1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8122202 MGR.NO. 005 PAGE 001 CONT 6242 SEC 01 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 624201001 HWY US0083 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 256,500.00 REPORT DATE 05/06/2013 09.15.16 CONTRACTOR KEGLEY, INC. 7013 EST PERIOD OCT 17,2012 TO APR 22,2013 EST NO 007 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 17, 2012 TIME COMPUTED FROM OCT 17, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 166 166 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 WORK COMPLETED TOTAL DAYS ALLOWED = 365 2 1 WORK COMPLETED DATE WORK COMPLETED 04/22/13 3 1 WORK COMPLETED DAYS CHARGED TO DATE = 166 4 1 WORK COMPLETED ASSESSED LIQ DAMAGES = 0 5 1 WORK COMPLETED LIQ DAMAGE RATE $ 590 6 1 WORK COMPLETED 7 1 WORK COMPLETED LIQUIDATED DAMAGES 8 1 WORK COMPLETED 0 DAYS AT $ 590 PER DAY 9 1 WORK COMPLETED TOTAL = $ .00 10 1 WORK COMPLETED 11 1 WORK COMPLETED CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED TO THE CONTRACTOR 14 1 WORK COMPLETED 15 1 WORK COMPLETED 16 1 WORK COMPLETED ---------------------------- 17 1 WORK COMPLETED AREA/PROJECT ENGINEER 18 1 WORK COMPLETED 19 1 WORK COMPLETED 20 1 WORK COMPLETED 21 1 WORK COMPLETED 22 1 WORK COMPLETED AND ACCEPTED - - - ----- ----- ----- 188 166 22 0 SATURDAY 0 SUNDAY 0 HOLIDAY 21 WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8122202 MGR.NO. 005 PAGE 001 CONT 6242 SEC 01 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 624201001 HWY US0083 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 256,500.00 REPORT DATE 05/06/2013 09.15.17 CONTRACTOR KEGLEY, INC. 7013 EST PERIOD OCT 17,2012 TO APR 22,2013 EST NO 007 & FINAL DIST. 22 COUNTY WEBB CONTROL 6242-01-001 PROJECT RMC - 624201001 HIGHWAY US0083 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- CLEANING & CRACK SEALING OF HIGHWAYS 0 0050 CRACK SEALING CONTRACT NET LENGTH475.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY NPM 6-22-12 0 0075 0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 475.000 613.310 540.000 331,187.40 0075 0712 ADJ EST QUANTITY TO DATE 613.310 0 SUBTOTAL BID ITEMS $ 331,187.40 0 TOTAL AMOUNT WORK DONE CRACK SEALING CONTRACT $ 331,187.40 0 TOTAL AMOUNT WORK DONE CONTROL 6242-01-001 $ 331,187.40 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8122202 MGR.NO. 005 PAGE 001 CONT 6242 SEC 01 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 624201001 HWY US0083 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 256,500.00 REPORT DATE 05/06/2013 09.15.17 CONTRACTOR KEGLEY, INC. 7013 EST PERIOD OCT 17,2012 TO APR 22,2013 EST NO 007 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN OCT 17, 2012 WORKING DAYS USED 166 PERCENT COMPLETE 100.00 PERCENT TIME USED 45.40 DATE COMPLETED APR 22 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6242-01-001 RMC - 624201001 22 US0083 WEBB - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 475.000 613.310 540.000 331,187.40 0712 ADJ EST QUANTITY TO DATE 613.310 0 SUBTOTAL BID ITEMS $ 331,187.40 0 CONTRACT TOTAL ALL ITEMS $ 331,187.40 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8122202 MGR.NO. 005 PAGE 001 CONT 6242 SEC 01 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 624201001 HWY US0083 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 256,500.00 REPORT DATE 05/06/2013 09.15.17 CONTRACTOR KEGLEY, INC. 7013 EST PERIOD OCT 17,2012 TO APR 22,2013 EST NO 007 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 240 RMC - 624201001 6242-01-001 331,187.40 .00 331,187.40 .00 .00 331,187.40 331,187.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 331,187.40 .00 331,187.40 .00 .00 331,187.40 331,187.40 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8122202 MGR.NO. 005 PAGE 001 CONT 6242 SEC 01 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 624201001 HWY US0083 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 256,500.00 REPORT DATE 05/06/2013 09.15.17 CONTRACTOR KEGLEY, INC. 7013 EST PERIOD OCT 17,2012 TO APR 22,2013 EST NO 007 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6242-01-001 RMC - 624201001 22 US0083 WEBB -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 331,187.40