1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11110104 MGR.NO. 008 PAGE 001 CONT 6232 SEC 94 JOB 001 RES ENGR SELMAN, DAVID PROJ RMC - 623294001 HWY US0069 3904 US 75 SOUTH SHERMAN CNTY GRAYSON DIST 01 CONTRACT PRICE $ 187,164.90 REPORT DATE 06/04/2012 16.45.30 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD FEB 20,2012 TO MAR 31,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 20, 2012 TIME COMPUTED FROM FEB 27, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 45 10 3 7 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 12 1 1 TOTAL DAYS ALLOWED = 45 2 1 DATE WORK COMPLETED 03/31/12 3 1 SATURDAY DAYS CHARGED TO DATE = 13 4 1 SUNDAY ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 RAIN 0 DAYS AT $ 500 PER DAY 9 1 TOO WET TOTAL = $ .00 10 1 SATURDAY 11 1 SUNDAY CERTIFIED AS CORRECT AND 12 1 TOO WET ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 SATURDAY AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 RAIN 20 1 RAIN 21 1 RAIN 22 1 RAIN 23 1 TOO WET 24 1 SATURDAY 25 1 SUNDAY 26 1 27 1 WORK COMPLETED 28 1 AWAITING FINAL DOCUMENTATION 29 1 AWAITING FINAL DOCUMENTATION 30 1 AWAITING FINAL DOCUMENTATION 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 41 13 28 4 SATURDAY 4 SUNDAY 0 HOLIDAY 5 RAIN 3 TOO WET 1 WORK COMPLETED 3 AWAITING FINAL DOCUMENTATION 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11110104 MGR.NO. 008 PAGE 001 CONT 6232 SEC 94 JOB 001 RES ENGR SELMAN, DAVID PROJ RMC - 623294001 HWY US0069 3904 US 75 SOUTH SHERMAN CNTY GRAYSON DIST 01 CONTRACT PRICE $ 187,164.90 REPORT DATE 06/04/2012 16.45.30 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD FEB 20,2012 TO MAR 31,2012 EST NO 003 & FINAL DIST. 01 COUNTY GRAYSON CONTROL 6232-94-001 PROJECT RMC - 623294001 HIGHWAY US0069 0LIMITS- VARIOUS ROADWAYS IN GRAYSON AND FANNIN COUNTIES 0TYPE OF WORK- CRACK SEAL 0 0005 ENTERED BY RENEE COSTON (OTHER WW) 0 0055 CRACK SEAL SAO NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0500 MOBILIZATION LS 1.000 1.000 14,130.000 14,130.00 0065 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 1,500.000 4,500.00 0070 0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 310.950 312.208 542.000 169,216.74 0 SUBTOTAL BID ITEMS $ 187,846.74 0 TOTAL AMOUNT WORK DONE CRACK SEAL SAO $ 187,846.74 0 TOTAL AMOUNT WORK DONE CONTROL 6232-94-001 $ 187,846.74 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11110104 MGR.NO. 008 PAGE 001 CONT 6232 SEC 94 JOB 001 RES ENGR SELMAN, DAVID PROJ RMC - 623294001 HWY US0069 3904 US 75 SOUTH SHERMAN CNTY GRAYSON DIST 01 CONTRACT PRICE $ 187,164.90 REPORT DATE 06/04/2012 16.45.30 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD FEB 20,2012 TO MAR 31,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN GRAYSON 0 AND FANNIN COUNTIES DATE WORK BEGAN FEB 20, 2012 WORKING DAYS USED 13 PERCENT COMPLETE 100.00 PERCENT TIME USED 28.80 DATE COMPLETED MAR 31 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6232-94-001 RMC - 623294001 01 US0069 GRAYSON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 14,130.000 14,130.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 1,500.000 4,500.00 0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 310.950 312.208 542.000 169,216.74 0 SUBTOTAL BID ITEMS $ 187,846.74 0 CONTRACT TOTAL ALL ITEMS $ 187,846.74 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11110104 MGR.NO. 008 PAGE 001 CONT 6232 SEC 94 JOB 001 RES ENGR SELMAN, DAVID PROJ RMC - 623294001 HWY US0069 3904 US 75 SOUTH SHERMAN CNTY GRAYSON DIST 01 CONTRACT PRICE $ 187,164.90 REPORT DATE 06/04/2012 16.45.30 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD FEB 20,2012 TO MAR 31,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 92 RMC - 623294001 6232-94-001 187,846.74 .00 187,846.74 .00 .00 187,846.74 187,846.74 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 187,846.74 .00 187,846.74 .00 .00 187,846.74 187,846.74 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11110104 MGR.NO. 008 PAGE 001 CONT 6232 SEC 94 JOB 001 RES ENGR SELMAN, DAVID PROJ RMC - 623294001 HWY US0069 3904 US 75 SOUTH SHERMAN CNTY GRAYSON DIST 01 CONTRACT PRICE $ 187,164.90 REPORT DATE 06/04/2012 16.45.30 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD FEB 20,2012 TO MAR 31,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6232-94-001 RMC - 623294001 01 US0069 GRAYSON -LIMITS - VARIOUS ROADWAYS IN GRAYSON AND FANNIN COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 187,846.74