1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12080111 MGR.NO. 009 PAGE 001 CONT 6185 SEC 66 JOB 001 RES ENGR BARNES, JAN PROJ RMC - 618566001 HWY IH0030 1365 N MAIN PARIS CNTY HOPKINS DIST 01 CONTRACT PRICE $ 80,362.62 REPORT DATE 10/28/2009 16.56.18 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 15, 2009 TIME COMPUTED FROM JUN 22, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 39 108 23 85 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 09 1 1 BETWEEN CYCLES TOTAL DAYS ALLOWED = 39 2 1 BETWEEN CYCLES DATE WORK COMPLETED 3 1 BETWEEN CYCLES DAYS CHARGED TO DATE = 23 4 1 BETWEEN CYCLES ASSESSED LIQ DAMAGES = 0 5 1 TIME NOT STARTED LIQ DAMAGE RATE $ 400 6 1 TIME NOT STARTED 7 1 TIME NOT STARTED LIQUIDATED DAMAGES 8 1 TIME NOT STARTED 0 DAYS AT $ 400 PER DAY 9 1 TIME NOT STARTED TOTAL = $ .00 10 1 TIME NOT STARTED 11 1 TIME NOT STARTED CERTIFIED AS CORRECT AND 12 1 TOO WET ONE COPY HAS BEEN GIVEN 13 1 TOO WET TO THE CONTRACTOR 14 1 TOO WET 15 1 TOO WET 16 1 TOO WET ---------------------------- 17 1 SATURDAY AREA/PROJECT ENGINEER 18 1 SUNDAY 19 1 TOO WET 20 1 TOO WET 21 1 TOO WET 22 1 TOO WET 23 1 TOO WET 24 1 SATURDAY 25 1 SUNDAY 26 1 TOO WET 27 1 TOO WET 28 1 TOO WET 29 1 TOO WET 30 1 TOO WET 31 1 SATURDAY ----- ----- ----- 139 23 116 3 SATURDAY 2 SUNDAY 0 HOLIDAY 4 BETWEEN CYCLES 7 TIME NOT STARTED 15 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12080111 MGR.NO. 009 PAGE 001 CONT 6185 SEC 66 JOB 001 RES ENGR BARNES, JAN PROJ RMC - 618566001 HWY IH0030 1365 N MAIN PARIS CNTY HOPKINS DIST 01 CONTRACT PRICE $ 80,362.62 REPORT DATE 10/28/2009 16.56.19 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 DIST. 01 COUNTY HOPKINS CONTROL 6185-66-001 PROJECT RMC - 618566001 HIGHWAY IH0030 0LIMITS- IH30 THROUGH HOPKINS & FRANKLIN COUNTIES & INTERCITY AREAS 0TYPE OF WORK- MOWING HIGHWAY ROW 0 0005 JOHN MCCOLLISTER 11/13/08 OTHER: 0010 MON-FRI, EXCEPT NAT HOL; SAT/STATE HOL OPTIONAL 0 0060 MOWING HIGHWAY RIGHT OF WAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0065 0730 FULL-WIDTH MOWING AC 4,758.000 3,172.000 16.890 53,575.08 0 SUBTOTAL BID ITEMS $ 53,575.08 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 53,575.08 0 TOTAL AMOUNT WORK DONE CONTROL 6185-66-001 $ 53,575.08 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12080111 MGR.NO. 009 PAGE 001 CONT 6185 SEC 66 JOB 001 RES ENGR BARNES, JAN PROJ RMC - 618566001 HWY IH0030 1365 N MAIN PARIS CNTY HOPKINS DIST 01 CONTRACT PRICE $ 80,362.62 REPORT DATE 10/28/2009 16.56.19 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 0*********************************************************************************************************************************** -LIMITS - IH30 THROUGH HOPKINS & FRANKLIN COUNTIES 0 & INTERCITY AREAS DATE WORK BEGAN JUN 15, 2009 WORKING DAYS USED 23 PERCENT COMPLETE 66.66 PERCENT TIME USED 58.90 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6185-66-001 RMC - 618566001 01 IH0030 HOPKINS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 4,758.000 3,172.000 16.890 53,575.08 0 SUBTOTAL BID ITEMS $ 53,575.08 0 CONTRACT TOTAL ALL ITEMS $ 53,575.08 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12080111 MGR.NO. 009 PAGE 001 CONT 6185 SEC 66 JOB 001 RES ENGR BARNES, JAN PROJ RMC - 618566001 HWY IH0030 1365 N MAIN PARIS CNTY HOPKINS DIST 01 CONTRACT PRICE $ 80,362.62 REPORT DATE 10/28/2009 16.56.19 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 113 RMC - 618566001 6185-66-001 53,575.08 .00 53,575.08 .00 .00 53,575.08 53,575.08 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 53,575.08 .00 53,575.08 .00 .00 53,575.08 53,575.08 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12080111 MGR.NO. 009 PAGE 001 CONT 6185 SEC 66 JOB 001 RES ENGR BARNES, JAN PROJ RMC - 618566001 HWY IH0030 1365 N MAIN PARIS CNTY HOPKINS DIST 01 CONTRACT PRICE $ 80,362.62 REPORT DATE 10/28/2009 16.56.19 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD OCT 01,2009 TO OCT 31,2009 EST NO 005 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6185-66-001 RMC - 618566001 01 IH0030 HOPKINS -LIMITS - IH30 THROUGH HOPKINS & FRANKLIN COUNTIES & INTERCITY AREAS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 53,575.08