1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7094001 MGR.NO. 009 PAGE 001 CONT 6193 SEC 26 JOB 001 RES ENGR MISER, CRAIG PROJ RMC - 619326001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 421,440.00 REPORT DATE 06/25/2010 15.20.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD SEP 14,2009 TO MAY 28,2010 EST NO 010 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 14, 2009 TIME COMPUTED FROM SEP 21, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 36 229 69 160 BROUGHT FORWARD ADDL DAYS GRANTED = 14 MAY 10 1 1 SATURDAY TOTAL DAYS ALLOWED = 50 2 1 SUNDAY DATE WORK COMPLETED 05/28/10 3 1 DAYS CHARGED TO DATE = 70 4 1 WAITING ON FINAL DOCUMENTATION ASSESSED LIQ DAMAGES = 20 5 1 WAITING ON FINAL DOCUMENTATION LIQ DAMAGE RATE $ 500 6 1 WAITING ON FINAL DOCUMENTATION 7 1 WAITING ON FINAL DOCUMENTATION LIQUIDATED DAMAGES 8 1 WAITING ON FINAL DOCUMENTATION 20 DAYS AT $ 500 PER DAY 9 1 WAITING ON FINAL DOCUMENTATION TOTAL = $ 10,000.00 10 1 WAITING ON FINAL DOCUMENTATION 11 1 WAITING ON FINAL DOCUMENTATION CERTIFIED AS CORRECT AND 12 1 WAITING ON FINAL DOCUMENTATION ONE COPY HAS BEEN GIVEN 13 1 WAITING ON FINAL DOCUMENTATION TO THE CONTRACTOR 14 1 WAITING ON FINAL DOCUMENTATION 15 1 WAITING ON FINAL DOCUMENTATION 16 1 WAITING ON FINAL DOCUMENTATION ---------------------------- 17 1 WAITING ON FINAL DOCUMENTATION AREA/PROJECT ENGINEER 18 1 WAITING ON FINAL DOCUMENTATION 19 1 WAITING ON FINAL DOCUMENTATION 20 1 WAITING ON FINAL DOCUMENTATION 21 1 WAITING ON FINAL DOCUMENTATION 22 1 WAITING ON FINAL DOCUMENTATION 23 1 WAITING ON FINAL DOCUMENTATION 24 1 WAITING ON FINAL DOCUMENTATION 25 1 WAITING ON FINAL DOCUMENTATION 26 1 WAITING ON FINAL DOCUMENTATION 27 1 WAITING ON FINAL DOCUMENTATION 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 257 70 187 1 SATURDAY 1 SUNDAY 0 HOLIDAY 24 WAITING ON FINAL DOCUMENTATION 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7094001 MGR.NO. 009 PAGE 001 CONT 6193 SEC 26 JOB 001 RES ENGR MISER, CRAIG PROJ RMC - 619326001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 421,440.00 REPORT DATE 06/25/2010 15.20.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD SEP 14,2009 TO MAY 28,2010 EST NO 010 & FINAL DIST. 01 COUNTY HOPKINS CONTROL 6193-26-001 PROJECT RMC - 619326001 HIGHWAY IH0030 0LIMITS- FM 499 LOOP 301 0TYPE OF WORK- FULL DEPTH CONCRETE REPAIR 0 0005 PREPARED BY SULPHUR SPRINGS AREA OFFICE 0 0055 FULL DEPTH CONCRETE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0361 FULL-DEPTH REPAIR CRCP (13") SY 2,500.000 2,523.927 166.000 418,971.88 0065 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 5.000 3,220.000 16,100.00 0065 0502 ADJ EST QUANTITY TO DATE 5.000 0 SUBTOTAL BID ITEMS $ 435,071.88 0 TOTAL AMOUNT WORK DONE FULL DEPTH CONCRETE REPAIR $ 435,071.88 0 TOTAL AMOUNT WORK DONE CONTROL 6193-26-001 $ 435,071.88 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7094001 MGR.NO. 009 PAGE 001 CONT 6193 SEC 26 JOB 001 RES ENGR MISER, CRAIG PROJ RMC - 619326001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 421,440.00 REPORT DATE 06/25/2010 15.20.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD SEP 14,2009 TO MAY 28,2010 EST NO 010 & FINAL 0*********************************************************************************************************************************** -LIMITS - FM 499 0 LOOP 301 DATE WORK BEGAN SEP 14, 2009 WORKING DAYS USED 70 PERCENT COMPLETE 100.00 PERCENT TIME USED 140.00 DATE COMPLETED MAY 28 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6193-26-001 RMC - 619326001 01 IH0030 HOPKINS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0361 FULL-DEPTH REPAIR CRCP (13") SY 2,500.000 2,523.927 166.000 418,971.88 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 5.000 3,220.000 16,100.00 0502 ADJ EST QUANTITY TO DATE 5.000 0 SUBTOTAL BID ITEMS $ 435,071.88 0 CONTRACT TOTAL ALL ITEMS $ 435,071.88 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7094001 MGR.NO. 009 PAGE 001 CONT 6193 SEC 26 JOB 001 RES ENGR MISER, CRAIG PROJ RMC - 619326001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 421,440.00 REPORT DATE 06/25/2010 15.20.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD SEP 14,2009 TO MAY 28,2010 EST NO 010 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 113 RMC - 619326001 6193-26-001 435,071.88 .00 435,071.88 .00 10,000.00 425,071.88 425,071.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 435,071.88 .00 435,071.88 .00 10,000.00 425,071.88 425,071.88 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7094001 MGR.NO. 009 PAGE 001 CONT 6193 SEC 26 JOB 001 RES ENGR MISER, CRAIG PROJ RMC - 619326001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 421,440.00 REPORT DATE 06/25/2010 15.20.18 CONTRACTOR NIXON ENGINEERING 9390 EST PERIOD SEP 14,2009 TO MAY 28,2010 EST NO 010 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6193-26-001 RMC - 619326001 01 IH0030 HOPKINS -LIMITS - FM 499 LOOP 301 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 435,071.88