03/2013 12.57.22 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 139 RMC - 624375001 6243-75-001 56,985.38 .00 56,985.38 .00 .00 56,985.38 48,174.20 8,811.18 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 56,985.38 .00 56,985.38 .00 .00 56,985.38 48,174.20 8,811.18 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7120103 MGR.NO. 007 PAGE 001 CONT 6243 SEC 75 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624375001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 93,985.92 REPORT DATE 05/03/2013 12.57.22 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 008 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6243-75-001 RMC - 624375001 01 US0082 LAMAR -LIMITS - VARIOUS ROADS IN LAMAR AND DELTA COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0700 POTHOLE REPAIR (STANDARD) TON 864.000 81.000 108.780 8,811.18 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 8,811.18 0 TOTAL AMOUNT WORK DONE TO DATE - $ 56,985.38