1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2090601 MGR.NO. 053 PAGE 001 CONT 6180 SEC 39 JOB 001 RES ENGR EICHORST, DOUG PROJ BPM - 618039001 HWY BI0020F 5100 W. IH20 MIDLAND CNTY MARTIN DIST 06 CONTRACT PRICE $ 156,812.00 REPORT DATE 09/14/2009 09.58.24 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 28,2009 TO AUG 21,2009 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 28, 2009 TIME COMPUTED FROM JUL 28, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 50 4 3 1 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 SATURDAY TOTAL DAYS ALLOWED = 50 2 1 SUNDAY DATE WORK COMPLETED 08/21/09 3 1 DAYS CHARGED TO DATE = 14 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 SATURDAY 16 1 SUNDAY ---------------------------- 17 1 WORK COMPLETED AREA/PROJECT ENGINEER 18 1 TIME SUSPENDED PENDING ACCEPTANCE 19 1 TIME SUSPENDED PENDING ACCEPTANCE 20 1 TIME SUSPENDED PENDING ACCEPTANCE 21 1 WORK ACCEPTED - - - 0 ----- ----- ----- 25 14 11 2 SATURDAY 3 SUNDAY 0 HOLIDAY 1 WORK COMPLETED 3 TIME SUSPENDED PENDING ACCEPTANCE 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2090601 MGR.NO. 053 PAGE 001 CONT 6180 SEC 39 JOB 001 RES ENGR EICHORST, DOUG PROJ BPM - 618039001 HWY BI0020F 5100 W. IH20 MIDLAND CNTY MARTIN DIST 06 CONTRACT PRICE $ 156,812.00 REPORT DATE 09/14/2009 09.58.24 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 28,2009 TO AUG 21,2009 EST NO 002 & FINAL DIST. 06 COUNTY MARTIN CONTROL 6180-39-001 PROJECT BPM - 618039001 HIGHWAY BI0020F 0LIMITS- RM 158 RM 159 0TYPE OF WORK- BRIDGE REPAIR 0 0005 MARTIN COUNTY 0 0055 BRIDGE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0434 ELASTOMERIC BEAR (EE1) EA 10.000 10.000 1,600.000 16,000.00 0065 0434 ELASTOMERIC BEAR (E1) EA 5.000 5.000 2,000.000 10,000.00 0070 0434 ELASTOMERIC BEAR (F1) EA 10.000 10.000 2,000.000 20,000.00 0075 0420 CL F CONC (PEDESTAL) EA 10.000 10.000 500.000 5,000.00 0080 0442 STR STL (MISCELLANEOUS) LB 6,453.000 6,453.000 4.000 25,812.00 0085 0495 RAISING EXIST STRUCT LS 1.000 1.000 80,000.000 80,000.00 0 SUBTOTAL BID ITEMS $ 156,812.00 0 TOTAL AMOUNT WORK DONE BRIDGE REPAIR $ 156,812.00 0 TOTAL AMOUNT WORK DONE CONTROL 6180-39-001 $ 156,812.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2090601 MGR.NO. 053 PAGE 001 CONT 6180 SEC 39 JOB 001 RES ENGR EICHORST, DOUG PROJ BPM - 618039001 HWY BI0020F 5100 W. IH20 MIDLAND CNTY MARTIN DIST 06 CONTRACT PRICE $ 156,812.00 REPORT DATE 09/14/2009 09.58.24 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 28,2009 TO AUG 21,2009 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - RM 158 0 RM 159 DATE WORK BEGAN JUL 28, 2009 WORKING DAYS USED 14 PERCENT COMPLETE 100.00 PERCENT TIME USED 28.00 DATE COMPLETED AUG 21 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6180-39-001 BPM - 618039001 06 BI0020F MARTIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0420 CL F CONC (PEDESTAL) EA 10.000 10.000 500.000 5,000.00 0434 ELASTOMERIC BEAR (EE1) EA 10.000 10.000 1,600.000 16,000.00 0434 ELASTOMERIC BEAR (E1) EA 5.000 5.000 2,000.000 10,000.00 0434 ELASTOMERIC BEAR (F1) EA 10.000 10.000 2,000.000 20,000.00 0442 STR STL (MISCELLANEOUS) LB 6,453.000 6,453.000 4.000 25,812.00 0495 RAISING EXIST STRUCT LS 1.000 1.000 80,000.000 80,000.00 0 SUBTOTAL BID ITEMS $ 156,812.00 0 CONTRACT TOTAL ALL ITEMS $ 156,812.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2090601 MGR.NO. 053 PAGE 001 CONT 6180 SEC 39 JOB 001 RES ENGR EICHORST, DOUG PROJ BPM - 618039001 HWY BI0020F 5100 W. IH20 MIDLAND CNTY MARTIN DIST 06 CONTRACT PRICE $ 156,812.00 REPORT DATE 09/14/2009 09.58.24 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 28,2009 TO AUG 21,2009 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 156 BPM - 618039001 6180-39-001 156,812.00 .00 156,812.00 .00 .00 156,812.00 .00 156,812.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 156,812.00 .00 156,812.00 .00 .00 156,812.00 .00 156,812.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2090601 MGR.NO. 053 PAGE 001 CONT 6180 SEC 39 JOB 001 RES ENGR EICHORST, DOUG PROJ BPM - 618039001 HWY BI0020F 5100 W. IH20 MIDLAND CNTY MARTIN DIST 06 CONTRACT PRICE $ 156,812.00 REPORT DATE 09/14/2009 09.58.25 CONTRACTOR SCR CONSTRUCTION CO., INC. 2002 EST PERIOD JUL 28,2009 TO AUG 21,2009 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6180-39-001 BPM - 618039001 06 BI0020F MARTIN -LIMITS - RM 158 RM 159 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0420 CL F CONC (PEDESTAL) EA 10.000 10.000 500.000 5,000.00 60 0434 ELASTOMERIC BEAR (EE1) EA 10.000 10.000 1,600.000 16,000.00 65 0434 ELASTOMERIC BEAR (E1) EA 5.000 5.000 2,000.000 10,000.00 70 0434 ELASTOMERIC BEAR (F1) EA 10.000 10.000 2,000.000 20,000.00 80 0442 STR STL (MISCELLANEOUS) LB 6,453.000 6,453.000 4.000 25,812.00 85 0495 RAISING EXIST STRUCT LS 1.000 1.000 80,000.000 80,000.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 156,812.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 156,812.00