1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1080607 MGR.NO. 051 PAGE 001 CONT 6169 SEC 61 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616961001 HWY IH0010 EAST DICKENSON BLVD FT. S CNTY PECOS DIST 06 CONTRACT PRICE $ 275,418.00 REPORT DATE 12/23/2009 14.27.28 CONTRACTOR L&L COMPANY 13907 EST PERIOD AUG 11,2008 TO DEC 10,2009 EST NO 017 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN AUG 11, 2008 TIME COMPUTED FROM AUG 11, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 118 477 34 443 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 09 1 1 RAIN TOTAL DAYS ALLOWED = 118 2 1 DATE WORK COMPLETED 12/10/09 3 1 DAYS CHARGED TO DATE = 39 4 1 SNOW ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 400 6 1 SUNDAY 7 1 TOO WET LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY 9 1 TOTAL = $ .00 10 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 487 39 448 1 SATURDAY 1 SUNDAY 0 HOLIDAY 1 RAIN 1 SNOW 1 TOO WET 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1080607 MGR.NO. 051 PAGE 001 CONT 6169 SEC 61 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616961001 HWY IH0010 EAST DICKENSON BLVD FT. S CNTY PECOS DIST 06 CONTRACT PRICE $ 275,418.00 REPORT DATE 12/23/2009 14.27.28 CONTRACTOR L&L COMPANY 13907 EST PERIOD AUG 11,2008 TO DEC 10,2009 EST NO 017 & FINAL DIST. 06 COUNTY PECOS CONTROL 6169-61-001 PROJECT RMC - 616961001 HIGHWAY IH0010 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- ROADSIDE MOWING 0 0005 PROJECT MANAGER 051 PATRICK M. RYAN, P.E. 0 0055 ROADSIDE MOWING NET LENGTH267.320 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 14,124.000 13,752.000 19.500 268,164.00 0 SUBTOTAL BID ITEMS $ 268,164.00 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 268,164.00 0 TOTAL AMOUNT WORK DONE CONTROL 6169-61-001 $ 268,164.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1080607 MGR.NO. 051 PAGE 001 CONT 6169 SEC 61 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616961001 HWY IH0010 EAST DICKENSON BLVD FT. S CNTY PECOS DIST 06 CONTRACT PRICE $ 275,418.00 REPORT DATE 12/23/2009 14.27.28 CONTRACTOR L&L COMPANY 13907 EST PERIOD AUG 11,2008 TO DEC 10,2009 EST NO 017 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN AUG 11, 2008 WORKING DAYS USED 39 PERCENT COMPLETE 100.00 PERCENT TIME USED 33.00 DATE COMPLETED DEC 10 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6169-61-001 RMC - 616961001 06 IH0010 PECOS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 14,124.000 13,752.000 19.500 268,164.00 0 SUBTOTAL BID ITEMS $ 268,164.00 0 CONTRACT TOTAL ALL ITEMS $ 268,164.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1080607 MGR.NO. 051 PAGE 001 CONT 6169 SEC 61 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616961001 HWY IH0010 EAST DICKENSON BLVD FT. S CNTY PECOS DIST 06 CONTRACT PRICE $ 275,418.00 REPORT DATE 12/23/2009 14.27.28 CONTRACTOR L&L COMPANY 13907 EST PERIOD AUG 11,2008 TO DEC 10,2009 EST NO 017 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 186 RMC - 616961001 6169-61-001 268,164.00 .00 268,164.00 .00 .00 268,164.00 237,802.50 30,361.50 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 268,164.00 .00 268,164.00 .00 .00 268,164.00 237,802.50 30,361.50 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1080607 MGR.NO. 051 PAGE 001 CONT 6169 SEC 61 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616961001 HWY IH0010 EAST DICKENSON BLVD FT. S CNTY PECOS DIST 06 CONTRACT PRICE $ 275,418.00 REPORT DATE 12/23/2009 14.27.28 CONTRACTOR L&L COMPANY 13907 EST PERIOD AUG 11,2008 TO DEC 10,2009 EST NO 017 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6169-61-001 RMC - 616961001 06 IH0010 PECOS -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 14,124.000 1,557.000 19.500 30,361.50 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 30,361.50 0 TOTAL AMOUNT WORK DONE TO DATE - $ 268,164.00