1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10070605 MGR.NO. 051 PAGE 001 CONT 6167 SEC 23 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616723001 HWY IH0010 1207 E. DICKENSON FT. STO CNTY PECOS DIST 06 CONTRACT PRICE $ 40,355.72 REPORT DATE 08/18/2008 10.31.51 CONTRACTOR ANED CONSULTANTS, INC. 11389 EST PERIOD DEC 17,2007 TO AUG 08,2008 EST NO 009 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 17, 2007 TIME COMPUTED FROM DEC 17, 2007 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 228 193 35 BROUGHT FORWARD ADDL DAYS GRANTED = 1 AUG 08 1 1 TOTAL DAYS ALLOWED = 366 2 1 DATE WORK COMPLETED 08/08/08 3 1 DAYS CHARGED TO DATE = 201 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 400 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 400 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 236 201 35 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10070605 MGR.NO. 051 PAGE 001 CONT 6167 SEC 23 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616723001 HWY IH0010 1207 E. DICKENSON FT. STO CNTY PECOS DIST 06 CONTRACT PRICE $ 40,355.72 REPORT DATE 08/18/2008 10.31.51 CONTRACTOR ANED CONSULTANTS, INC. 11389 EST PERIOD DEC 17,2007 TO AUG 08,2008 EST NO 009 & FINAL DIST. 06 COUNTY PECOS CONTROL 6167-23-001 PROJECT RMC - 616723001 HIGHWAY IH0010 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- LITTER PICKUP 0 0005 PROJECT MANAGER 051, PATRICK RYAN, PE 0 0055 LITTER PICKUP NET LENGTH108.710 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL AC 5,747.600 2,810.900 6.990 19,648.19 0065 0734 LITTER REMOVAL(SPOT) AC 20.000 0.000 9.000 .00 0 SUBTOTAL BID ITEMS $ 19,648.19 0 TOTAL AMOUNT WORK DONE LITTER PICKUP $ 19,648.19 0 TOTAL AMOUNT WORK DONE CONTROL 6167-23-001 $ 19,648.19 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10070605 MGR.NO. 051 PAGE 001 CONT 6167 SEC 23 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616723001 HWY IH0010 1207 E. DICKENSON FT. STO CNTY PECOS DIST 06 CONTRACT PRICE $ 40,355.72 REPORT DATE 08/18/2008 10.31.52 CONTRACTOR ANED CONSULTANTS, INC. 11389 EST PERIOD DEC 17,2007 TO AUG 08,2008 EST NO 009 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN DEC 17, 2007 WORKING DAYS USED 201 PERCENT COMPLETE 100.00 PERCENT TIME USED 54.90 DATE COMPLETED AUG 8 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6167-23-001 RMC - 616723001 06 IH0010 PECOS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL AC 5,747.600 2,810.900 6.990 19,648.19 0 SUBTOTAL BID ITEMS $ 19,648.19 0 CONTRACT TOTAL ALL ITEMS $ 19,648.19 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10070605 MGR.NO. 051 PAGE 001 CONT 6167 SEC 23 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616723001 HWY IH0010 1207 E. DICKENSON FT. STO CNTY PECOS DIST 06 CONTRACT PRICE $ 40,355.72 REPORT DATE 08/18/2008 10.31.52 CONTRACTOR ANED CONSULTANTS, INC. 11389 EST PERIOD DEC 17,2007 TO AUG 08,2008 EST NO 009 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 186 RMC - 616723001 6167-23-001 19,648.19 .00 19,648.19 .00 .00 19,648.19 19,648.19 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 19,648.19 .00 19,648.19 .00 .00 19,648.19 19,648.19 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10070605 MGR.NO. 051 PAGE 001 CONT 6167 SEC 23 JOB 001 RES ENGR RYAN, PATRICK PROJ RMC - 616723001 HWY IH0010 1207 E. DICKENSON FT. STO CNTY PECOS DIST 06 CONTRACT PRICE $ 40,355.72 REPORT DATE 08/18/2008 10.31.52 CONTRACTOR ANED CONSULTANTS, INC. 11389 EST PERIOD DEC 17,2007 TO AUG 08,2008 EST NO 009 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6167-23-001 RMC - 616723001 06 IH0010 PECOS -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 19,648.19