1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3120605 MGR.NO. 771 PAGE 001 CONT 6235 SEC 25 JOB 001 RES ENGR STROOPE,MIKE PROJ RMC - 623525001 HWY US0385 3901 E. HWY 80 ODESSA CNTY ANDREWS DIST 06 CONTRACT PRICE $ 139,185.60 REPORT DATE 01/04/2013 08.43.54 CONTRACTOR LUBBOCK LAWN SERVICE 7043 EST PERIOD DEC 01,2012 TO DEC 31,2012 EST NO 006 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 10, 2012 TIME COMPUTED FROM JUL 23, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 56 144 31 113 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 12 1 1 SATURDAY TOTAL DAYS ALLOWED = 56 2 1 SUNDAY DATE WORK COMPLETED 3 1 NO WORK SCHEDULED DAYS CHARGED TO DATE = 40 4 1 NO WORK SCHEDULED ASSESSED LIQ DAMAGES = 0 5 1 NO CHARGES TIME HAD NOT STARTED LIQ DAMAGE RATE $ 500 6 1 NO CHARGES TIME HAD NOT STARTED 7 1 NO CHARGES TIME HAD NOT STARTED LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 500 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 NO CHARGES TIME HAD NOT STARTED 11 1 RAIN CERTIFIED AS CORRECT AND 12 1 TIME CHARGES STARTED FOR THIS ESTIMATE ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 WORK IS COMPLETED FOR THIS ESTIMATE 23 1 NO WORK SCHEDULED 24 1 NO WORK SCHEDULED 25 1 NO WORK SCHEDULED 26 1 NO WORK SCHEDULED 27 1 NO WORK SCHEDULED 28 1 NO WORK SCHEDULED 29 1 NO WORK SCHEDULED 30 1 NO WORK SCHEDULED 31 1 NO WORK SCHEDULED ----- ----- ----- 175 40 135 3 SATURDAY 3 SUNDAY 0 HOLIDAY 11 NO WORK SCHEDULED 4 NO CHARGES TIME HAD NOT STARTED 1 RAIN 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3120605 MGR.NO. 771 PAGE 001 CONT 6235 SEC 25 JOB 001 RES ENGR STROOPE,MIKE PROJ RMC - 623525001 HWY US0385 3901 E. HWY 80 ODESSA CNTY ANDREWS DIST 06 CONTRACT PRICE $ 139,185.60 REPORT DATE 01/04/2013 08.43.55 CONTRACTOR LUBBOCK LAWN SERVICE 7043 EST PERIOD DEC 01,2012 TO DEC 31,2012 EST NO 006 DIST. 06 COUNTY ANDREWS CONTROL 6235-25-001 PROJECT RMC - 623525001 HIGHWAY US0385 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- ROADSIDE MOWING 0 0050 ROADSIDE MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 ANDREWS MOWING CONTRACT BY LEE 09/28/11 0 0075 0730 STRIP MOWING AC 1,066.000 533.000 21.400 11,406.20 0080 0730 FULL-WIDTH MOWING AC 5,438.000 2,719.000 21.400 58,186.60 0 SUBTOTAL BID ITEMS $ 69,592.80 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 69,592.80 0 TOTAL AMOUNT WORK DONE CONTROL 6235-25-001 $ 69,592.80 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3120605 MGR.NO. 771 PAGE 001 CONT 6235 SEC 25 JOB 001 RES ENGR STROOPE,MIKE PROJ RMC - 623525001 HWY US0385 3901 E. HWY 80 ODESSA CNTY ANDREWS DIST 06 CONTRACT PRICE $ 139,185.60 REPORT DATE 01/04/2013 08.43.55 CONTRACTOR LUBBOCK LAWN SERVICE 7043 EST PERIOD DEC 01,2012 TO DEC 31,2012 EST NO 006 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUL 10, 2012 WORKING DAYS USED 40 PERCENT COMPLETE 50.00 PERCENT TIME USED 71.40 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6235-25-001 RMC - 623525001 06 US0385 ANDREWS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 1,066.000 533.000 21.400 11,406.20 0730 FULL-WIDTH MOWING AC 5,438.000 2,719.000 21.400 58,186.60 0 SUBTOTAL BID ITEMS $ 69,592.80 0 CONTRACT TOTAL ALL ITEMS $ 69,592.80 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3120605 MGR.NO. 771 PAGE 001 CONT 6235 SEC 25 JOB 001 RES ENGR STROOPE,MIKE PROJ RMC - 623525001 HWY US0385 3901 E. HWY 80 ODESSA CNTY ANDREWS DIST 06 CONTRACT PRICE $ 139,185.60 REPORT DATE 01/04/2013 08.43.55 CONTRACTOR LUBBOCK LAWN SERVICE 7043 EST PERIOD DEC 01,2012 TO DEC 31,2012 EST NO 006 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 2 RMC - 623525001 6235-25-001 69,592.80 .00 69,592.80 .00 .00 69,592.80 29,211.00 40,381.80 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 69,592.80 .00 69,592.80 .00 .00 69,592.80 29,211.00 40,381.80 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3120605 MGR.NO. 771 PAGE 001 CONT 6235 SEC 25 JOB 001 RES ENGR STROOPE,MIKE PROJ RMC - 623525001 HWY US0385 3901 E. HWY 80 ODESSA CNTY ANDREWS DIST 06 CONTRACT PRICE $ 139,185.60 REPORT DATE 01/04/2013 08.43.56 CONTRACTOR LUBBOCK LAWN SERVICE 7043 EST PERIOD DEC 01,2012 TO DEC 31,2012 EST NO 006 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6235-25-001 RMC - 623525001 06 US0385 ANDREWS -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0730 FULL-WIDTH MOWING AC 5,438.000 1,887.000 21.400 40,381.80 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 40,381.80 0 TOTAL AMOUNT WORK DONE TO DATE - $ 69,592.80