1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7080633 MGR.NO. 053 PAGE 001 CONT 6180 SEC 19 JOB 001 RES ENGR EICHORST, DOUG PROJ SUP - 618019001 HWY IH0020 5100 W. IH20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 84,985.39 REPORT DATE 09/04/2009 07.09.42 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 012 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2008 TIME COMPUTED FROM SEP 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 08/31/09 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7080633 MGR.NO. 053 PAGE 001 CONT 6180 SEC 19 JOB 001 RES ENGR EICHORST, DOUG PROJ SUP - 618019001 HWY IH0020 5100 W. IH20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 84,985.39 REPORT DATE 09/04/2009 07.09.43 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 012 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 DIST. 06 COUNTY MIDLAND CONTROL 6180-19-001 PROJECT SUP - 618019001 HIGHWAY IH0020 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- LITTER PICKUP 0 0050 LITTER REMOVAL NET LENGTH150.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 ESTIMATE PREPARED BY CHRISTI FOOTE 0 0075 0734 LITTER REMOVAL AC 725.000 505.000 21.310 10,761.55 0080 0734 LITTER REMOVAL - TRACT (2) AC 1,716.000 1,430.000 14.290 20,434.70 0080 0734 ADJ EST QUANTITY TO DATE 1,430.000 0085 0734 LITTER REMOVAL - TRACT (3) AC 1,686.000 1,686.000 13.150 22,170.90 0090 0734 LITTER REMOVAL - TRACT (4) AC 270.000 270.000 17.270 4,662.90 0095 0734 LITTER REMOVAL - TRACT (5) AC 220.000 220.000 14.360 3,159.20 0100 0734 LITTER REMOVAL - TRACT (6) AC 324.000 297.000 27.150 8,063.55 0100 0734 ADJ EST QUANTITY TO DATE 297.000 0105 0734 LITTER REMOVAL - TRACT (7) AC 390.000 325.000 15.960 5,187.00 0105 0734 ADJ EST QUANTITY TO DATE 325.000 0110 9001*LITTER REMOVAL-TRACT#2 AC 286.000 286.000 15.820 4,524.52 0115 9001*LITTER REMOVAL TRACT#6 AC 27.000 27.000 30.060 811.62 0120 9001*LITTER REMOVAL TRACT#7 AC 65.000 65.000 17.670 1,148.55 0 SUBTOTAL BID ITEMS $ 80,924.49 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 80,924.49 0 TOTAL AMOUNT WORK DONE CONTROL 6180-19-001 $ 80,924.49 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7080633 MGR.NO. 053 PAGE 001 CONT 6180 SEC 19 JOB 001 RES ENGR EICHORST, DOUG PROJ SUP - 618019001 HWY IH0020 5100 W. IH20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 84,985.39 REPORT DATE 09/04/2009 07.09.43 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 012 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN SEP 1 , 2008 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 31 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6180-19-001 SUP - 618019001 06 IH0020 MIDLAND - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL AC 725.000 505.000 21.310 10,761.55 0734 LITTER REMOVAL - TRACT (2) AC 1,716.000 1,430.000 14.290 20,434.70 0734 ADJ EST QUANTITY TO DATE 1,430.000 0734 LITTER REMOVAL - TRACT (3) AC 1,686.000 1,686.000 13.150 22,170.90 0734 LITTER REMOVAL - TRACT (4) AC 270.000 270.000 17.270 4,662.90 0734 LITTER REMOVAL - TRACT (5) AC 220.000 220.000 14.360 3,159.20 0734 LITTER REMOVAL - TRACT (6) AC 324.000 297.000 27.150 8,063.55 0734 ADJ EST QUANTITY TO DATE 297.000 0734 LITTER REMOVAL - TRACT (7) AC 390.000 325.000 15.960 5,187.00 0734* ADJ EST QUANTITY TO DATE 325.000 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* LITTER REMOVAL-TRACT#2 AC 286.000 286.000 15.820 4,524.52 9001* LITTER REMOVAL TRACT#6 AC 27.000 27.000 30.060 811.62 9001* LITTER REMOVAL TRACT#7 AC 65.000 65.000 17.670 1,148.55 0 SUBTOTAL BID ITEMS $ 80,924.49 0 CONTRACT TOTAL ALL ITEMS $ 80,924.49 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7080633 MGR.NO. 053 PAGE 001 CONT 6180 SEC 19 JOB 001 RES ENGR EICHORST, DOUG PROJ SUP - 618019001 HWY IH0020 5100 W. IH20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 84,985.39 REPORT DATE 09/04/2009 07.09.43 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 012 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 165 SUP - 618019001 6180-19-001 80,924.49 .00 80,924.49 .00 .00 80,924.49 73,693.95 7,230.54 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 80,924.49 .00 80,924.49 .00 .00 80,924.49 73,693.95 7,230.54 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7080633 MGR.NO. 053 PAGE 001 CONT 6180 SEC 19 JOB 001 RES ENGR EICHORST, DOUG PROJ SUP - 618019001 HWY IH0020 5100 W. IH20 MIDLAND CNTY MIDLAND DIST 06 CONTRACT PRICE $ 84,985.39 REPORT DATE 09/04/2009 07.09.43 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO AUG 31,2009 EST NO 012 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6180-19-001 SUP - 618019001 06 IH0020 MIDLAND -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 75 0734 LITTER REMOVAL AC 725.000 35.000 21.310 745.85 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 110 9001* LITTER REMOVAL-TRACT#2 AC 0.000 286.000 15.820 4,524.52 115 9001* LITTER REMOVAL TRACT#6 AC 0.000 27.000 30.060 811.62 120 9001* LITTER REMOVAL TRACT#7 AC 0.000 65.000 17.670 1,148.55 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 7,230.54 0 TOTAL AMOUNT WORK DONE TO DATE - $ 80,924.49