1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6092201 MGR.NO. 003 PAGE 001 CONT 6194 SEC 81 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 619481001 HWY FM0469 1817 BOB BULLOCK LP LARED CNTY LASALLE DIST 22 CONTRACT PRICE $ 243,511.48 REPORT DATE 08/31/2009 16.54.14 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 15,2009 TO AUG 01,2009 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 15, 2009 TIME COMPUTED FROM JUL 15, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 20 17 10 7 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 09 1 1 WORK COMPLETED AND ACCEPTED TOTAL DAYS ALLOWED = 20 DATE WORK COMPLETED 08/01/09 DAYS CHARGED TO DATE = 10 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 18 10 8 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6092201 MGR.NO. 003 PAGE 001 CONT 6194 SEC 81 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 619481001 HWY FM0469 1817 BOB BULLOCK LP LARED CNTY LASALLE DIST 22 CONTRACT PRICE $ 243,511.48 REPORT DATE 08/31/2009 16.54.15 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 15,2009 TO AUG 01,2009 EST NO 002 & FINAL DIST. 22 COUNTY LASALLE CONTROL 6194-81-001 PROJECT RMC - 619481001 HIGHWAY FM0469 0LIMITS- RM 450+1.50 RM 458+1.60 0TYPE OF WORK- BLADE LEVEL-UP 0 0050 BLADE LEVEL UP CONTRACT NET LENGTH 8.072 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY NPM 4-27-09 0 0075 0134 BACKFILL (TY B) STA 347.000 401.280 28.000 11,235.84 0075 0134 ADJ EST QUANTITY TO DATE 401.280 0080 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0085 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 2,815.000 2,815.00 0090 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 3,655.000 640.000 1.000 640.00 0090 0662 ADJ EST QUANTITY TO DATE 640.000 0095 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 4,686.000 7,540.000 .120 904.80 0095 0666 ADJ EST QUANTITY TO DATE 7,540.000 0100 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 44,809.000 42,880.000 .100 4,288.00 0100 0666 ADJ EST QUANTITY TO DATE 42,880.000 0105 0672 REFL PAV MRKR TY II-A-A EA 797.000 874.000 2.480 2,167.52 0105 0672 ADJ EST QUANTITY TO DATE 874.000 0110 3035 BLADE LEVEL UP (LIMESTONE ROCK ASPH) TON 4,818.000 5,881.200 43.650 256,714.38 0110 3035 ADJ EST QUANTITY TO DATE 5,881.200 0115 0666*REF PAV MRK TY II (W) 24" (SLD) LF 9.000 9.000 6.250 56.25 0 SUBTOTAL BID ITEMS $ 288,821.79 0 TOTAL AMOUNT WORK DONE BLADE LEVEL UP CONTRACT $ 288,821.79 0 TOTAL AMOUNT WORK DONE CONTROL 6194-81-001 $ 288,821.79 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6092201 MGR.NO. 003 PAGE 001 CONT 6194 SEC 81 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 619481001 HWY FM0469 1817 BOB BULLOCK LP LARED CNTY LASALLE DIST 22 CONTRACT PRICE $ 243,511.48 REPORT DATE 08/31/2009 16.54.15 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 15,2009 TO AUG 01,2009 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - RM 450+1.50 0 RM 458+1.60 DATE WORK BEGAN JUL 15, 2009 WORKING DAYS USED 10 PERCENT COMPLETE 100.00 PERCENT TIME USED 50.00 DATE COMPLETED AUG 1 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6194-81-001 RMC - 619481001 22 FM0469 LASALLE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0134 BACKFILL (TY B) STA 347.000 401.280 28.000 11,235.84 0134 ADJ EST QUANTITY TO DATE 401.280 0500 MOBILIZATION LS 1.000 1.000 10,000.000 10,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 2,815.000 2,815.00 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 3,655.000 640.000 1.000 640.00 0662 ADJ EST QUANTITY TO DATE 640.000 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 4,686.000 7,540.000 .120 904.80 0666 ADJ EST QUANTITY TO DATE 7,540.000 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 44,809.000 42,880.000 .100 4,288.00 0666 ADJ EST QUANTITY TO DATE 42,880.000 0672 REFL PAV MRKR TY II-A-A EA 797.000 874.000 2.480 2,167.52 0672 ADJ EST QUANTITY TO DATE 874.000 3035 BLADE LEVEL UP (LIMESTONE ROCK ASPH) TON 4,818.000 5,881.200 43.650 256,714.38 3035* ADJ EST QUANTITY TO DATE 5,881.200 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00666* REF PAV MRK TY II (W) 24" (SLD) LF 9.000 9.000 6.250 56.25 1 SUBTOTAL BID ITEMS $ 288,821.79 0 CONTRACT TOTAL ALL ITEMS $ 288,821.79 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6092201 MGR.NO. 003 PAGE 001 CONT 6194 SEC 81 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 619481001 HWY FM0469 1817 BOB BULLOCK LP LARED CNTY LASALLE DIST 22 CONTRACT PRICE $ 243,511.48 REPORT DATE 08/31/2009 16.54.15 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 15,2009 TO AUG 01,2009 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 142 RMC - 619481001 6194-81-001 288,821.79 .00 288,821.79 .00 .00 288,821.79 287,765.54 1,056.25 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 288,821.79 .00 288,821.79 .00 .00 288,821.79 287,765.54 1,056.25 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6092201 MGR.NO. 003 PAGE 001 CONT 6194 SEC 81 JOB 001 RES ENGR MARTINEZ, NELDA PROJ RMC - 619481001 HWY FM0469 1817 BOB BULLOCK LP LARED CNTY LASALLE DIST 22 CONTRACT PRICE $ 243,511.48 REPORT DATE 08/31/2009 16.54.15 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD JUL 15,2009 TO AUG 01,2009 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6194-81-001 RMC - 619481001 22 FM0469 LASALLE -LIMITS - RM 450+1.50 RM 458+1.60 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 80 0500 MOBILIZATION LS 1.000 0.100 10,000.000 1,000.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 115 0666* REF PAV MRK TY II (W) 24" LF 0.000 9.000 6.250 56.25 (SLD) 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 1,056.25 0 TOTAL AMOUNT WORK DONE TO DATE - $ 288,821.79