1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8082234 MGR.NO. 005 PAGE 001 CONT 6184 SEC 45 JOB 001 RES ENGR MARTINEZ, NELDA PROJ SUP - 618445001 HWY SH0255T 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 6,061.14 REPORT DATE 03/11/2010 09.24.32 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO JUN 12,2009 EST NO 010 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2008 TIME COMPUTED FROM SEP 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 273 273 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 06/12/09 3 1 DAYS CHARGED TO DATE = 283 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 WORK COMPLETED CERTIFIED AS CORRECT AND 12 1 WORK COMPLETED AND ACCEPTED ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 285 283 2 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8082234 MGR.NO. 005 PAGE 001 CONT 6184 SEC 45 JOB 001 RES ENGR MARTINEZ, NELDA PROJ SUP - 618445001 HWY SH0255T 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 6,061.14 REPORT DATE 03/11/2010 09.24.32 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO JUN 12,2009 EST NO 010 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 DIST. 22 COUNTY WEBB CONTROL 6184-45-001 PROJECT SUP - 618445001 HIGHWAY SH0255T 0LIMITS- SH 255T SH 255T 0TYPE OF WORK- LANDSCAPING MAINTENANCE SERVICE AT CCTR 0 0050 LANDSCAPING SERVICE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY NPM 9-1-08 0 0075 0751 PLANT BED MAINTENANCE (SITE A) CYC 1.000 0.000 6,061.140 .00 0075 0751 ADJ EST QUANTITY TO DATE 0.000 0080 9000*MOWING, EDGING & TRIMMING MAINTENANCE CYC 9.000 9.000 673.460 6,061.14 0 SUBTOTAL BID ITEMS $ 6,061.14 0 TOTAL AMOUNT WORK DONE LANDSCAPING SERVICE $ 6,061.14 0 TOTAL AMOUNT WORK DONE CONTROL 6184-45-001 $ 6,061.14 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8082234 MGR.NO. 005 PAGE 001 CONT 6184 SEC 45 JOB 001 RES ENGR MARTINEZ, NELDA PROJ SUP - 618445001 HWY SH0255T 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 6,061.14 REPORT DATE 03/11/2010 09.24.32 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO JUN 12,2009 EST NO 010 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 0*********************************************************************************************************************************** -LIMITS - SH 255T 0 SH 255T DATE WORK BEGAN SEP 1 , 2008 WORKING DAYS USED 283 PERCENT COMPLETE 100.00 PERCENT TIME USED 77.50 DATE COMPLETED JUN 12 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6184-45-001 SUP - 618445001 22 SH0255T WEBB 0000 9.000 9.000 6,061.14 0 SUBTOTAL BID ITEMS $ 6,061.14 0 CONTRACT TOTAL ALL ITEMS $ 6,061.14 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8082234 MGR.NO. 005 PAGE 001 CONT 6184 SEC 45 JOB 001 RES ENGR MARTINEZ, NELDA PROJ SUP - 618445001 HWY SH0255T 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 6,061.14 REPORT DATE 03/11/2010 09.24.32 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO JUN 12,2009 EST NO 010 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 240 SUP - 618445001 6184-45-001 6,061.14 .00 6,061.14 .00 .00 6,061.14 6,061.14 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 6,061.14 .00 6,061.14 .00 .00 6,061.14 6,061.14 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8082234 MGR.NO. 005 PAGE 001 CONT 6184 SEC 45 JOB 001 RES ENGR MARTINEZ, NELDA PROJ SUP - 618445001 HWY SH0255T 1817 BOB BULLOCK LP LARED CNTY WEBB DIST 22 CONTRACT PRICE $ 6,061.14 REPORT DATE 03/11/2010 09.24.33 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 01,2008 TO JUN 12,2009 EST NO 010 & FINAL WORLD TECHNICAL SERVICES, INC. 09518 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6184-45-001 SUP - 618445001 22 SH0255T WEBB -LIMITS - SH 255T SH 255T - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 6,061.14