1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5090601 MGR.NO. PAGE 001 CONT 6193 SEC 88 JOB 001 RES ENGR SINCLAIR, HEATHER PROJ RMC - 619388001 HWY IH0020 5100 W. IH 20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 70,321.60 REPORT DATE 09/14/2009 10.17.34 CONTRACTOR AJAX EQUIPMENT COMPANY 6298 EST PERIOD JUN 10,2009 TO AUG 10,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 10, 2009 TIME COMPUTED FROM JUN 12, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 20 52 18 34 BROUGHT FORWARD ADDL DAYS GRANTED = 10 AUG 09 1 1 SATURDAY TOTAL DAYS ALLOWED = 30 2 1 SUNDAY DATE WORK COMPLETED 08/10/09 3 1 DAYS CHARGED TO DATE = 21 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 WORK COMPLETED 7 1 WAITING FOR REVIEW AND ACCEPTANCE LIQUIDATED DAMAGES 8 1 SATURDAY 0 DAYS AT $ 400 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 WORK ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 62 21 41 2 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED 1 WAITING FOR REVIEW AND ACCEPTANCE 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5090601 MGR.NO. PAGE 001 CONT 6193 SEC 88 JOB 001 RES ENGR SINCLAIR, HEATHER PROJ RMC - 619388001 HWY IH0020 5100 W. IH 20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 70,321.60 REPORT DATE 09/14/2009 10.17.35 CONTRACTOR AJAX EQUIPMENT COMPANY 6298 EST PERIOD JUN 10,2009 TO AUG 10,2009 EST NO 003 & FINAL DIST. 06 COUNTY MIDLAND CONTROL 6193-88-001 PROJECT RMC - 619388001 HIGHWAY IH0020 0LIMITS- STA. 1204+53.69 STA. 1205+26.16 0TYPE OF WORK- BRIDGE REPAIR 0 0005 MIDLAND COUNTY 0 0055 BRIDGE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0058 0427*CONCRETE PAINT FINISH SF 50.000 50.000 30.000 1,500.00 0059 0429*CONC STRUCT REPAIR SF 50.000 41.000 147.000 6,027.00 0060 0442 STR STL (MISCELLANEOUS) LB 457.600 457.600 16.000 7,321.60 0065 0500 MOBILIZATION LS 1.000 1.000 7,000.000 7,000.00 0070 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 7,000.000 7,000.00 0075 0788 CONCRETE BEAM REPAIR EA 2.000 2.000 8,000.000 16,000.00 0080 0788 CONCRETE BEAM REPAIR (CFRP) EA 1.000 1.000 11,000.000 11,000.00 0085 0788 CONCRETE BEAM REP(STRAND SPLICE & CFRP) EA 2.000 2.000 11,000.000 22,000.00 0 SUBTOTAL BID ITEMS $ 77,848.60 0 TOTAL AMOUNT WORK DONE BRIDGE REPAIR $ 77,848.60 0 TOTAL AMOUNT WORK DONE CONTROL 6193-88-001 $ 77,848.60 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5090601 MGR.NO. PAGE 001 CONT 6193 SEC 88 JOB 001 RES ENGR SINCLAIR, HEATHER PROJ RMC - 619388001 HWY IH0020 5100 W. IH 20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 70,321.60 REPORT DATE 09/14/2009 10.17.35 CONTRACTOR AJAX EQUIPMENT COMPANY 6298 EST PERIOD JUN 10,2009 TO AUG 10,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - STA. 1204+53.69 0 STA. 1205+26.16 DATE WORK BEGAN JUN 10, 2009 WORKING DAYS USED 21 PERCENT COMPLETE 100.00 PERCENT TIME USED 70.00 DATE COMPLETED AUG 10 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6193-88-001 RMC - 619388001 06 IH0020 MIDLAND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0442 STR STL (MISCELLANEOUS) LB 457.600 457.600 16.000 7,321.60 0500 MOBILIZATION LS 1.000 1.000 7,000.000 7,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 7,000.000 7,000.00 0788 CONCRETE BEAM REPAIR EA 2.000 2.000 8,000.000 16,000.00 0788 CONCRETE BEAM REPAIR (CFRP) EA 1.000 1.000 11,000.000 11,000.00 0788 CONCRETE BEAM REP(STRAND SPLICE & CFRP) EA 2.000 2.000 11,000.000 22,000.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00427* CONCRETE PAINT FINISH SF 50.000 50.000 30.000 1,500.00 0429* CONC STRUCT REPAIR SF 50.000 41.000 147.000 6,027.00 0 SUBTOTAL BID ITEMS $ 77,848.60 0 CONTRACT TOTAL ALL ITEMS $ 77,848.60 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5090601 MGR.NO. PAGE 001 CONT 6193 SEC 88 JOB 001 RES ENGR SINCLAIR, HEATHER PROJ RMC - 619388001 HWY IH0020 5100 W. IH 20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 70,321.60 REPORT DATE 09/14/2009 10.17.35 CONTRACTOR AJAX EQUIPMENT COMPANY 6298 EST PERIOD JUN 10,2009 TO AUG 10,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 165 RMC - 619388001 6193-88-001 77,848.60 .00 77,848.60 .00 .00 77,848.60 64,130.40 13,718.20 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 77,848.60 .00 77,848.60 .00 .00 77,848.60 64,130.40 13,718.20 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5090601 MGR.NO. PAGE 001 CONT 6193 SEC 88 JOB 001 RES ENGR SINCLAIR, HEATHER PROJ RMC - 619388001 HWY IH0020 5100 W. IH 20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 70,321.60 REPORT DATE 09/14/2009 10.17.35 CONTRACTOR AJAX EQUIPMENT COMPANY 6298 EST PERIOD JUN 10,2009 TO AUG 10,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6193-88-001 RMC - 619388001 06 IH0020 MIDLAND -LIMITS - STA. 1204+53.69 STA. 1205+26.16 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0442 STR STL (MISCELLANEOUS) LB 457.600 343.200 16.000 5,491.20 65 0500 MOBILIZATION LS 1.000 0.100 7,000.000 700.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 58 0427* CONCRETE PAINT FINISH SF 0.000 50.000 30.000 1,500.00 59 0429* CONC STRUCT REPAIR SF 0.000 41.000 147.000 6,027.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 13,718.20 0 TOTAL AMOUNT WORK DONE TO DATE - $ 77,848.60