1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5120106 MGR.NO. 007 PAGE 001 CONT 6242 SEC 02 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624202001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 174,168.00 REPORT DATE 05/03/2013 13.17.22 CONTRACTOR MORTON ENTERPRISE 12756 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 06, 2012 TIME COMPUTED FROM JUN 13, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 254 299 202 97 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 TOTAL DAYS ALLOWED = 254 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 224 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 SATURDAY 7 1 SUNDAY LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 SATURDAY TO THE CONTRACTOR 14 1 SUNDAY 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 SATURDAY 21 1 SUNDAY 22 1 23 1 24 1 25 1 26 1 27 1 SATURDAY 28 1 SUNDAY 29 1 30 1 0 ----- ----- ----- 329 224 105 4 SATURDAY 4 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5120106 MGR.NO. 007 PAGE 001 CONT 6242 SEC 02 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624202001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 174,168.00 REPORT DATE 05/03/2013 13.17.22 CONTRACTOR MORTON ENTERPRISE 12756 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 DIST. 01 COUNTY LAMAR CONTROL 6242-02-001 PROJECT RMC - 624202001 HIGHWAY US0082 0LIMITS- VARIOUS ROADWAYS IN LAMAR, DELTA AND RED RIVER COUNTIES 0TYPE OF WORK- ONE WAY TRAFFIC CONTROL (FLAGGING) 0 0005 ENTERED BY RENEE COSTON 3-26-12 (5 DAY WW) 0 0055 ONE WAY TRAFFIC CONTROL (FLAGGING) NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0510 ONE-WAY TRAFFIC CONTROL HR 7,200.000 6,632.000 24.190 160,428.08 0 SUBTOTAL BID ITEMS $ 160,428.08 0 TOTAL AMOUNT WORK DONE ONE WAY TRAFFIC CONTROL (FLAGGING) $ 160,428.08 0 TOTAL AMOUNT WORK DONE CONTROL 6242-02-001 $ 160,428.08 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5120106 MGR.NO. 007 PAGE 001 CONT 6242 SEC 02 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624202001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 174,168.00 REPORT DATE 05/03/2013 13.17.23 CONTRACTOR MORTON ENTERPRISE 12756 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN LAMAR, DELTA 0 AND RED RIVER COUNTIES DATE WORK BEGAN JUN 6 , 2012 WORKING DAYS USED 224 PERCENT COMPLETE 92.11 PERCENT TIME USED 88.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6242-02-001 RMC - 624202001 01 US0082 LAMAR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0510 ONE-WAY TRAFFIC CONTROL HR 7,200.000 6,632.000 24.190 160,428.08 0 SUBTOTAL BID ITEMS $ 160,428.08 0 CONTRACT TOTAL ALL ITEMS $ 160,428.08 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5120106 MGR.NO. 007 PAGE 001 CONT 6242 SEC 02 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624202001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 174,168.00 REPORT DATE 05/03/2013 13.17.23 CONTRACTOR MORTON ENTERPRISE 12756 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 139 RMC - 624202001 6242-02-001 160,428.08 .00 160,428.08 .00 .00 160,428.08 142,672.62 17,755.46 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 160,428.08 .00 160,428.08 .00 .00 160,428.08 142,672.62 17,755.46 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5120106 MGR.NO. 007 PAGE 001 CONT 6242 SEC 02 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624202001 HWY US0082 3600 SW LOOP 286 PARIS CNTY LAMAR DIST 01 CONTRACT PRICE $ 174,168.00 REPORT DATE 05/03/2013 13.17.23 CONTRACTOR MORTON ENTERPRISE 12756 EST PERIOD APR 01,2013 TO APR 30,2013 EST NO 011 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6242-02-001 RMC - 624202001 01 US0082 LAMAR -LIMITS - VARIOUS ROADWAYS IN LAMAR, DELTA AND RED RIVER COUNTIES LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0510 ONE-WAY TRAFFIC CONTROL HR 7,200.000 734.000 24.190 17,755.46 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 17,755.46 0 TOTAL AMOUNT WORK DONE TO DATE - $ 160,428.08